CA1294054C - Method and system for scheduling, monitoring and dynamically managing resources - Google Patents

Method and system for scheduling, monitoring and dynamically managing resources

Info

Publication number
CA1294054C
CA1294054C CA000576881A CA576881A CA1294054C CA 1294054 C CA1294054 C CA 1294054C CA 000576881 A CA000576881 A CA 000576881A CA 576881 A CA576881 A CA 576881A CA 1294054 C CA1294054 C CA 1294054C
Authority
CA
Canada
Prior art keywords
resources
utilization
indicia
conflict
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CA000576881A
Other languages
French (fr)
Inventor
William R. Rassman
Bradley M. Berman
Scott Blau
Andrew Chiang
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IntelliMED Corp
Original Assignee
IntelliMED Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=22254786&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=CA1294054(C) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by IntelliMED Corp filed Critical IntelliMED Corp
Application granted granted Critical
Publication of CA1294054C publication Critical patent/CA1294054C/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06314Calendaring for a resource
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G16INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR SPECIFIC APPLICATION FIELDS
    • G16HHEALTHCARE INFORMATICS, i.e. INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR THE HANDLING OR PROCESSING OF MEDICAL OR HEALTHCARE DATA
    • G16H40/00ICT specially adapted for the management or administration of healthcare resources or facilities; ICT specially adapted for the management or operation of medical equipment or devices
    • G16H40/20ICT specially adapted for the management or administration of healthcare resources or facilities; ICT specially adapted for the management or operation of medical equipment or devices for the management or administration of healthcare resources or facilities, e.g. managing hospital staff or surgery rooms

Abstract

ABSTRACT OF THE DISCLOSURE

The invention relates to the method for the prospective scheduling, periodic monitoring and dynamic management of a plurality of interrelated and interdependent resources using a computer system. The method includes providing a data base containing information about the resources and graphically displaying utilization and availability of the resources as a function of time. Indicia can be made to appear on the display to provide visual identification of symbols as well as information about scheduling, status and conflicts involving the resources. In addition, access to the data base can be made available to provide a continuous update of the display so that the display of the resources is for the most recent data in the data base. Access to the data base can also permit the operatior to call up a wide variety of information about the resources and can also be used to track events and procedures.

Description

METHOD AND SYSTEM FOR SCHEDULING, MONITORING AND DYNAMICALLY MANAGING RESOURCES

Field of Invention The invention relates to a method for managing resources and particularly to the method and system for the prospective scheduling and real time dynamic management of a plurality of interdependent and interrelated resources using a computer system for communicating information.

Backqround of the Invention Many different fields require the management of resources in order to carry out programs and schedule activities ~; effectively and efficiently. For example, the construction of a building requires scheduling the use of general and specialized personnel, of particular pieces of equipment and of delivery vehicles, In addition, a number of these resources may have to be shared with other construction projects at other sites. It also involves managing the rescheduling of the use of those resources as time passes and events unfold, often not in accordance with the original schedule.
:
::

`' :
:
... .... -~`

t-`~
Similarly, the efficient and effective use of surgical operating rooms in a hospital requires coordinating the use of numerous different resources, usually requiring collecting and gaining access to and then making use of information derived from many different sources. Some of the resources which must be managed and coordinated in a surgical suite or wing include the operating rooms, the surgeons, the anaesthesiologists, the residents, the nurses, the technicians, specialized pieces of equipment and the like.

In the last decade, there has been a significant increase in the use of computers and computer display systems for accessing and displaying data. For example, U.S. Patent lS No. 3,725,650 discloses a method and arrangement for visually representing industrial management data. This patent teaches the use of a computer display for representing data in the form of bar-graphs or pie-graphs. The displays are for past and real time data .~0 and do not include projections into the future. In addition, each graph is independent of each other graph so that the i~pact of a change in one will not affect another. There is no suggestion in this patent that the method therein disclosed could be used for prospective or dynamic management of the utilization of resources.
.

U.S. Patent No. 4,646,238 relates to a computerized system for planning the testing and grading of products as part of a manufacturing process. This patent does not disclose any system for prospectively scheduling the utilization of resources, nor does it disclose any method for monitoring actual utilization of resources, nor does it disclose a system where scheduling conflicts are noted.

35 U.S. Patent No. 4,547,851 relates to interactive communications systems used in restaurants for processing ' ' . ~
food orders by patrons and for making entertainment, like video games available to patrons. It does not relate to resource scheduling, either prospectively or dynamically.

U.S, Patent No. 4,591,983 discloses a hierarchical knowledge system and does not appear to pertain at all to scheduling of interrelated and interdependent resources.

U.S. Patent No. 4,336,589 discloses a method and system for monitoring and controlling the flow of articles in a warehouse. It is designed primarily to keep track of orders and of the articles ordered as they are taken from stock and prepared for shipment. There is no suggestion that such a system could be used for resource scheduling, management or monitoring.

Project planners which employ computers are also well known. Such project planners most commonly are task or activity focused. They are designed primarily for sequential scheduling of related tasks. For example, if a construction project must proceed through six phases, and phase 2 cannot begin until phase 1 is 2/3 complete, and phases 3, 4 and 6 each must await completion of the preceding phase, but phase 5 can begin simultaneously with phase 4, a project planner could be used to set up the schedule at the outset and to adjust that schedule to reflect slippages as they occur~ Project planners, however, are not well equipped to manage the resources employed in the various activities or to alert the operators to the need to adjust the scheduled activities in response to other demands upon those resources.

The management of resources, utilization of which can change in time and can have complex interrelationships, can present serious problems to effective scheduling of the use of those resources and the tasks or activities in .

12~9~Ci$~ ~
which they are employed. Inefficient and particularly incompatible solutions to these problems can be very costly in a manufacturin~ setting, in the construction of a building and elsewhere. Inappropriate solutions to such problems become far more serious when they involve medical facilities and the performance oE surgery because they can then present life and death issues.

What is needed is an effective display o~ at least some of the available resources as a function of time associated with a data base of information relating to displayed resources and perhaps to others as well. In addition, such a system should, most advantageously, be capable of being accessed in order to produce additional displays relating to additional resources. In one of its more general forms, such a syætem should permit changing the time scale to accommodate widely diverse applications. Most desirably, it should also be able to display short range as well as long range projected (and/or historical) utilization without distorting relationships between displayed data when going rom short to long range or vice versa.

Additionally, and, in some settings, most importantly, the system should be capa~le of showing interrelationships between resources so that changes in utilization of one or more resources, reveal the impact of those changes upon the availability and utilization of other resources as well as upon anticipated future utilization o~ the same resource and upon the activities in which they are employed.

Summary of the Invention The present invention provides a method of prospectively planning utilization of a multiplicity of related resources 3~25~ 5~L

using a computer having a memory, including the steps of:
creating a data base of information about at least some of said resources; identifying some of said resources as being primary, and other resources as being secondary;
establishing temporal relationships between at least some of said resources; prospectively scheduling utilization of at least some of said primary resources and at least some of said secondary resources; determining whether any of said scheduled utilizations of one of said resources is incompatible with the scheduled utilization of the same or another resource; communicating, by means of conflict indicia, the existence of any said incompatible scheduled utilizations.

From another aspect, the present invention provides the method of prospectively planning utilization of a multiplicity of related resources using a computer having a memory, including the steps of: creating a data base of information about at least some of said resources; including in said data base permissible and impermissible uses of at least some of said resources; prospectively scheduling utilization of at least some of said resources; searching said data base to determine if any of said scheduled utilizations constitutes an impermissible use;
communicating, by means of conflict indicia, said impermissible scheduled utilizations.

The present invention also provides a system for prospectively planning utilization of a multiplicity of resources, at least some of which are interrelated, comprising: a computer having a memory; a data base stored in said memory containing information about at least some of said resources; a set of primary resources and a se~ of : secondary resources; scheduling means for prospectively scheduling utilization of at least some of said primary resources as a function of time; means for comparing at least one of said scheduled utilizations with at least one other scheduled utilization or with information in said data base, to detect incompatibilities; and means for communicating, ~y use of conflict indicia, the existence of detected incompatibilities.

The present invention also provides a sys~em for prospectively scheduling, periodic monitoring and managing utilization of a plurality of resources, at least some of which are interrelated, comprising: a computer having a memory; a data base stored in said memory, containing information about at least some of said resources; a set of primary resources and a set of secondary resources;
scheduling means for prospectively scheduling utilization of at least some of said primary resources as a function of time; means for communicating at least some of said prospectively scheduled utilization information through use of scheduling indicia; means for comparing at least one of said scheduled utilizations with at least one other scheduled utilization or wi~h information in said data base to detect incompatibilities; means for communicating, by use of conflict indicia, the existence of detected incompatibilities; means for collecting information about actual utilization of at least one of said primary resources subsequent to the first scheduled use of a resource; means for modifying at least one of said scheduled utilizations to reflect variances between said actual utilization and said prospectively scheduled utilization.

Of course, not every application of this invention will necessarily incorporate all of the above features. It is anticipated that some applications will have need for only ,~

~2~

- 6a -some of the features and other, more complex or more sophisticated or more automated applications will make use of more of the features contemplated by the instant invention.

Brief Description of the Drawinas A description of the invention will be given in connection with the drawings which include:

Fig. 1 shows a prospective display of scheduled resources in accordance with the invention.

Fig. lA shows one of the cells from Fig. 1 after the first milestone has been completed.

Fig. lB shows one of the cells of Fig. 1 with the identifying label having been moved to above the cell to denote that the patient is in the room.

Fig. lC shows the same information as in Fig. lA, but using a different means to indicate completion of milestone 1.

Fig. lD shows the same cell as Fig. lA, but at a later point in time, after the second milestone has been passed.

Fig. lE shows a cell in which a circle or clock face is used to display status indicia.

Fig. 2 shows the schedule of Fig. 1 as a dynamic display, modified in accordance with the present invention ~y events as they have occurred.

Fig. 3 shows the schedule of Fig. 1 after completion. It is an historical record generated in accordance with the present invention, showing not only what took place, but also how reality varied from projected utilization.

Fig. 4 shows an alternative method for graphically displaying scheduling information while simultaneously displaying in textual form, information about the scheduled resources.

Fig. ~ shows the display of Fig. 4 at a later point in time.

Fig. 6 shows a display of a prospective schedule of industrial projects in accordance with the invention.

Fig. 7 shows an dynamic display of the schedule of Fig. 6, modified to take into account some events as they have occurred.

Fig. 8 shows a reconfigured display of some of the information appearing on Fig. 1.

Fig. 9 shows a display wherein a pop-up window, overlayed upon the display of Fig. 1, shows information about case klm.

Discussion of the Invention The method according to the invention enables dynamic control of a complex project involving a plurality of resources which are interrelated and which can change with time, Preferably, the method ut lizes a display system such as the type associated with a personal computer and a keyboard ~or selectively changing the display. In addition, a data base containing data relating to the resources can be made available. The data base can be updated from one or more real time sources and this in return can result in an update of the data being displayed. The keyboard can also be used to input data to the data base and to do prospective scheduling. The data preferably is displayed graphically as a function of time to pcrtray the temporal relationships between various resources, activities and events.

Inputting, modifying, handling and accessing of the data can be carried out using known methods and techniques.
Similarly, generating appropriate graphical displays can be done by using well known techniques.
~:
There are numerous situations which can effectively be managed by the use of the instant invention. One such situation is monitoring and planning the use of the facilities and other resources available in the surgical suite of a hospital. Each operating room represents a resource and information can be provided in the data base about each operating room. For example, some operating rooms may be limited to ambulatory procedures, some may be :~ ~ specifically designed and equipped for open heart surgery, some may require only 15 minutes for clean up between procedures and others might need 20 minutes. Some specialized pieces of equipment may be limited to use-in only some of the operating rooms. Some equipment may require long periods of sterilization between procedures, while others require none. Also, some resources may be unavailable because of construction, repair or maintenance activities. If the particular application calls for a rule-based system (as will be discussed below), the applicable rules would normally be in the knowledge or data base. Preferably, all such information would be included in a primary or semi-permanent data base.

The primary data base could also include standard information about certain known activities or procedures.
For example, it may include information like: an a Dendectomy should be scheduled to take 90 minutes, requires that medications A, B, C and D be available, that only operating rooms X, Y and Z are suita`ole for such a procedure and that only doctors J, K and L are authorized to perform such operations.

A supplemental, or transitory data base, preferably integrated with the primary data base, can also be employed to store information more frequently changed than the information in the primary data base. The transitory data base could include information about the planned utilization of a given resource on a particular day or at a particular time. Tasks or procedures waiting to be scheduled could also be in the transitory data base. It could also include relevant information about a particular patient (e.g., name, doctor, procedure to be performed, allergies) who is scheduled for surgery. If anything in the planned utilization is incompatible with information in either the primary or secondary data base, a conflict indicator can be made to appear on the display or on audible signal given. For example, if the procedure is schedule for a room in which construction is going on, a conflict indicator would be displayed. Similarly, if the patient is allergic to medication that is called for, a conflict indicator would alert the operator of the system to the problem.

Each surgical operating room has a planned use in time and the intended use may be associated with a particular patient, pieces of equipment and procedure, as well as key personnel who will be involved in performing the operation and the medication to be administered.

Each surgeon also represents a resource and the surgeon's prior commitments may be important for determining the availability of the surgeon for other surgical operations or in case of an emergency. In the same way, a patient can be regarded as a resource and the planned locations and activities of the patient can be displayed so that the patient can easily be located. Similarly, pieces of eauipment and key personnel can be treated as resources.
All this information would normally be put in the supplemental data base and would then be searched along wi~h the primary data base, each time a resource is : scheduled for use and each time a schedule is modified.

