CN100398285C - Method of artificial board production line thermopress loading and unloading and machine set - Google Patents

Method of artificial board production line thermopress loading and unloading and machine set Download PDF

Info

Publication number
CN100398285C
CN100398285C CNB200510025367XA CN200510025367A CN100398285C CN 100398285 C CN100398285 C CN 100398285C CN B200510025367X A CNB200510025367X A CN B200510025367XA CN 200510025367 A CN200510025367 A CN 200510025367A CN 100398285 C CN100398285 C CN 100398285C
Authority
CN
China
Prior art keywords
plate
transporter
unloader
cage
hot press
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB200510025367XA
Other languages
Chinese (zh)
Other versions
CN1686690A (en
Inventor
李绍昆
袁建新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Wood Based Panel Machinery Co Ltd
Original Assignee
Shanghai Wood Based Panel Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Wood Based Panel Machinery Co Ltd filed Critical Shanghai Wood Based Panel Machinery Co Ltd
Priority to CNB200510025367XA priority Critical patent/CN100398285C/en
Publication of CN1686690A publication Critical patent/CN1686690A/en
Application granted granted Critical
Publication of CN100398285C publication Critical patent/CN100398285C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The present invention relates to a plate blank thermal pressing loading and unloading method of a thermal pressing working section in a plate blank pressing device of an artificial board production line and a machine unit structure thereof. The action of an original machine is divided into two parts by increasing the layer number of the thermal pressing loading and unloading machine unit and increasing an amplitude surface, the up-and-down movement of a hanging cage is