As can readily be appreciated, it is not unusual for the actual time taken to complete a particular procedure to vary from the scheduled or anticipated time. If ~he actual time exceeds the projected time, such information should be readily available in order to determine if alternate arrangements must be made. For example, such a deviation could affect subseguent scheduled use of the operating room. In addition, the extended involvement of the patient, the surgeon, key personnel and particular pieces of equipment could have an impact on other surgical procedures which have been planned for that surgeon, those personnel and those pieces of equipment. It could also affect other procedures that might have been scheduled for that patient.

~z~

As used herein, a "resource" in the hospital setting could be a room, a person, a piece of e~uipment, or the like.
In other settings, "resources" could include containers, vehicles, supervisors, workers units of goods, blocks of time, dollars, aircraft, boarding gates, pilots and the like. Some resources may be reusable, others may be subject to depletion, and still others may be renewable.
Generally, a resource has a known and/or anticipated availability and can be related to one or more other resources as a function of time or as a function of some other consumption, depletion or saturation. As those skilled in the art will readily appreciate, consumption, depletion, saturation and the like are analogous to time in that each can be used as a measuring yardstick. ~or example, a work day can be viewed as consisting of 32 fifteen minute blocks of time during which activities can be scheduled and resources used. Similarly, a reservoir of 2000 items may be viewed as consisting of 500 groups of ; 4, with various activities and resources scheduled for utilization as different groups of 4 are consumed. The term "time," as used herein, should be understood in its broadest sense and not limited to measurements based upon rotations of the earth.

The availability and utilization of resources can be displayed as a function of time by use of "scheduling indicia". Progress of a planned procedure can be monitored and displayed by use of "Status indicia."
Incompatible scheduling of resources can be signalled by the displaying of "conflict indicia." Any of the several indicia, scheduling, status or conflict, described herein, can be displayed in a myriad of ways, including color changes, color bars, shadings, alphanumerics and the like, and combinations thereof. The several indicia can also be displayed by the use of highlighting, geometric symbols, flashing, and/or enhancements such as a brightened frame around data~

While the operator of the system can select certain resources for primary display purposes, the system monitors utilization, not only of the displayed primary resources but also of other or secondary resources which may or may not appear on the display, but which are used in conjunction with the displayed primary resources. To illustrate, the operator may choose to display "operating rooms" as the primary resources. One of those operating rooms, 0, however, may require surgeon S, anaesthesiologist A, heart/lung machine H and heart monitor M. Resources S, ~, H and M may be referred to as secondary resources. If the procedure scheduled for room O ta~es longer than expected, the system will display conflicts, not only with respect to the primary resource, operating room 0, but also with respect to scheduled utilization of the secondary resources, surgeon S, anaesthesiologist A, heart/lung machine H and monitor M.
; The system can, of course, be so configured as to suppress one or more of these indicia.

In using the system of the instant invention, the operator collects information from various sources concerning needs or requests for use of the resources. In the context of a hospital surgical suite this might involve requests from surgeons for operating rooms, for pieces of equipment, perhaps or particular staff members and for other physicians, such as anaesthesiologist's. Each surgeon would identify the procedure to be performed, the anticipated time to complete the procedure, patient information and other relevant data. Other information might also be supplied, such as other commitments of involved personnel.

~9~

The operator loads this information into the data base in any conventional manner and then proceeds to schedule the various resources. If an attempt is made to set up a schedule that involves apparently inconsistent or incompatible use of a given resource, a conflict indicator would be displayed. Having thus been alerted, the operator would then either revise the proposed schedule or determine whether the conflict is real or only apparent.

~o illustrate t~e difference between real and apparent conflicts, consider the situation of a surgeon employing a new procedure which only a few people have been trained to use. The new and unique aspect of the overall surgery . may take only 30 minutes of an anticipated 3 hour surgery. The other steps to be performed, e.g., opening the patient in preparation for the critical procedure, stabilizing the patient on the heart/lung machine and closing the wound after the new procedure has been completed, could be performed by other surgeons.
Nevertheless, since the operatlng room would normally be assigned to the primary surgeon for the entire 3 hour period, the system would display a conflict indicator if that primary surgeon were scheduled elsewhere during any part of those 3 hours. In the real world, however, that surgeon's personal presence might only be required for 30 minutes, thereby allowing him to discharge other duties during the remaining 2-1/2 hours when the operating room is being used in his name.

Recognizing that some conflicts may be real and others only apparent, the system and method of the present invention can be made to recognize different kinds of conflicts, some which it "knows" are irreconcilable, some which it "knows" are susceptible of accommodation and some which it is unable to "recognize" as falling in either category. Each type of conflict could be indicated by its own unique conflict indicia. With that kind of information displayed, the operator can tell whether to reschedule resources immediately or whether to check further to see if a real conflict exits.

After collecting and usually, but not necessarily, after loading the relevant information into the data bank, the operator decides which resources are to be `'primary" for display purposes and which are to be `'secondary". In the hospital setting the operator may select "operating rooms'`
for display as the primary resources. Alternatively, "surgeons" or "heart/lung machines" or "CT scanners" or "nuclear magnetic imagers" etc. or some combination thereof might be chosen.
Assume, for illustration purposes, "operating rooms" is selected for display as the primary resources. Initiallv, the screen will display only the two axes -- time (down the left margin), and operating rooms (across the top as column headings). Although at the outset the remainder of the display would normally be blank, it need not be. For example, for each unscheduled block of time the display can be made to show "open`' or some equivalent designation. Also "repair" may be used to reflect that a particular room is not available for scheduling.
Designations such as "repair,`' "construction" `'sabatical"
could be made to appear automatically as long as the requisite information has been stored in the data base.

The operator would then proceed to prepare a schedule, beginning with '`Case abc'` for operating room 1. The operator could schedule that case to begin at 7:00 a.m.
and to end at 8:45 a.m. Or, if the information as to "Case abc'` had already been loaded into the data base, once the starting time had been selected, an automatic search of the data base could cause the system to .

calculate and display the end point. In ei~her case, a scheduling indicator would be displayed to reflect utilization of the primary resource, in this instance, "Rm l". In Fig. l, the vertical rectangle, labeled "Case abc" is the scheduling indicator. In similar fashion, the remaining operating rooms could be scheduled and scheduling indicia displayed. As long as nothing is planned for one of the primary resources at a particular time, the blanX screen or "open" at that location would constitute the scheduling indicator.

During the scheduling of the primary resources, the system can be made to monitor conflicts in utilization involving primary as well as secondary resources. If such conflicts are detected, a conflict indicator will be dis~layed. mhe conflict could involve only primary resources, e.g. two procedures scheduled for the same operating room at the same time. In that event, the operator would be able to detect the nature o the conflict on the display.
However, the conflict could involve secondary resources, some of which may not appear on the display. In that event, the operator would be alerted to look for the conflict among the secondary resources. Alternatively, by use of color, shading, shape positioning or the like, the conflict indicia itself can identify the secondary resource which is the source of conflict.

On the display, a scheduling indicator showing planned or actual use of a particular primary resource during a given block of time can be referred to as a "cell", On Fig l the rectangle showing that "Case abc" is scheduled for Room l from 7:00 to 8:45 a.m. would be a "celll'. Each cell could be given a title which could be made to appear above the cell or within its confines. Space permitting, a cell could also be made to have several pieces of data relating to secondary resources displayed therein. For 94OEr;~

example, within the cell that represents "Case abc" the name of the surgeon or the type of equipment being employed could be displayed.

In the event it is decided to display secondary resources within cells, such secondary resource displays could be used to indicate conflicts. For e~ample, if Doctor S were scheduled simultaneously in two operating rooms, the display of Doctor S as a secondary resouece in either or both of those cells could be made to flash. Such flashing would, in that embodiment, constitute the conflict indicia.

The display of secondary resources could also be employed to make additional options available. For example, instead of having to go through a menu, simply by moving the cursor to one of those displayed secondary resources, the system could be made to display a window with that secondary resource's schedule or other information about that secondary resource. Such a window is shown in Fig. 9.

Thus, the system need not be menu-driven. The use of shortcuts, such as displays of secondary resources within cells, may avoid the use of menus. However, in the more complex and/or more sophisticated applications of the instant invention, it is unlikely ~hat sufficient short-cuts can effectively be used so as to avoid all use of menus.

In the displays illustrated in Figs 1 through 3 and 6 through 8, along the Y axis time is shown running from top to bottom, and along the X axis the primary resources are shown. As will readily be understood, which resources to display, and along which axis is a matter of choice and convenience. Similarly, the time intervals can be selected to match the needs of the application. Moreover, ::

as illustrated in Figs. 4 and 5 those time intervals need not even be displayed.

Turning now to Fig. 1, the display depicts a mixture of resources and their availability in time. The resources are labeled across the top using abbreviations in which "Rm`' is room, "Doc" refers to a medical surgeon, "Mic"
refers to a particular type of apparatus, namely a microscope and "Res" refers to some other piece of equipment.

The time is shown at the left in Fig. 1, starting with 07:00, based on a 24-hour clock. It is usually most convenient to have all of the primary resources in a display of the same type, such as rooms. However, such uniformity is not essential. As can be seen, the primary resources selected for display in Fig. 1 are of three different types. The primary resources in the first three columns, "Rm 1", "Rm 2", and "Rm 3", are of one type, but the the primary resources of the last three columns, are of two other types, The primary resource of column 4 is a surgeon and the primary resources of columns 5 and 6 are pieces of equipment.

In Fig. 1, "Rm 1" can be taken to refer to a surgical operating room. At 07:00 in the morning "Case abc" is scheduled to occupy "Rm 1" until 08:45. Thereafter, "Case def" will be in "Rm 1" from 9:00 until 09:45.

Rm 2 has "Case ghi" from 07:00 to 09:30. Rm 3 has "Case klm" from 07:00 to 07:15 which is followed by "Case mno"
from 07:45 to 08:30. "Case prs" follows from 08:45 to 09:00 and then "Case tuv" from 09:15 to 09:45.

While there may be many surgeons involvel, only the ~;~ activities of the surgeon "Doc a" are shown. "Doc a" will be in Rm 3 from 7:00 to 7:15, involved in "Case abc" from 7:45 ~o 8:15 and in Rm 4 (not displayed) from 9:00 to 9:45. `'Mic x" will be used by "Doc a" from 7:00 to 7:15, will be used for "Case mno" from 7:45 to ~:15 and will be in room 1 from 8:45 to 9:45. Also, the resource "Res y"
will be used for "Case abc" from 7:00 to 7:15 (even though "Case abc" will continue long after 7:15) and will then be moved for use in "Case ghi" (already in progress) from 7:30 to 8:00. Resource "Res y" is then shown as being assigned to "Case def" from 8:15 to 9:30. Although "Case def" is not scheduled to begin until 9:00, keeping "Res y"
available for that case from 8:15 does not necessarily represent a conflict, although it may represent a waste of a valuable asset. Depending upon the needs of the particular application, such scheduling of "Res y" could, ~ut need not, trigger the display of a conflict indicator.

In Fig. 1, "Case abc" is scheduled from 7:00 to 8:45.
"Doc a" is scheduled to be invol~ed in that case, but only from 7:45 to 8:15. He is also scheduled for "Rm 3" ("Case klm") from 7:00 to 7:15. If "Case abc" is Doc a's case, then when the operator tried to schedule him for Rm 3 ("Case klm") from 7.00 to 7:15 a conflict indicator would have been displayed. The operator would then have checked, determined that Doc a was needed in Rm 1 ("Case abc") only from 7:45 to 8:15 and then overridden or suppressed the conflict indicator.

The display in Fig. 1 represents the results of a prospective scheduling of activities and has been presented for a predetermined time period. Revising the time scale (from 15 minute to 30 minute intervals, for example) will allow the operator to see further into the future but will result in the size of the scheduling indicia to be physically reduced. The distances between cells under each resource will also shrin~ so that ~29~

resolution of adjacent cases in ti.me may not be discernible. Such shrinking of the time scale will also permit less information, for example, about secondary resources, to be displayed within each cell.

Time scale compression may also trigger conflict indicia.
For example, if the scale of Fig. l were changed from 15 minute intervals to one hour intervals, conflict indicia would be displayed between several of the cells, including 1~ "Case abc" and "Case def" in Rm. 1. Each cell would be occupying a portion of the time block 8:00 to 9:00.

The use of conflict as well as status indicia to communicate data permits communication of multi-dimensional information on a two dimensional display. Some of the data which cause the display of conflict or status indicia may be drawn from the semi-permanent data base, some may be from the transitory data base and some may be from current or real time inputs.
In a hospital surgical wing application, as well as in many other applications to which the instant invention can be put, inclusion of an internal real-time clock would be quite advantageous. For example, such a clock could be used to tell the operator which resources are in use and which ones are available at the time of viewing. It could also enable the viewer to determine where a particular resource, such as "Doc a" is at the present time. In addition, the inclusion of a real-time clock can enable automatic display of conflict indicia.

If timely information is available, status indicia can be used to monitor and display progress of a procedure. The entry of the patient into the operating room could be signalled by use of the identifying label. "Case abc"
could be blue before the patient enters, orange as long as :

the patient is in the room and red after the patient has left. Alternatively, the label could be moved from within the cell to a site just above it to signify that the patient is in the room (Fig. lB). Other status indicia could be used to monitor progress of the surgery. One way to do that would be to have the cell representing the time the patie~t is in the operating room changed progressively as the surgery proceeds toward completion. For example, initially the cell can be changed so that one-quarter of it along its time length is in a contrasting color or distinctive pattern (Fig. lA) to indicate that step 1 has been completed. Another way would be to use alphanumerics, such as "Step 1" in a column occupying the first guarter of the scheduling indicator cell (Fig. lC).
If the label is used to signify entry of the patient, the first column within the cell would be used to indicate completion of step 1 (Fig. lC). Status indicia might also take the form of a clock face, part of which is shaded or colored as the procedure progresses or as time passes (Fig. lE). Moreover, a combination of such indicia could also be used.

When a second milestone or significant stage has been reached, a second status indicator could be displayed. As an example, a second column, 1/4 the width of the cell, could be changed to a contrasting color (Fig. lD).
Additional indicia, for example, additional columns within the cell, could be used to represent other milestones or significant stages during the surgery.
The method of the instant invention, when a real-time clock is incorporated, can be made to display status indicia automatically. To illustrate, "Case abc" (Fig. 1) might involve four major stages. Assume that stage 1 is expected to take twenty minutes, stage 2 thirty minutes, stage 3 forty minutes and stage 4 fifteen minutes. Means, s~

for example, a signal button, can be provided in the operating room to indicate when each stage has been completed. If that button is depressed on or before 7:20 a.m., a status indicator in the form of a vertical bar within cell "Case abc" and occupying 1/4 of that cell, can be made to appear (Fig. lA). However, if the real-time clock reaches 7:21 before the signal button is depressed, that status indicator can be ma.de automatically to begin flashing and to continue flashing until the indicator button is depressed. Such flashing of a status indicator can alert the operator to the fact that the procedure is taking longer than anticipated. With such information in hand, the need for rescheduling can be anticipated before the situation becomes critical.

The real-time clock could also be used for automatic display of conflict indicia. If the signal button in ~m 3 has not been used to signify that "Doc a" has completed his task before 7:45, a conflict indicator can be made to appear because Doc a is scheduled to be in Rm 1 working on Case abc at that time.

Status indicia may, but need not be communicated according to a predetermined sequence. In some procedures se~uencing may not be important with respect to some or all of the stages of the procedure. When sequencing is imperative, the method and system of the present invention can be made to operate in a programmed mode. Each time a milestone is reached, all that the operator need do is depress a button. ~ach button press signals the reaching of t.. e next milestone in a predetermined sequence.

In other applications, however, a manual mode might be more suitable. In the manual mode, the operator, by movement of the cursor or some other mechanism, first identifies the stage or milestone and then signals its completion. Thus, the operator could, in the manual mode, signal completion of stage 3 before stage 2.

Hybrids of the two modes may also be employed. Thus, even in the manual mode, predetermined sequences or rules may be established. For example, it may be necessary that step 3 be completed before step 4 is begun, but steps 1, 2 and 5 may proceed without regard to the timing of steps 3 and 4. Conflict indicia can be made to signal the violation of any sequence rules.

~s can be appreciated, many installations are iikely to want the flexibility of selecting either the programmed mode, the manual mode or the hybrid mode. The present invention readily accommodates such flexibility.

rrequently it is important that a record be kept of what happened and when. This can be accomplished according to the instant invention simply by recording (e.g. in the memory or on a printout) the time when each milestone is reached. Normally, a real time record, using the real-time clock, would be made each time a milestone : signal is sent. However, often, contemporoueous signalling is impossible. For example, during surgery, no one may be free to depress the signal button at the time a milestone is reached. Therefore, the present invention also contemplates means for manual entry of the time when an event occurred. It also contemplates use of appropriate indicia, usually on the historical record, of whether the time recorded was real-time or was manually entered.

The historical record also provides for accountability.
From that record it can readily be determined what sequence was followed, when each milestone was reached and which resources were involved.

- 129~

The system can also be made to take certain actions automatically. For example, if a piece of equipment must be warmed up for a predetermined period of time before use, the method of the instant invention would encompass having the system energize that piece of equipment when a particular milestone in the procedure has been completed.
Similarly, in an industrial setting, the system could automatically cut purchase orders or open molds when certain predetermined milestones are reached.
The method of this invention also contempla~es a rule-based system wherein the detection of certain conflict indicia would cause automatic rescheduling of some resources. To illustrate, assume that in Fig. 1, there must be 15 minutes between completing Case abc and beginning Case def. If a signal has not been sent by 8:50 that Case abc is over, a rule could be established tha~
would automatically reschedule Case def to begin at 9:15.
The rule could also require checking the schedules of all the resources involved in Case der before rescheduling.

If, upon checking those Case def-related schedules no new conflicts are detected, the rescheduling would be done and : notice of the change communicated automatically to the people affected. This could be done, for example, by : having the system call the office of the surgeon scheduled to do Case def and, by use of a voice synthesizer, report the new schedule.

If the rescheduling of Case def is found to provoke other conflicts, the system could be designed so as not to do the rescheduling, but instead merely to give notice of the first conflict. That notice could be by means of a visual display, by the sounding of a distinctive note or the like. Another possibility would be to have the system try : .

~Z94~

to reschedule the resources involved in the second tier conflict and only if no conflicts result from that second rescheduling, to proceed to reschedule at both the first and second tiers. Otherwise, the rule would require abandoning the effort to reschedule.

The instant invention also contemplates the use of status indicia to predict unanticipated availability of resources. For example, if stage 2 in "Case abc," not expected to be finished until 7:50, has been completed before 7:40, the status indicator bar (Fig. lA) can be displayed in a different contrasting color. The appearance of such a color bar on the display would alert the operator to anticipate availability of operating room 1 (and the other resources involved in "Case abc") earlier than originally expected.

Fig. 2 represents a dynamic display of information based on real-time information, as contrasted with the static prospective information that is reflected in Fig l. On Fig. 2, the time now is indicated by "(tn)" and an arrow.

Fig. 2 shows a conflict between "Case abc" and "Case def"
for surgical operating room 1, as denoted by conflict indicator C-l. This conflict could have arisen as a result of the operator, reacting to status indicia, revising the anticipated completion time of "Case abc."
Alternatively, it may have been triggered by the passage of time (as indicated by the real-time clock) beyond 8:45 without a signal having been received that "Case abc" has been completed.

It should be noted that the revision of the scheduled completion of "Case abc" also causes a conflict in the schedule of "Doc a" who is supposed to be in "Rm 4" at 9:00. Conflict indicator C-2 reflects that conflict.

.

~2~54 Ideally, conflict indicia would be displayed regardless of which resource or resources are involved. For example, even if the unexpected delay in completing "Case abc" did not cause a conflict in use of Room 1, it may have caused a conflict in the schedule of the anaesthesiologist involved in that case. If the anaesthesiologist's schedule had been placed in the data base, a search of the data base in response to rescheduling of the completion of "Case abc" would reveal that the anaesthesiologist's extended involvement in "Case abc" conflicts with his other obligations. As a result, yet another conflict indicator C-3 would be displayed. Conflict indicator C-3 could be non-specific, in that it would merely reflect the existence of a conflict but not identify the source.
Conflict indicia C-1 and C-2, on the other hand signify not only the existence of a conflict but also identify one or more of the resources involved. Alternatively, C-3 could be ~ade specific by use of color, position, shape etc.

It should be noted that identifiers "Case abc" and "Case ghi" under rooms 1 and 2 have been moved from within the cells to above them to indicate that those cases are currently proceeding in their respective operating rooms.
The identifier "Case abc" under "Doc a" has also been moved to above the cell to reflect that Doc a is currently involved in that case.

Under Rm. 1 on Fig. 2, it can be seen that the scheduled completion time has been changed from 8:45 to 9:15, representing a delay (d) of 30 minutes. The cross-hatching under Rm. 1 shows that Case def, originally scheduled to begin at 9:00, will not begin until 9:30.

The locations of the identifiers under Rm. 3 immediately reveal that Cases klm, mno and prs have been completed and 1~9~0~4 that Case tuv has not yet begun. It can also be seen that Case mno was originally scheduled to end at 8:15 but did not actually end until 8:30.

Still on Fig. 2, under "Doc. a", it can be seen that his involvement in Case abc did not end at 8:15 as planned, ; but is still in progress at the current time and is now : scheduled to end at 9:15.

Finally, it can be seen that Mic. X, initially scheduled to be moved into ~T,. 1 at 8:45, perhaps to permit set-up and calibration in advance of Case def, has not yet been moved in, and is not scheduled for that move until 9:1~.

Fig. 3 is an historical display of how the primary resources were actually used relative to the schedule shown in Fig. 1. In Fig. 3, it can be seen that "Case abc" which had been planned to be completed at 08:45 (dashed line in "Case abc" cell), was not completed until ~20 about 09:05 and "Case def" started immediately thereafter. Conflict indicator C-4 (double cross-hatching) shows that "Case def" did not begin at the time anticipated. Similarly, conflict indicia show that "Doc a" did not begin the procedure in Rm 4 until 9:05 (C-5) because he was delayed by Case abc.
; , .
In the embodiment of Fig. 3, indicia in the form of single cross-hatching, are used to show changes that were made from the prospective schedule. The opposite direction ; 30 cross-hatching of the Case tuv cell denotes a cancelled procedure.

It should be noted that neither Fig. 1 nor Fig. 3 shows a current time indicator. In order to keep the two types of displays from belng confused, some notation would normally ~ be used to differentiate one from the other. One such :

method would be to use one background color for prospective displays and a contrasting background color for historical displays. Such use of contrasting colors could also make superflous a separate current time flag.
On the dynamic display, the passage of time could be shown ~ by having the interface line between the two colors move ; inexorably downward.

The display of Fig. 2 contemplates showing time passing by having the time arrow (tn) move down the screen, with the cells remain stationary. As those skilled in the art will readily appreciate, the time line can be held stationary while the cells move. One such display is reflected on tne left half of Fig. 4. As time passes, the digital clock changes and the cells index upwardly.

Fig. 4 also shows how, in accordance with the instant invention, a graphical display may be combined with and supplemented by a real time textual display. As one cell passes off the screen, the textual display showing current utilization of that resource would automatically change to reflect the new circumstance.

Fig. 4 shows the situation at 8:05. Fig. 5 shows the situation with respect to the same operating rooms at 11:2-5. It should be noted that the time relationships between cells have changed between 8:05 tFig~ 4) and 11:25 (Fig. 5). This has occurred because embedded in the cells in this embodiment are milestone markers (M). The cells stop at each of these milestone markers until indication is received that the milestone has in fact been reached.
~ The cell then resumes indexing upwardly. In this ;~ embodiment, the combination of milestone markers and cell movements constitute the status indicia.

o~

Fig. 6 shows a display of a prospective schedule for the beginning of the month of June 1987 for Projects X and Y
and Resources 123, 223 and 224. Project X has two phases which can be partially overlapping. Project Y has three pnases none of which can overlap. Resources 123, and 223 are used in phases 1 and 2 of Project Y. Resource 224 is used twice during phase 1 of Project X and in phase 3 of Project Y.

Fig. 7 shows the dynamic or actual events as of June 8, 1987 with respect to the schedule shown in Fig. 6. Phase 1 of Project X did not begin on time ar.d ended late. The late ending is indicated by arrow t in the "phase one"
cell. That delay has caused a conflict to arise because Resource 224 cannot be used concurrently in phase 1 of Project X and phase 3 of Project Y. This conflict is indicated by indicia C-6, C-7 and C-8. The time is indicated by a screen background color change. The interface between the two colors is the current time (t ).
Although Project X and Resource 224 used in Project X have been rescheduled on Fig. 7, Project Y phase three and the use of Resource 224 in "Y" three have not yet been rescheduled.
-While some overlap between phases one and two of Project X
was anticipated, the delay in completion of phase one resulted in too great an overlap, and the start of phase two had to be delayed as a result. This is indicated by shading in the Project X, phase two cell.

Fig. ~ shows a display relating to Fig. 1 which has been reconfigured to include additional information about some of the cells.

~4(~

As discussed above, the method and system of the instant invention may be menu driven. The nature of the menus and submenus, the information to which they peemit access and the other functions they make available will vary depending upon the application. Some menus can be used merely to call up information from the data base. Other menus ean be used to modify the display format. How such menus can be used and the kinds of menus whieh ean be made available are as varied as the applieations to which the invention may be applied and the creativity of those who use the invention.

The conventional use of pop-up windows allows additional information to be displayed beyond that which can conveniently be placed on a graphical display. In Fig. g a pop up window has been called up in order to view detailed information concerning a particular case.

The display ean also be used to trace the location of 2 specifie physician or patient. The data base in a hospital system could also allow the display of the availability of other resources, unrelated to the surgical suite. For example, a hospital system could be designed to identify the present and future oceupants of rooms so that individuals eould be easily loeated and timely information retrieved as to availability of rooms.

Although it is antieipated that, at least in the early applieations of the instant invention, inputting of information will normally be through key boards and/or signal switches, it should be understood that the invention is not limited to use of such devices.
Depending upon the particular application, telephone, radio, mierowave, infrared and other deviees and methods of transmitting signals eould be used. In an industrial se'ting where dynamic scheduling depends upon personnel in the field arriving and departing rom a myriad of different locations, telephones or "beepers" could be used to input current information. Similarly, conflict indicia or rescheduling informa~ion could automatically be communicated to field personnel by means of "beepers" or other such devices.

While it is believed that a cathode ray tube display is most suitable for use in practicing the instant invention, the term "display" has been used herein much more generically. Depending upon the particular application, hard copy, e.g., a paper print-out, might be an acceptable display. Similarly, an array of incandescent bulbs might be adequate. Other, more or less sophisticated displays could also be employed.
Finally, the above-described embodiments of the invention are intended to be illustrative only. Numerous alternative embodiments may be devised by those skilled in the art without departing from the spirit and the scope of the following claims.

Claims (97)

1. A method of prospectively planning utilization of a multiplicity of related resources using a computer having a memory, including the steps of:
creating a data base of information about at least some of said resources;
identifying some of said resources as being primary, and other resources as being secondary;
establishing temporal relationships between at least some of said resources;
prospectively scheduling utilization of at least some of said primary resources and at least some of said secondary resources;
determining whether any of said scheduled utilizations of one of said resources is incompatible with the scheduled utilization of the same or another resource;
communicating, by means of conflict indicia, the existence of any said incompatible scheduled utilizations.
2. The method of prospectively planning utilization of a multiplicity of related resources using a computer having a memory, including the steps of:
creating a data base of information about at least some of said resources;
including in said data base permissible and impermissible uses of at least some of said resources;
prospectively scheduling utilization of at least some of said resources;
searching said data base to determine if any of said scheduled utilizations constitutes an impermissible use;
communicating, by means of conflict indicia, said impermissible scheduled utilizations.
3. The method of claim 1 or 2 wherein communication of at least some of said conflict indicia is by means of sound.
4. The method of claim 1 or 2 wherein communication of at least some of said conflict indicia is by means of light, radio waves or other electromagnetic radiation.
5. The method of claim 1 further comprising an optical display and wherein said communication of at least one of said conflict indicia is accomplished by having same appear on said display.
6. The method of claim 2 further comprising an optical display and wherein said communication of at least one of said conflict indicia is accomplished by having same appear on said display.
7. The method of claim 6 wherein said prospectively scheduled utilization is reflected on said display in the form of scheduling indicia.
8. The method of claim 7 further comprising the steps of:
obtaining information representing actual utilization of at least one of said resources at a point in time subsequent to the first scheduled utilization of said resource;
communicating said actual utilization information by having same appear on said display in the form of status indicia.
9. The method of claim 8 further comprising the steps of:

determining whether said actual utilization is inconsistent with any prior scheduled utilizations of any resource;
rescheduling at least one of said inconsistent previously scheduled utilizations.
10. The method of claim 8 further comprising the step of recording said actual utilizations.
11. The method of claim 1 further comprising the steps of:
obtaining information representing actual utilization of at least one of said resources at a point in time subsequent to the first scheduled utilization of said resource;
determining whether said actual utilization is incompatible with any of said temporal relationships or with any information stored in said data base; and communicating, by means of conflict indicia, the existence of any such incompatible utilizations.
12. A system for prospectively planning utilization of a multiplicity of resources, at least some of which are interrelated, comprising:
a computer having a memory;
a data base stored in said memory containing information about at least some of said resources;
a set of primary resources and a set of secondary resources;
scheduling means for prospectively scheduling utilization of at least some of said primary resources as a function of time;
means for comparing at least one of said scheduled utilizations with at least one other scheduled utilization or with information in said data base, to detect incompatibilities; and means for communicating, by use of conflict indicia, the existence of detected incompatibilities.
13. The system of claim 12 further comprising an optically recognizable display.
14. The system of claim 13 wherein at least some of said scheduling information is made to appear, by means of scheduling indicia, on said display.
15. The system of claim 14 wherein at least some of said conflict indicia are made to appear on said display.
16. The system of claim 15 where-n said scheduling indicia reflect planned utilization of at least some of said primary resources as a function of time.
17. The system of claim 16 wherein at least some of said scheduling indicia incorporate information about utilization of at least some of said secondary resources.
18. A system for prospectively scheduling, periodic monitoring and managing utilization of a plurality of resources, at least some of which are interrelated, comprising:
a computer having a memory;
a data base stored in said memory, containing information about at least some of said resources;
a set of primary resources and a set of secondary resources;
scheduling means for prospectively scheduling utilization of at least some of said primary resources as a function of time;

means for communicating at least some of said prospectively scheduled utilization information through use of scheduling indicia;
means for comparing at least one of said scheduled utilizations with at least one other scheduled utilization or with information in said data base to detect incompatibilities;
means for communicating, by use of conflict indicia, the existence of detected incompatibilities;
means for collecting information about actual utilization of at least one of said primary resources subsequent to the first scheduled use of a resource;
means for modifying at least one of said scheduled utilizations to reflect variances between said actual utilization and said prospectively scheduled utilization.
19. The system of claim 18 further comprising means for inputting the actual status of utilization of at least one of said primary resources at a point in time subsequent to the initial planned utilization of at least one of said primary resources.
20. The system of claim 19 further comprising means for collecting information about actual utilization of at least one of said primary resources at a point in time subsequent to the first prospectively scheduled utilization thereof and means for communicating said actual utilization information by use of status indicia.
21. The system of claim 20 further comprising means for comparing said actual utilization of at least one of said primary resources with the prospectively scheduled utilization of said resource and means for communicating, through use of status indicia, the results of said comparison.
22. The system of claim 18 wherein said means for collecting said actual utilization information includes real-time clock means.
23. The system of claim 19 wherein said means for inputting said actual utilization status of resources includes real time clock means.
24. The system of claim 20 wherein said means for collecting information about actual utilization of resources includes real time clock means.
25. The system of claim 18 further comprising means for detecting modification-caused incompatible utilizations and communicating said detected modification-caused incompatibilities by use of conflict indicia.
26. The system of claim 18 further comprising optical display means for displaying at least one of said scheduling indicia or said conflict indicia.
27. The system of claim 20 further comprising optical display means for displaying at least one of said scheduling indicia, said conflict indica or said status indicia.
28. The system of claim 25 further comprising optical display means for displaying at least one of said scheduling indicia, said conflict indicia or said status indicia.
29. The system of claim 18 wherein said modifying means includes means for automatically altering at least one of said scheduled utilizations in response to detection of at least one modification-caused incompatibility.
30. The system of claim 14 wherein at least some of said scheduling indicia appear in the form of a graphical display.
31. The system of claim 15 wherein at least some of said scheduling and conflict indicia appear in the form of a graphical display.
32. The system of claim 28 wherein at least some of said scheduling, conflict and status indicia appear in he form of a graphical display.
33. The system of claim 30, 31 or 32 wherein said graphical display is made to appear concurrently with a textual display of information about utilization of at least some of said primary or secondary resources.
34. The system of claim 13 wherein information stored in said data base about at least one of said resources can be accessed and made to appear on said display.
35. The system of claim 19 further comprising means for recording the time of said inputting of said actual status utilization data.
36. The system of claim 19 further comprising means for recording the time of said actual status utilization.
37. A method of prospectively planning utilization of a multiplicity of related resources using a computer having a memory, including the steps of:
identifying some of said resources as being primary, and other resources as being secondary;
establishing temporal relationships between at least some of said resources;
creating a data base of information about at least one of said resources, at least some of which information is independent of said temporal relationships between resources;
prospectively scheduling utilization of at least some of said primary resources and at least some of said secondary resources;
displaying, in graphical fashion, the prospectively scheduled utilization of at least some of said resources;
determining whether any of said scheduled utilizations of one of said resources is incompatible with any of the information in said data base; and communicating, by means of conflict indicia, the existence of any said incompatible scheduled utilizations.
38. The method of claim 37 wherein said display is a transient optical display and wherein said communication of at least one of said conflict indicia is accomplished by having same appear on said display.
39. The method of claim 38 further comprising the step of displaying status indicia.
40. The method of claim 38 wherein at least two different types of conflict indicia are displayed.
41. The method of claim 40 wherein one of said types of conflict indicia identifies a temporal conflict and another conflict indicia identifies an impermissible use as determined by a search of said data base.
42. The method of claim 40 wherein at least some of said conflict indicia identify the type of conflict involved.
43. The method of claim 38 further comprising the steps of displaying utilization information about at least some primary resources;
displaying utilization information about at least some of said secondary resources; and displaying a relationship between at least one of said primary resources to at least one of said secondary resources.
44. The method of claim 38 wherein there is displayed simultaneously at least one primary resource and at least one secondary resource.
45. The method of claim 38 wherein the display of information is dynamic in that it reflects status information in real time.
46. The method of claim 38 wherein at least one of said conflict indicia identifies a real conflict and at least one other of said conflict indicia identifies an apparent conflict.
47. The method of claim 38 wherein said data base can be interrogated to cause a display of information about at least one of said resources.
48. The method of claim 37 further comprising the steps of:
obtaining information representing actual utilization of at least one of said resources at a point in time subsequent to the first scheduled utilization of said resource;
determining whether said actual utilization is incompatible with any of said temporal relationships or with any information stored in said data base; and communicating, by means of conflict indicia, the existence of any such incompatible utilizations.
49. The method of claim 37 further comprising the step of determining whether any of said scheduled utilizations is incompatible with any of said temporal relationships.
50. The method of prospectively planning utilization of a multiplicity of related resources using a computer having a memory, including the steps of:
creating a data base of information about at least some of said resources, at least some of which data is independent of temporal relationships between resources;
including in said data base permissible and impermissible uses of at least some of said resources;
prospectively scheduling utilization of at least some of said resources;
displaying, in graphical fashion, the prospectively scheduled utilization of at least some of said resources;
searching said data base to determine if any of said scheduled utilizations constitutes an impermissible use; and communicating, by means of conflict indicia, said impermissible scheduled utilizations.
51. The method of claim 37 or 50 wherein communication of at least some of said conflict indicia is by means of sound.
52. The method of claim 37 or 50 wherein communication of at least some of said conflict indicia is by means of light, radio waves or other electromagnetic radiation.
53. The method of claim 50 wherein said display is a transient optical display and wherein said communication of at least one of said conflict indicia is accomplished by having same appear on said display.
54. The method of claim 53 wherein said prospectively scheduled utilization is reflected on said display in the form of scheduling indicia.
55. The method of claim 54 further comprising the steps of:
obtaining information representing actual utilization of at least one of said resources at a point in time subsequent to the first scheduled utilization of said resource;
communicating said actual utilization information by having same appear on said display in the form of status indicia.
56. The method of claim 55 further comprising the steps of:
determining whether said actual utilization is inconsistent with any prior scheduled utilizations of any resource;
rescheduling at least one of said inconsistent previously scheduled utilizations.
57. The method of claim 55 further comprising the step of recording said actual utilizations.
58. The method of claim 50 further comprising the step of communicating at least two different types of conflict indicia.
59. The method of claim 58 wherein one of said conflict indicia identifies a temporal conflict and another of said conflict indicia identifies an impermissible use as determined by a search of said data base.
60. The method of claim 50 wherein said data base is comprised of a permanent or semi-permanent data base and a transitory data base.
61. A system for prospectively planning utilization of a multiplicity of resources, at least some of which are interrelated, comprising:
a computer having a memory;
a data base stored in said memory containing information about at least some of said resources, at least some of which information is independent of temporal relationships between resources;
a set designated as primary resources and a set designated as secondary resources;
scheduling means for prospectively scheduling utilization of at least some of said primary resources as a function of time;
display means for displaying in graphical form, the prospectively scheduled utilization of at least some of said resources;
means for comparing at least one of said scheduled utilizations with at least one other scheduled utilization or with information in said data base, to detect incompatibilities; and means for communicating, by use of conflict indicia, the existence of detected incompatibilities.
62. The system of claim 61 wherein said display means are characterized by being transient.
63. The system of claim 62 wherein at least some of said scheduling information is made to appear in textual form on said display.
64. The system of claim 63 wherein at least some of said conflict indicia are made to appear on said display.
65. The system of claim 64 wherein said scheduling information reflects planned utilization of at least some of said primary resources as a function of time.
66. The system of claim 65 wherein at least some of said scheduling information incorporates information about utilization of at least some of said secondary resources.
67. The system of claim 64 wherein at least some of said conflict indicia appear on said graphical display.
68. The system of claim 61 wherein at least some of said conflict indicia appear on said graphical display.
69. The system of claim 61 wherein at least two different kinds of conflict indicia are employed to communicate the existence of at least two different kinds of incompatibilities.
70. The system of claim 69 wherein at least one of said conflict indicia identifies a temporal incompatibility and at least one other conflict indicia identifies an incompatibility as determined by a search of said data base.
71. A system for prospectively scheduling, periodic monitoring and managing utilization of a plurality of resources, at least some of which are interrelated, comprising:
a computer having a memory;
a data base stored in said memory, containing information about at least some of said resources at least some of which information is independent of temporal relationships between resources;
a set designated as primary resources and a set designated as secondary resources;

scheduling means for prospectively scheduling utilization of at least some of said primary resources as a function of time;
display means for displaying in graphical form, the prospectively scheduled utilization of at least some of said resources;
means for communicating at least some of said prospectively scheduled utilization information through use of graphically displayed scheduling indicia;
means for comparing at least one of said scheduled utilizations with at least one other scheduled utilization or with information in said data base to detect incompatibilities;
means for communicating, by use of conflict indicia, the existence of detected incompatibilities;
means for collecting information about actual utilization of at least one of said primary resources subsequent to the first scheduled use of a resource; and means for modifying at least one of said scheduled utilizations to reflect variances between said actual utilization and said prospectively scheduled utilization.
72. The system of claim 71 further comprising means for inputting the actual status of utilization of at least one of said primary resources at a point in time subsequent to the initial planned utilization of at least one of said primary resources.
73. The system of claim 72 further comprising means for collecting information about actual utilization of at least one of said primary resources at a point in time subsequent to the first prospectively scheduled utilization thereof and means for communicating said actual utilization information by use of status indicia.
74. The system of claim 73 further comprising means for comparing said actual utilization of at least one of said primary resources with the prospectively scheduled utilization of said resource and means for communicating, through use of status indicia, the results of said comparison.
75. The system of claim 73 wherein said means for collecting information about actual utilization of resources includes real time clock means.
76. the system of claim 73 wherein said display means includes means for displaying at least one of said conflict indicia or said status indicia.
77. The system of claim 73 further comprising means for dynamically displaying by use of said status indicia, the status of utilization of at least one of said resources in real time.
78. The system of claim 72 wherein said means for inputting said actual utilization status of resources includes real time clock means.
79. The system of claim 72 further comprising means for recording the time of said inputting of said actual status utilization data.
80. The system of claim 72 further comprising means for recording the time of said actual status utilization.
81. The system of claim 61 or claim 71 wherein said data base is comprised of a semi-permanent data base and a transitory data base.
82. The system of claim 71 wherein said means for collecting said actual utilization information includes real-time clock means.
83. The system of claim 82, 77, or 75 wherein said real time clock means is made to appear concurrently with said graphical display of the prospectively scheduled utilization of at least some of said resources.
84. The system of claim 71 further comprising means for detecting modification-caused incompatible utilizations and communicating said detected modification-caused incompatibilities by use of conflict indicia.
85. The system of claim 84 wherein said display means includes means for displaying at least one of said conflict indicia or said status indicia.
86. The system of claim 71 wherein said display means are characterized by being transient in nature.
87. The system of claim 71 wherein said modifying means includes means for automatically altering at least one of said scheduled utilizations in response to detection of at least one modification-caused incompatibility.
88. The system of claim 71 wherein at least some of said actual utilization information appears on said graphical display.
89. The system of claim 68, 67 or 88 wherein said graphical display is made to appear concurrently with a textual display of information about utilization of at least some of said primary or secondary resources.
90. The system of claim 62 wherein information stored in said data base about at least one of said resources can be accessed and made to appear on said display.
91. The system of claim 71 wherein at least one of said conflict indicia is communicated by graphical display thereof.
92. The system of claim 62 or 91 further comprising means for displaying utilization information about at least some of said primary resources;
means for displaying utilization information about at least some of said secondary resources; and means for displaying a relationship between at least one of said primary resources and at least one of said secondary resources.
93. The system of claim 62 or 91 further comprising means for simultaneously displaying information about at least one primary resource and at least one secondary resource.
94. The system of claim 62 or 91 further comprising means for dynamically displaying on said transient display, status information about the utilization of at least some of said resources in real time.
95. The system of claim 62 or 91 wherein at least one of said conflict indicia identifies a real conflict and at least one other conflict indicia identifies an apparent conflict.
96. The system of claim 62 or 91 further comprising means for interrogating said data base to cause a display of information about one of said resources.
97. The system of claims 62 and 91 wherein at least two different kinds of incompatibilities can be detected and wherein at least some of said conflict indicia identify the nature of the incompatibility associated therewith.
CA000576881A 1987-09-10 1988-09-09 Method and system for scheduling, monitoring and dynamically managing resources Expired - Lifetime CA1294054C (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US07/096,027 US4937743A (en) 1987-09-10 1987-09-10 Method and system for scheduling, monitoring and dynamically managing resources
US096,027 1987-09-10

Publications (1)

Publication Number Publication Date
CA1294054C true CA1294054C (en) 1992-01-07

Family

ID=22254786

Family Applications (1)

Application Number Title Priority Date Filing Date
CA000576881A Expired - Lifetime CA1294054C (en) 1987-09-10 1988-09-09 Method and system for scheduling, monitoring and dynamically managing resources

Country Status (6)

Country Link
US (1) US4937743A (en)
EP (1) EP0306965A3 (en)
JP (1) JP2634070B2 (en)
AU (1) AU622371B2 (en)
CA (1) CA1294054C (en)
IL (1) IL87663A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010066023A1 (en) * 2008-12-12 2010-06-17 Smart Technologies Ulc System for supporting coordination of resources for events in an organization

Families Citing this family (339)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5230066A (en) * 1986-09-19 1993-07-20 Mitsubishi Denki Kabushiki Kaisha Microcomputer
US5133075A (en) * 1988-12-19 1992-07-21 Hewlett-Packard Company Method of monitoring changes in attribute values of object in an object-oriented database
US5208904A (en) * 1989-03-07 1993-05-04 Brother Kogyo Kabushiki Kaisha Data processing apparatus and method for preparing data representative of supplemental figure attached to basic figure reproduced on output medium
US5117353A (en) * 1989-05-05 1992-05-26 Staff-Plus, Inc. System for use in a temporary help business
US5164897A (en) * 1989-06-21 1992-11-17 Techpower, Inc. Automated method for selecting personnel matched to job criteria
DE3925168A1 (en) * 1989-07-28 1991-01-31 Udo Quilitz METHOD FOR ASSIGNING DATA SETS TO TIME VALUES OF A TIMED ORDER
US5233533A (en) * 1989-12-19 1993-08-03 Symmetrix, Inc. Scheduling method and apparatus
US5253340A (en) * 1990-01-19 1993-10-12 Canon Kabushiki Kaisha Data processing apparatus having a graphics device with priority scheduling of drawing requests
US5226120A (en) * 1990-05-21 1993-07-06 Synoptics Communications, Inc. Apparatus and method of monitoring the status of a local area network
US5295065A (en) * 1990-06-01 1994-03-15 Motorola, Inc. Resource-lot association coordinator
US5208765A (en) * 1990-07-20 1993-05-04 Advanced Micro Devices, Inc. Computer-based method and system for product development
JP2527266B2 (en) * 1990-09-10 1996-08-21 富士通株式会社 Scheduling method in knowledge-based system
JP2732711B2 (en) * 1990-12-20 1998-03-30 株式会社日立製作所 Multidimensional information display method and apparatus
US5237497B1 (en) * 1991-03-22 1998-05-26 Numetrix Lab Ltd Method and system for planning and dynamically managing flow processes
JPH0816877B2 (en) * 1991-06-10 1996-02-21 インターナショナル・ビジネス・マシーンズ・コーポレイション Method and system for real-time capture and reduction of resource data for data processing system
JPH0774984B2 (en) * 1991-06-10 1995-08-09 インターナショナル・ビジネス・マシーンズ・コーポレイション System resource utilization measurement method and data processing system
US5278751A (en) * 1991-08-30 1994-01-11 International Business Machines Corporation Dynamic manufacturing process control
JPH05225206A (en) * 1991-10-29 1993-09-03 Internatl Business Mach Corp <Ibm> Method and apparatus for integrating project schedule and resource-planning calendar
US5365360A (en) * 1991-11-15 1994-11-15 International Business Machines Corporation Method and apparatus for presenting information contained within a data icon by assigning attributes to various dimensions of the data icon
US5644692A (en) * 1991-12-06 1997-07-01 Lucent Technologies Inc. Information display apparatus and methods
CA2082848C (en) * 1991-12-06 2000-12-19 Stephen G. Eick Apparatus for selective simultaneous display of information about a plurality of events
JPH05165842A (en) * 1991-12-13 1993-07-02 Toyota Central Res & Dev Lab Inc Estimating device for process time
JPH0683404A (en) * 1992-01-20 1994-03-25 Internatl Business Mach Corp <Ibm> Apparatus and method for customizing schedule display
JPH0756652B2 (en) * 1992-03-24 1995-06-14 インターナショナル・ビジネス・マシーンズ・コーポレイション Search for video frame sequence
US5247438A (en) * 1992-03-30 1993-09-21 Infoassist, Inc. Personal time management system and method
US5659693A (en) * 1992-08-27 1997-08-19 Starfish Software, Inc. User interface with individually configurable panel interface for use in a computer system
US5432932A (en) * 1992-10-23 1995-07-11 International Business Machines Corporation System and method for dynamically controlling remote processes from a performance monitor
US5553235A (en) * 1992-10-23 1996-09-03 International Business Machines Corporation System and method for maintaining performance data in a data processing system
US5506955A (en) * 1992-10-23 1996-04-09 International Business Machines Corporation System and method for monitoring and optimizing performance in a data processing system
US5483468A (en) * 1992-10-23 1996-01-09 International Business Machines Corporation System and method for concurrent recording and displaying of system performance data
US5487144A (en) * 1992-12-01 1996-01-23 Yokogawa Electric Corporation Scheduling system
US5659768A (en) * 1993-01-06 1997-08-19 Forbes; Kenneth S. System and method for the time representation of tasks
US5615138A (en) * 1993-04-08 1997-03-25 Honda Giken Kogyo Kabushiki Kaisha Method for establishing the working mantime in the production line
JPH06342357A (en) * 1993-06-01 1994-12-13 Mitsubishi Electric Corp User interface system
JPH0756754A (en) * 1993-08-03 1995-03-03 Internatl Business Mach Corp <Ibm> Apparatus and method for allocation of multimedia group resource
JPH0757006A (en) * 1993-08-17 1995-03-03 Nec Corp Resource management device
IL106792A (en) * 1993-08-24 1998-02-08 Scitex Corp Ltd Artwork design and production system
DE4329886B4 (en) * 1993-09-06 2012-05-03 Heidelberger Druckmaschinen Ag Sequencing system for printing companies
US5467268A (en) * 1994-02-25 1995-11-14 Minnesota Mining And Manufacturing Company Method for resource assignment and scheduling
US5623404A (en) * 1994-03-18 1997-04-22 Minnesota Mining And Manufacturing Company System and method for producing schedules of resource requests having uncertain durations
IL112660A (en) * 1994-03-31 1998-01-04 Minnesota Mining & Mfg System integrating active and simulated decision- making processes
CA2187181A1 (en) * 1994-04-04 1995-10-12 Supratik Bose Interactive method for operating a computer so as to graphically display the results of a computation
US5590269A (en) * 1994-04-22 1996-12-31 Minnesota Mining & Manufacturing Company Resource assignment system providing mixed-initiative user interface updates
US6801820B1 (en) 1994-05-27 2004-10-05 Lilly Software Associates, Inc. Method and apparatus for scheduling work orders in a manufacturing process
US7647241B1 (en) 1994-05-27 2010-01-12 Infor Global Solutions (Veenendaal) B.V Computer program product for determining and reducing customer service impact
US5787000A (en) * 1994-05-27 1998-07-28 Lilly Software Associates, Inc. Method and apparatus for scheduling work orders in a manufacturing process
US7039595B1 (en) 1998-10-21 2006-05-02 Infor International Limited System and method for throughput measurement
CA2130065C (en) * 1994-08-12 1999-03-02 Michael Joel Cincinatus Utilizing pseudotables as a method and mechanism for providing database monitor information
KR960008583A (en) * 1994-08-26 1996-03-22 윌리암 티. 엘리스 Data Processing Systems and Methods for Managing Data Processing Systems
US7539624B2 (en) * 1994-09-01 2009-05-26 Harris Corporation Automatic train control system and method
US7092894B1 (en) 1994-09-01 2006-08-15 Harris Corporation Cost reactive scheduler and method
US5623413A (en) * 1994-09-01 1997-04-22 Harris Corporation Scheduling system and method
US5668944A (en) * 1994-09-06 1997-09-16 International Business Machines Corporation Method and system for providing performance diagnosis of a computer system
US7373322B1 (en) 1994-09-20 2008-05-13 Papyrus Technology Corporation Two-way wireless communication system for financial industry transactions
US5774877A (en) * 1994-09-20 1998-06-30 Papyrus Technology Corp. Two-way wireless system for financial industry transactions
US6768981B2 (en) 1994-09-20 2004-07-27 Papyrus Corporation Method for executing a cross-trade in a two-way wireless system
US5797002A (en) * 1994-09-20 1998-08-18 Papyrus Technology Corp. Two-way wireless system for financial industry transactions
US6023679A (en) * 1994-10-04 2000-02-08 Amadeus Global Travel Distribution Llc Pre- and post-ticketed travel reservation information management system
US5842173A (en) * 1994-10-14 1998-11-24 Strum; David P. Computer-based surgical services management system
US5596502A (en) * 1994-11-14 1997-01-21 Sunoptech, Ltd. Computer system including means for decision support scheduling
US5761684A (en) * 1995-05-30 1998-06-02 International Business Machines Corporation Method and reusable object for scheduling script execution in a compound document
US5634100A (en) * 1995-08-07 1997-05-27 Apple Computer, Inc. System and method for event parameter interdependence and adjustment with pen input
US5644721A (en) * 1995-08-30 1997-07-01 System One Information Management, L.L.C. Multiple currency travel reservation information management system and method
US5765140A (en) * 1995-11-17 1998-06-09 Mci Corporation Dynamic project management system
WO1997025682A1 (en) * 1996-01-05 1997-07-17 Hirsch John D System and method for optimal operating room scheduling and booking
US5835898A (en) * 1996-02-29 1998-11-10 Dcd Corporation Visual schedule management system for a manufacturing facility
US5781737A (en) * 1996-04-30 1998-07-14 International Business Machines Corporation System for processing requests for notice of events
US5918207A (en) * 1996-05-01 1999-06-29 Electronic Data Systems Corporation Process and system for predictive resource planning
US5970463A (en) * 1996-05-01 1999-10-19 Practice Patterns Science, Inc. Medical claims integration and data analysis system
US6049774A (en) * 1996-07-08 2000-04-11 At&T Corp. Machine, method and medium for dynamic optimization for resource allocation
US5923552A (en) * 1996-12-31 1999-07-13 Buildnet, Inc. Systems and methods for facilitating the exchange of information between separate business entities
US5831534A (en) * 1997-01-09 1998-11-03 Mooney; John M. Patient detection system
US6571215B1 (en) * 1997-01-21 2003-05-27 Microsoft Corporation System and method for generating a schedule based on resource assignments
US6609100B2 (en) * 1997-03-07 2003-08-19 Lockhead Martin Corporation Program planning management system
US5978768A (en) * 1997-05-08 1999-11-02 Mcgovern; Robert J. Computerized job search system and method for posting and searching job openings via a computer network
US6032123A (en) * 1997-05-12 2000-02-29 Jameson; Joel Method and apparatus for allocating, costing, and pricing organizational resources
US6064974A (en) * 1997-05-30 2000-05-16 Novell, Inc. Method and system for monitoring the status of a limited resource
US6169534B1 (en) 1997-06-26 2001-01-02 Upshot.Com Graphical user interface for customer information management
US6035278A (en) * 1997-07-08 2000-03-07 Netscape Communications Corporation Method and system for schedule and task management
US6073110A (en) * 1997-07-22 2000-06-06 Siemens Building Technologies, Inc. Activity based equipment scheduling method and system
US6990458B2 (en) * 1997-08-28 2006-01-24 Csg Systems, Inc. System and method for computer-aided technician dispatch and communication
WO1999018530A1 (en) * 1997-10-06 1999-04-15 Nexprise, Inc. Trackpoint-based computer-implemented systems and methods for facilitating collaborative project development and communication
US6028819A (en) * 1997-12-16 2000-02-22 Schlumberger Technology Corporation Method and system of simulating and optimizing land seismic operations
US6965867B1 (en) 1998-04-29 2005-11-15 Joel Jameson Methods and apparatus for allocating, costing, and pricing organizational resources
US6282546B1 (en) * 1998-06-30 2001-08-28 Cisco Technology, Inc. System and method for real-time insertion of data into a multi-dimensional database for network intrusion detection and vulnerability assessment
US6157915A (en) * 1998-08-07 2000-12-05 International Business Machines Corporation Method and apparatus for collaboratively managing supply chains
AU5791899A (en) * 1998-08-27 2000-03-21 Upshot Corporation A method and apparatus for network-based sales force management
US6171112B1 (en) 1998-09-18 2001-01-09 Wyngate, Inc. Methods and apparatus for authenticating informed consent
US6149440A (en) * 1998-09-18 2000-11-21 Wyngate, Inc. Methods and apparatus for authenticating informed consent
US6336101B1 (en) * 1998-09-24 2002-01-01 International Business Machines Corporation Tracking of computer components allocated during configuration of computer systems and networks by a simplified user friendly configuration process
US6298334B1 (en) 1998-10-15 2001-10-02 Netdecide Corporation Object-based numeric-analysis engine
US7505827B1 (en) 1998-11-06 2009-03-17 Honeywell International Inc. Automated finite capacity scheduler
US6275812B1 (en) * 1998-12-08 2001-08-14 Lucent Technologies, Inc. Intelligent system for dynamic resource management
CA2356182A1 (en) * 1998-12-21 2000-06-29 Roland R. Thompson System and method for performing substitute fulfillment information compilation and notification
US6334133B1 (en) * 1998-12-21 2001-12-25 Frontline Data, Inc. System and method for performing substitute fulfillment
JP3327235B2 (en) * 1998-12-22 2002-09-24 トヨタ自動車株式会社 Order delivery management system
US6614450B1 (en) * 1999-03-03 2003-09-02 Gateway, Inc. Information display system for scheduling the utilization of a facility
US6408218B1 (en) 1999-03-18 2002-06-18 Textron Systems Corporation Shop floor control system
US6806891B1 (en) * 1999-05-07 2004-10-19 The Foxboro Company Method and apparatus for automated management and display of booking status
US6389454B1 (en) 1999-05-13 2002-05-14 Medical Specialty Software Multi-facility appointment scheduling system
US6625636B1 (en) * 1999-05-13 2003-09-23 International Business Machines Corporation Job protection within a distributed processing system having subsystem downtime
US8121874B1 (en) * 1999-05-27 2012-02-21 Accenture Global Services Limited Phase delivery of components of a system required for implementation technology
US7945468B1 (en) 1999-08-20 2011-05-17 Frontline Technologies, Inc. Notification of employees via pass code accessed web pages
US6662230B1 (en) 1999-10-20 2003-12-09 International Business Machines Corporation System and method for dynamically limiting robot access to server data
US6876991B1 (en) 1999-11-08 2005-04-05 Collaborative Decision Platforms, Llc. System, method and computer program product for a collaborative decision platform
US8788308B1 (en) * 2004-03-29 2014-07-22 West Corporation Employee scheduling and schedule modification method and apparatus
US6798413B1 (en) * 1999-12-03 2004-09-28 Dcs, Inc. Workflow management system
US6968314B1 (en) 1999-12-22 2005-11-22 International Business Machines Corporation Enhanced security features for an automated order fulfillment system
US20020029272A1 (en) * 2000-02-11 2002-03-07 Scott Weller Method and system for assigning and distributing work over a computer network
WO2001069496A2 (en) * 2000-03-13 2001-09-20 Volt Information Sciences, Inc. System and method for internet based procurement of goods and services
US20010047287A1 (en) * 2000-03-31 2001-11-29 Simon Jacobs Finding technique for a scheduling system
US20030196312A1 (en) * 2000-04-06 2003-10-23 Ford Motor Company Method for manufacturing an item
US10115076B2 (en) * 2000-04-21 2018-10-30 Goalassist Corporation System and method employing capacity/demand management for human-factor resources
US7457765B2 (en) * 2000-06-02 2008-11-25 Drason Consulting Services, Llc Method and system for scheduling employees in a patient care environment
US7587329B2 (en) * 2000-06-02 2009-09-08 Drason Consulting Services, Llc Method and system for optimizing employee scheduling in a patient care environment
WO2001097058A2 (en) * 2000-06-13 2001-12-20 Axt Juergen Method for apportioning industrial or technological resources in technical systems
AU2001269886A1 (en) * 2000-06-15 2002-01-14 Xis Incorporated Method and system for product lifecycle management
US7236976B2 (en) * 2000-06-19 2007-06-26 Aramark Corporation System and method for scheduling events and associated products and services
US6751630B1 (en) * 2000-07-20 2004-06-15 Ge Medical Technology Services, Inc. Integrated multiple biomedical information sources
US7174303B2 (en) * 2000-07-31 2007-02-06 Uappoint, Inc Customer driven, sponsor controlled network-based graphical scheduling system and method
US8180661B2 (en) * 2000-08-23 2012-05-15 Landport Systems, Inc. System and method for managing property
US20020129139A1 (en) * 2000-09-05 2002-09-12 Subramanyan Ramesh System and method for facilitating the activities of remote workers
US6742028B1 (en) 2000-09-15 2004-05-25 Frank Wang Content management and sharing
US8050944B2 (en) * 2000-09-20 2011-11-01 Epic Systems Corporation Intelligent patient visit information management and navigation system
US7249145B1 (en) 2000-10-13 2007-07-24 General Electric Company Methods and apparatus for selecting candidates to interview
TW541483B (en) * 2000-10-27 2003-07-11 Manugistics Inc System and method for ensuring order fulfillment
WO2002037376A1 (en) * 2000-10-27 2002-05-10 Manugistics, Inc. Supply chain demand forecasting and planning
US20020095307A1 (en) * 2000-10-27 2002-07-18 Manugistics, Inc. System and method for inventory and capacity availability management
US20020095322A1 (en) * 2000-10-27 2002-07-18 Manugistics, Inc. System and method of monitoring supply chain parameters
US6962531B2 (en) * 2000-11-03 2005-11-08 Harrah's Operating Company, Inc. Automated service scheduling system
US7765121B2 (en) * 2000-11-03 2010-07-27 Harrah's Operating Company, Inc. Automated service scheduling system based on customer value
US20020055918A1 (en) * 2000-11-08 2002-05-09 Patrick Hlathein Operating room resource management system incorporating an interactive, visual method for coordinating multiple, interdependent
US7139720B1 (en) * 2000-11-14 2006-11-21 Xerox Corporation Project planning system and method for accommodating AD HOC requests within a fixed core development cycle
US20020120472A1 (en) * 2000-12-22 2002-08-29 Dvorak Carl D. System and method for integration of health care records
US6983423B2 (en) * 2000-12-22 2006-01-03 Epic Systems Corporation Electronic system for collecting and communicating clinical order information in an acute care setting
US6901407B2 (en) * 2001-01-12 2005-05-31 Rick D. Curns System and method for updating project management scheduling charts
US6818006B2 (en) * 2001-04-03 2004-11-16 Medtronic Vascular, Inc. Temporary intraluminal filter guidewire
US6584400B2 (en) 2001-04-09 2003-06-24 Louis J C Beardsworth Schedule activated management system for optimizing aircraft arrivals at congested airports
JP2002312473A (en) * 2001-04-11 2002-10-25 Matsushita Electric Ind Co Ltd Health examination system
US6959405B2 (en) * 2001-04-18 2005-10-25 Blue Pumpkin Software, Inc. Method and system for concurrent error identification in resource scheduling
US20020156670A1 (en) * 2001-04-23 2002-10-24 Newman Frederic M. Method of managing workers at a well site
US20020153134A1 (en) * 2001-04-23 2002-10-24 Newman Frederic M. Method of managing work orders at a well site
US6947161B2 (en) * 2001-05-16 2005-09-20 Hewlett-Packard Development Company, L.P. Systems and methods for automatic status tracking of automatically ordered replaceable components for printing devices
US20020178043A1 (en) * 2001-05-25 2002-11-28 Searles J. Brian Method and system for monitoring employee availability
US20020188490A1 (en) * 2001-06-12 2002-12-12 Kruse Patricia S. Meeting scheduling/meeting room reservation linkage method
US7415393B1 (en) 2001-06-14 2008-08-19 Massachusetts Institute Of Technology Reliability buffering technique applied to a project planning model
US7349863B1 (en) 2001-06-14 2008-03-25 Massachusetts Institute Of Technology Dynamic planning method and system
US7027051B2 (en) * 2001-06-29 2006-04-11 International Business Machines Corporation Graphical user interface for visualization of sampled data compared to entitled or reference levels
US20010051892A1 (en) * 2001-07-26 2001-12-13 David Brown Method for scheduling appointments
US20050015504A1 (en) * 2001-09-13 2005-01-20 Dorne Raphael Jh Resource management method and apparatus
AU2002336552A1 (en) * 2001-09-17 2003-04-01 Duke University Methods of providing medical information and related systems and computer program products
US10346767B2 (en) * 2001-10-31 2019-07-09 Goalassist Corporation System and method employing capacity/demand management in prepared food service industry
US6785881B1 (en) * 2001-11-19 2004-08-31 Cypress Semiconductor Corporation Data driven method and system for monitoring hardware resource usage for programming an electronic device
US20030154110A1 (en) * 2001-11-20 2003-08-14 Ervin Walter Method and apparatus for wireless access to a health care information system
US20030130872A1 (en) * 2001-11-27 2003-07-10 Carl Dvorak Methods and apparatus for managing and using inpatient healthcare information
US20030120582A1 (en) * 2001-12-21 2003-06-26 Oncall Solutions, Inc. Call schedule auctioning method and apparatus
CA2368523A1 (en) * 2002-01-18 2003-07-18 Genus Resource Management Technologies Inc. Method and system for integrated natural resource management
US20030139952A1 (en) * 2002-01-24 2003-07-24 Ford Global Technologies, Inc. Complexity management and production optimization system
US20030216945A1 (en) * 2002-03-25 2003-11-20 Dvorak Carl D. Method for analyzing orders and automatically reacting to them with appropriate responses
US20030220815A1 (en) * 2002-03-25 2003-11-27 Cathy Chang System and method of automatically determining and displaying tasks to healthcare providers in a care-giving setting
US20030200168A1 (en) * 2002-04-10 2003-10-23 Cullen Andrew A. Computer system and method for facilitating and managing the project bid and requisition process
US7698146B2 (en) * 2002-04-24 2010-04-13 Volt Information Sciences Inc. System and method for collecting and providing resource rate information using resource profiling
US7925568B2 (en) * 2002-04-10 2011-04-12 Volt Information Sciences, Inc. Computer system and method for producing analytical data related to the project bid and requisition process
US7558745B2 (en) * 2002-09-30 2009-07-07 Volt Information Sciences, Inc. Method of and system for enabling and managing sub-contracting entities
US20030212604A1 (en) * 2002-05-09 2003-11-13 Cullen Andrew A. System and method for enabling and maintaining vendor qualification
US20030204434A1 (en) * 2002-04-29 2003-10-30 Linton Jonathan Daniel Forecast of amount in the face of uncertainty
US20030220821A1 (en) * 2002-04-30 2003-11-27 Ervin Walter System and method for managing and reconciling asynchronous patient data
US20030220816A1 (en) * 2002-04-30 2003-11-27 Andy Giesler System and method for managing interactions between machine-generated and user-defined patient lists
US20030220817A1 (en) * 2002-05-15 2003-11-27 Steve Larsen System and method of formulating appropriate subsets of information from a patient's computer-based medical record for release to various requesting entities
US20040010422A1 (en) * 2002-05-20 2004-01-15 Cliff Michalski Method and apparatus for batch-processed invoicing
US20040010465A1 (en) * 2002-05-20 2004-01-15 Cliff Michalski Method and apparatus for exception based payment posting
US20040002884A1 (en) * 2002-06-28 2004-01-01 Lenio Allan J. Method for facilitating product launches through an integrated communication process
US7983923B1 (en) 2002-07-10 2011-07-19 Sap Ag Collaborative management of delivery schedules
US7979294B2 (en) * 2002-07-31 2011-07-12 Epic Systems Corporation System and method for providing decision support to appointment schedulers in a healthcare setting
WO2004015605A1 (en) * 2002-08-08 2004-02-19 Hiroshi Egawa Method for setting reservation for examination of patient in medical organization, reservation setting system, computer program, and recording medium
US7814055B2 (en) * 2002-08-28 2010-10-12 Apple Inc. Method of managing a calendar and a computer system for implementing that method
EP1546972A1 (en) * 2002-09-09 2005-06-29 Apple Computer, Inc. A computer program comprising a plurality of calendars
AU2003263107A1 (en) * 2002-09-09 2004-03-29 Apple Computer, Inc. A method of managing a calendar and a computer system for implementing that method
US20040172520A1 (en) * 2002-09-19 2004-09-02 Michael Smit Methods and apparatus for visually creating complex expressions that inform a rules-based system of clinical decision support
JP3976659B2 (en) * 2002-10-09 2007-09-19 富士通株式会社 Business management method by computer
US7840434B2 (en) * 2002-10-29 2010-11-23 At&T Intellectual Property I, L. P. Methods and systems for assigning multiple tasks
US11361853B2 (en) 2002-10-29 2022-06-14 Practice Velocity, LLC Method and system for automated medical records processing with telemedicine
US7953625B2 (en) * 2002-10-29 2011-05-31 Sap Aktiengesellschaft Available resource presentation
US9842188B2 (en) 2002-10-29 2017-12-12 Practice Velocity, LLC Method and system for automated medical records processing with cloud computing
US7624027B1 (en) 2002-10-29 2009-11-24 Practice Velocity, LLC Method and system for automated medical records processing
US10714213B2 (en) 2002-10-29 2020-07-14 Practice Velocity, LLC Method and system for automated medical records processing with patient tracking
US8606594B2 (en) 2002-10-29 2013-12-10 Practice Velocity, LLC Method and system for automated medical records processing
EP1565109A1 (en) * 2002-11-25 2005-08-24 Fonar Corporation Method, apparatus, and facility for mri dual scanning
US7034916B2 (en) 2002-12-04 2006-04-25 Eastman Kodak Company Scheduling between digital projection and film projection corresponding to a predetermined condition
US6812994B2 (en) * 2002-12-04 2004-11-02 Eastman Kodak Company Streamlined methods and systems for scheduling and handling digital cinema content in a multi-theatre environment
US20040111307A1 (en) * 2002-12-04 2004-06-10 International Business Machines Corporation Electronic calendar management of privately owned resources
US7236227B2 (en) 2002-12-04 2007-06-26 Eastman Kodak Company System for management of both pre-show and feature presentation content within a theatre
US20040133889A1 (en) * 2002-12-12 2004-07-08 Renzo Colle Scheduling tasks across multiple locations
US20040117046A1 (en) * 2002-12-12 2004-06-17 Renzo Colle User interface for scheduling tasks
US20040122711A1 (en) * 2002-12-20 2004-06-24 Mediware Information Systems Inc. System and method for the optimization of the delivery of hospital services
US20060212188A1 (en) * 2003-02-27 2006-09-21 Joel Kickbusch Method and apparatus for automatic selection of alternative routing through congested areas using congestion prediction metrics
US7797087B2 (en) 2003-02-27 2010-09-14 General Electric Company Method and apparatus for selectively disabling train location reports
US7725249B2 (en) * 2003-02-27 2010-05-25 General Electric Company Method and apparatus for congestion management
US7937193B2 (en) 2003-02-27 2011-05-03 General Electric Company Method and apparatus for coordinating railway line of road and yard planners
US7512481B2 (en) * 2003-02-27 2009-03-31 General Electric Company System and method for computer aided dispatching using a coordinating agent
US20060212187A1 (en) * 2003-02-27 2006-09-21 Wills Mitchell S Scheduler and method for managing unpredictable local trains
US20050154634A1 (en) * 2003-03-08 2005-07-14 Robert Konop Human factors scheduling safety system
US7831458B2 (en) * 2003-04-09 2010-11-09 Siemens Aktiengesellschaft Method and system for supplying a number of service providers with technical service devices
US8292172B2 (en) * 2003-07-29 2012-10-23 General Electric Company Enhanced recordation device for rail car inspections
WO2005020018A2 (en) * 2003-08-18 2005-03-03 Gilbert Leistner System and method for identification of quasi-fungible goods and services, and financial instruments based thereon
US8494945B2 (en) 2003-08-18 2013-07-23 Gilbert Leistner Methods for creating a group practice
WO2005027011A2 (en) * 2003-09-12 2005-03-24 Quadrat Planning of simultaneous examinations for a single patient within one time slot
EP1550969A3 (en) * 2003-12-11 2005-08-31 International Business Machines Corporation Method and system for dynamically and automatically set-up offerings for IT-services
US20050228707A1 (en) * 2003-12-23 2005-10-13 Robert Hendrickson Method for real-time allocation of customer service resources and opportunities for optimizing business and financial benefit
US20050154600A1 (en) * 2004-01-08 2005-07-14 American International Group, Inc. Extended work program
US7848946B2 (en) 2004-01-12 2010-12-07 Jda Software Group, Inc. Sales history decomposition
AU2005206586A1 (en) * 2004-01-21 2005-08-04 Rnc Global Products A project management method and system
US8275865B2 (en) * 2004-02-05 2012-09-25 International Business Machines Corporation Methods, systems and computer program products for selecting among alert conditions for resource management systems
US20050182582A1 (en) * 2004-02-12 2005-08-18 International Business Machines Corporation Adaptive resource monitoring and controls for a computing system
USD801981S1 (en) 2004-02-19 2017-11-07 Johnson Controls Technology Company Display screen with graphical user interface
WO2005084402A2 (en) * 2004-03-02 2005-09-15 Volt Information Sciences Inc. Method of and system for consultant re-seller business information transfer
US7739126B1 (en) 2004-03-02 2010-06-15 Cave Consulting Group Method, system, and computer program product for physician efficiency measurement and patient health risk stratification
US8340981B1 (en) 2004-03-02 2012-12-25 Cave Consulting Group, Inc. Method, system, and computer program product for physician efficiency measurement and patient health risk stratification utilizing variable windows for episode creation
US20050222884A1 (en) * 2004-03-31 2005-10-06 Ralf Ehret Capacity planning of resources
US20050228710A1 (en) * 2004-04-09 2005-10-13 Sam Richards Asset scheduling management in media production
US7383291B2 (en) * 2004-05-24 2008-06-03 Apple Inc. Method for sharing groups of objects
US7877356B1 (en) 2004-05-24 2011-01-25 Apple Inc. Retaining intermediate states of shared groups of objects and notification of changes to shared groups of objects
US7809682B2 (en) * 2004-05-24 2010-10-05 Apple Inc. Data synchronization between multiple devices
US7991637B1 (en) 2004-05-24 2011-08-02 Apple Inc. Freeform communication in calendaring system
US7814231B2 (en) * 2004-05-24 2010-10-12 Apple Inc. Method of synchronizing between three or more devices
US7925584B2 (en) * 2004-06-29 2011-04-12 Textura Corporation Construction payment management system and method with document tracking features
US7908047B2 (en) * 2004-06-29 2011-03-15 General Electric Company Method and apparatus for run-time incorporation of domain data configuration changes
US20050289051A1 (en) 2004-06-29 2005-12-29 Allin Patrick J Construction payment management system and method
US20080288379A1 (en) * 2004-06-29 2008-11-20 Allin Patrick J Construction payment management system and method with automated electronic document generation features
US9460441B2 (en) 2004-06-29 2016-10-04 Textura Corporation Construction payment management system and method with document exchange features
US8561076B1 (en) 2004-06-30 2013-10-15 Emc Corporation Prioritization and queuing of media requests
US20060015386A1 (en) * 2004-07-19 2006-01-19 Moore Dennis B Avoiding conflicting requests for resources or meetings
US8286125B2 (en) * 2004-08-13 2012-10-09 Cypress Semiconductor Corporation Model for a hardware device-independent method of defining embedded firmware for programmable systems
US7970639B2 (en) * 2004-08-20 2011-06-28 Mark A Vucina Project management systems and methods
US20060041461A1 (en) * 2004-08-20 2006-02-23 Mark Vucina Project management device and method
US7735091B2 (en) * 2004-08-23 2010-06-08 At&T Intellectual Property I, L.P. Methods, systems and computer program products for providing application services to a user
US8725547B2 (en) * 2004-08-24 2014-05-13 Epic Systems Corporation Utilization indicating schedule scanner
US20060053034A1 (en) * 2004-09-08 2006-03-09 Epic Systems Corporation System and method for providing a real-time status for managing encounters in health care settings
US7693735B2 (en) * 2004-11-23 2010-04-06 Etadirect Holdings, Inc. Dynamic schedule mediation
US20060122865A1 (en) * 2004-11-24 2006-06-08 Erik Preiss Procedural medicine workflow management
US20060143060A1 (en) * 2004-12-28 2006-06-29 General Electric Company Integrated scheduling system for health care providers
US8024355B2 (en) * 2004-12-29 2011-09-20 Sap Ag Dynamic capacity demand profile construction with a persisted capacity demand profile and a collision buffer
US7443303B2 (en) 2005-01-10 2008-10-28 Hill-Rom Services, Inc. System and method for managing workflow
US7844480B2 (en) * 2005-01-27 2010-11-30 International Business Machines Corporation Method and system for planning and managing multiple projects on demand with critical chain and replenishment
US20060177041A1 (en) * 2005-02-04 2006-08-10 Michael Warner Method and system to project staffing needs using predictive modeling
SG159530A1 (en) * 2005-02-11 2010-03-30 Volt Inf Sciences Inc Project work change in plan/scope administrative and business information synergy system and method
EP1859395A1 (en) * 2005-03-04 2007-11-28 Quadrat Method and user interface for managing and displaying solutions for multiple resources in an appointment scheduling system
EP1859398A1 (en) 2005-03-04 2007-11-28 Quadrat Method for processing a linked list of time segments
EP1861302A4 (en) * 2005-03-14 2010-05-05 Gen Electric A system and method for railyard planning
US20060218027A1 (en) * 2005-03-22 2006-09-28 Carrion Veronica L System and method for single user interface window event scheduling
US7505615B2 (en) * 2005-05-06 2009-03-17 Stereotaxis, Inc. Preoperative and intra-operative imaging-based procedure workflow with complexity scoring
CA2653280A1 (en) * 2005-05-25 2006-11-30 Romeena Pty Limited As Trustee For Kemp Family Trust Instrument tracking
MX2008001458A (en) * 2005-08-01 2008-04-07 Volt Inf Sciences Inc Outsourced service level agreement provisioning management system and method.
US10157355B2 (en) * 2005-11-15 2018-12-18 General Electric Company Method to view schedule interdependencies and provide proactive clinical process decision support in day view form
US20070143169A1 (en) * 2005-12-21 2007-06-21 Grant Chad W Real-time workload information scheduling and tracking system and related methods
US20070162315A1 (en) * 2006-01-06 2007-07-12 Microsoft Corporation Space reservation system
US8375026B1 (en) 2006-01-13 2013-02-12 CareerBuilder, LLC Method and system for matching data sets of non-standard formats
US8103679B1 (en) 2006-01-13 2012-01-24 CareerBuilder, LLC Method and system for matching data sets of non-standard formats
US8090725B1 (en) 2006-01-13 2012-01-03 CareerBuilder, LLC Method and system for matching data sets of non-standard formats
US20070168304A1 (en) * 2006-01-18 2007-07-19 Hletko Paul M Method of financing mobile assets
US7474980B2 (en) * 2006-01-24 2009-01-06 The United States Of America As Represented By The Secretary Of The Army Automated tool for monitoring archaeological sites (ATMAS™)
KR100678126B1 (en) * 2006-03-24 2007-02-02 삼성전자주식회사 Method of managing duplication schedule in mobile communication terminal
US7603212B2 (en) * 2006-03-30 2009-10-13 Honeywell International, Inc. Real time planning and scheduling for a team of unmanned vehicles
US7710999B2 (en) * 2006-04-27 2010-05-04 Alcatel Lucent Policy calendar
US20070260497A1 (en) * 2006-05-02 2007-11-08 Wolfgang Daum Method of planning train movement using a front end cost function
US7797088B2 (en) * 2006-05-02 2010-09-14 General Electric Company Method and apparatus for planning linked train movements
US8498762B2 (en) * 2006-05-02 2013-07-30 General Electric Company Method of planning the movement of trains using route protection
US7734383B2 (en) * 2006-05-02 2010-06-08 General Electric Company Method and apparatus for planning the movement of trains using dynamic analysis
US20070276716A1 (en) * 2006-05-25 2007-11-29 Akihiro Kosugi Method For Retrieval of Available Intervals
US7680750B2 (en) * 2006-06-29 2010-03-16 General Electric Company Method of planning train movement using a three step optimization engine
US8082071B2 (en) * 2006-09-11 2011-12-20 General Electric Company System and method of multi-generation positive train control system
WO2008048591A2 (en) * 2006-10-18 2008-04-24 Mediviz Systems, Inc. Medical decision support system and method
US20080109267A1 (en) * 2006-11-02 2008-05-08 International Business Machines Corporation Online startup of an innovation project
US8433461B2 (en) * 2006-11-02 2013-04-30 General Electric Company Method of planning the movement of trains using pre-allocation of resources
US20080115077A1 (en) * 2006-11-09 2008-05-15 International Business Machines Corporation Persistent status indicator for calendar
CN1968147B (en) * 2006-11-27 2010-04-14 华为技术有限公司 Service processing method, network device, and service processing system
US8306883B2 (en) * 2007-04-30 2012-11-06 Textura Corporation Construction payment management systems and methods with specified billing features
US8522258B1 (en) 2007-06-15 2013-08-27 At&T Mobility Ii Llc Event handling system
US8571905B2 (en) 2007-07-16 2013-10-29 IT Casino Solutions, LLC Casino operations management system
US8380744B2 (en) 2007-07-17 2013-02-19 At&T Intellectual Property I, L.P. Methods, systems, and computer-readable media for generating a report indicating job availability
US20090024438A1 (en) * 2007-07-17 2009-01-22 Robert Ingman Methods, Systems, and Computer-Readable Media for Providing Workforce To Load Information
US8239232B2 (en) 2007-07-17 2012-08-07 At&T Intellectual Property I, L.P. Methods, systems, and computer-readable media for providing commitments information relative to a turf
US20090024435A1 (en) * 2007-07-17 2009-01-22 Robert Ingman Methods, Systems, and Computer-Readable Media for Providing Notification of a Last Job Dispatch
US8060401B2 (en) 2007-07-17 2011-11-15 At&T Intellectual Property I, Lp Methods, systems, and computer-readable media for providing an indication of a schedule conflict
US8352302B2 (en) 2007-07-17 2013-01-08 At&T Intellectual Property I, L.P. Methods, systems, and computer-readable media for determining a plurality of turfs from where to reallocate a workforce to a given turf
US8069072B2 (en) * 2007-07-17 2011-11-29 At&T Intellectual Property I, Lp Methods, systems, and computer-readable media for providing an indication of hightime
US8341547B2 (en) 2007-07-17 2012-12-25 At&T Intellectual Property I, L.P. Methods, systems, and computer-readable media for providing contact information at turf level
US8249905B2 (en) 2007-07-17 2012-08-21 At&T Intellectual Property I, Lp Methods, systems, and computer-readable media for providing future job information
WO2009012454A1 (en) * 2007-07-18 2009-01-22 Chevron U.S.A. Inc. Systems and methods for increasing safety and efficiency in oil field operations
US20090023431A1 (en) * 2007-07-19 2009-01-22 Hewlett-Packard Development Company, L.P. Systems and Methods for Communicating with a Network Switch
US20090177535A1 (en) * 2007-09-18 2009-07-09 Pmp Corporation System and method for monitoring and executing substitute fulfillment
US20090125368A1 (en) * 2007-10-16 2009-05-14 Vujicic Jovo John System and Method for Scheduling Work Orders
EP2060986B1 (en) * 2007-11-13 2019-01-02 Karl Storz SE & Co. KG System and method for management of processes in a hospital and/or in an operating room
US8180657B2 (en) * 2007-12-31 2012-05-15 International Business Machines Corporation System and method for event slot negotiation
US8140366B2 (en) * 2008-01-04 2012-03-20 Frontline Technologies, Inc. Method, system and program product for filling job orders
US20090187563A1 (en) * 2008-01-22 2009-07-23 Geospot, Inc. Methods for Generating and Indicating a Time Relevant Status for an Operating Entity
JP5044820B2 (en) * 2008-01-24 2012-10-10 インターナショナル・ビジネス・マシーンズ・コーポレーション Process management system, process management method, and program
US20090204461A1 (en) * 2008-02-13 2009-08-13 International Business Machines Corporation Method and system for workforce optimization
US20090204460A1 (en) * 2008-02-13 2009-08-13 International Business Machines Corporation Method and System For Workforce Optimization
US8352296B2 (en) * 2008-04-18 2013-01-08 Microsoft Corporation Managing real time meeting room status
US8635126B2 (en) 2010-11-17 2014-01-21 It Casino Solutions Llc Casino operations management system
US8301464B1 (en) 2008-07-18 2012-10-30 Cave Consulting Group, Inc. Method and system for producing statistical analysis of medical care information
US11244416B2 (en) 2008-07-18 2022-02-08 Cave Consulting Group, Inc. System, method, and graphical user interface for identifying medical care providers outside a process-of-care standard
US8010382B2 (en) 2008-09-16 2011-08-30 General Electric Company Systems and methods for self-updating intelligent procedure duration estimation for patient scheduling
US20100088140A1 (en) * 2008-10-06 2010-04-08 Lahav Gil Automated systems and methods for time management
US20100179854A1 (en) * 2009-01-15 2010-07-15 Shafer Steven L Scheduling System and Method
US9483807B2 (en) * 2009-03-26 2016-11-01 Laguna Mena Inc Hospital communication system
EP2256679A1 (en) * 2009-05-29 2010-12-01 Siemens Aktiengesellschaft Customizable scheduling tool, manufacturing executing system comprising said tool and method of using said tool
US20120203589A1 (en) * 2009-07-27 2012-08-09 Nextgen Healthcare Information Systems, Inc. Systematic Rule-Based Workflow Tasking and Event Scheduling
WO2011013227A1 (en) * 2009-07-30 2011-02-03 株式会社日立製作所 Staff allocation system and server
AU2010282417A1 (en) * 2009-08-12 2012-03-08 Volt Information Sciences, Inc System and method for productizing human capital labor employment positions/jobs
US8260648B2 (en) * 2009-09-09 2012-09-04 King Fahd University Of Petroleum And Minerals Process scheduling optimization method
US20130103444A1 (en) * 2011-10-21 2013-04-25 Epic Systems Corporation Group scheduling and assignment of resources
US20130290008A1 (en) * 2012-04-27 2013-10-31 Oracle International Corporation Staff assignment for clinical trials
US9021376B2 (en) * 2012-07-02 2015-04-28 International Business Machines Corporation Task timer
US20140108023A1 (en) * 2012-10-12 2014-04-17 Harold Arkoff Operating room management system with mobile app
US9268604B1 (en) * 2012-12-11 2016-02-23 The Boeing Company Automated allocation of vehicle systems for different specified vehicle testing tasks
US20140288941A1 (en) * 2013-03-25 2014-09-25 Arizona S-Corp. Case scheduling, logistics management and associated data management
US20150006341A1 (en) * 2013-06-27 2015-01-01 Metratech Corp. Billing transaction scheduling
US10241654B2 (en) * 2013-12-20 2019-03-26 Dassault Systemes Americas Corp. Computer method and apparatus for automated scheduling
US10037821B2 (en) * 2013-12-27 2018-07-31 General Electric Company System for integrated protocol and decision support
CA2846592C (en) * 2014-03-14 2023-01-03 Mxi Technologies Ltd. Resource planning method and system
US10055703B2 (en) * 2015-01-13 2018-08-21 Accenture Global Services Limited Factory management system
US10204320B2 (en) * 2015-04-30 2019-02-12 Teletracking Technologies, Inc. Integrated system for producing procedural data change sets communicated to client devices
US11037673B2 (en) 2015-09-04 2021-06-15 Materials Management Microsystems, Inc. Systems and methods for tracking surgical inventory and sterilization
US20170083842A1 (en) * 2015-09-21 2017-03-23 International Business Machines Corporation Risk evaluation in parallelizing projects
US11188878B2 (en) * 2015-09-22 2021-11-30 International Business Machines Corporation Meeting room reservation system
WO2017127722A1 (en) 2016-01-20 2017-07-27 Lucent Medical Systems, Inc. Low-frequency electromagnetic tracking
US20190156293A1 (en) * 2017-11-17 2019-05-23 Qualcomm Incorporated User location and activity based smart reminders
US11055647B2 (en) * 2018-03-22 2021-07-06 Microsoft Technology Licensing, Llc Resource conflict detection and communication
US10192410B1 (en) * 2018-04-06 2019-01-29 Seeca Medical, Inc. System for providing notification of a status of a patient examination and related methods
EP3772029A1 (en) 2019-07-31 2021-02-03 Ciaomanager Srl Method and apparatus for assigning rooms to reservations in hotels
US10658079B1 (en) 2019-08-18 2020-05-19 Medigate tech Ltd. Crowd-based recommendations of a version of firmware for medical devices
US10825566B1 (en) 2019-08-18 2020-11-03 Medigate tech Ltd. Ensuring availability of medical devices to receive maintenance
US10600512B1 (en) 2019-08-18 2020-03-24 Medigate tech Ltd. Network-based calculation of prevalence of repeated medical imaging
US11056232B2 (en) 2019-08-18 2021-07-06 Medigate tech Ltd. Medication usage auditing based on analysis of infusion pump network traffic
US20210319884A1 (en) * 2020-04-10 2021-10-14 GE Precision Healthcare LLC Systems and methods for resource availability management
CN111522849A (en) * 2020-04-22 2020-08-11 深圳市春蚕智能信息技术有限公司 Database dynamic access method, server and storage medium
US11687855B2 (en) 2020-10-26 2023-06-27 Showrunnr, Inc. System for synchronizing entertainment production resource procurement with production project scheduling

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT286004B (en) * 1969-09-15 1970-11-25 Franz Dr Gelder Process and device for the optical representation of business variables
US4019027A (en) * 1975-05-09 1977-04-19 Kelley William L Apparatus and method for schedule monitoring and control
US4336589A (en) * 1980-04-07 1982-06-22 Rapistan Division, Lear Siegler, Inc. Warehousing monitor and control system
US4553222A (en) * 1983-03-14 1985-11-12 Kurland Lawrence G Integrated interactive restaurant communication system for food and entertainment processing
JPS59214964A (en) * 1983-05-20 1984-12-04 Hitachi Ltd Conversational scheduling system
US4700318A (en) * 1983-12-09 1987-10-13 Stuart Ockman Project construction with depiction means and methods
US4591983A (en) * 1984-07-09 1986-05-27 Teknowledge, Inc. Hierarchical knowledge system
JPS6123003A (en) * 1984-07-09 1986-01-31 Hitachi Ltd Schedule drawing method
US4646238A (en) * 1984-10-26 1987-02-24 Analog Devices, Inc. Material requirements planning system and procedures for use in process industries
US4744028A (en) * 1985-04-19 1988-05-10 American Telephone And Telegraph Company, At&T Bell Laboratories Methods and apparatus for efficient resource allocation
US4835683A (en) * 1986-05-23 1989-05-30 Active English Information Systems, Inc. Expert information system and method for decision record generation
EP0329911B1 (en) * 1988-02-08 1995-03-22 International Business Machines Corporation Method for scheduling meetings

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010066023A1 (en) * 2008-12-12 2010-06-17 Smart Technologies Ulc System for supporting coordination of resources for events in an organization

Also Published As

Publication number Publication date
EP0306965A3 (en) 1991-07-10
AU622371B2 (en) 1992-04-02
JPH01162977A (en) 1989-06-27
EP0306965A2 (en) 1989-03-15
AU2206088A (en) 1989-03-23
US4937743A (en) 1990-06-26
JP2634070B2 (en) 1997-07-23
IL87663A0 (en) 1989-02-28
IL87663A (en) 1992-06-21

Similar Documents

Publication Publication Date Title
CA1294054C (en) Method and system for scheduling, monitoring and dynamically managing resources
US20220319683A1 (en) System and method for clinical workforce management interface
US5970466A (en) Graphical computer system and method for appointment scheduling
US6335733B1 (en) Method and system for displaying and editing a resource schedule
US5500938A (en) Method and apparatus for directly selecting and signalling start and stop times in an electronic calendar
US8874456B2 (en) Resource scheduling and monitoring
US8365095B2 (en) System and method for assigning and scheduling activities
US20060053034A1 (en) System and method for providing a real-time status for managing encounters in health care settings
US20020191035A1 (en) Computerized customizable scheduler
US20060004605A1 (en) System and method for a comprehensive interactive graphical representation of a health care facility for managing patient care and health care facility resources
Martin et al. The interactional affordances of technology: An ethnography of human-computer interaction in an ambulance control centre
US20080126126A1 (en) Method And Apparatus For Managing And Locating Hospital Assets, Patients And Personnel
US11610670B1 (en) System and method of dynamically generating work assignments
TWI759357B (en) Service support apparatus, service support method and service support program
Fisher Indoor positioning and digital management: Emerging surveillance regimes in hospitals
US20200380451A1 (en) Method and system for scheduling shifts and employee leave management
CA2518293A1 (en) Apparatus and method for the mobile visual display and modification of bed management information and patient placement information
CN105242899A (en) Method and apparatus for displaying information in portable monitor for ward rounds
US20140278521A1 (en) Location limited check-in kiosk method and apparatus
US20060015383A1 (en) Generic contextual floor plans
US11861961B2 (en) Key management system
JP2001022850A (en) Method and device for managing schedule, and recording medium storing schedule management program
JPH09251491A (en) Working information management system
EP1628211B1 (en) Method for providing a user interface
Wong et al. The effect of layout on dispatch planning and decision making

Legal Events

Date Code Title Description
MKLA Lapsed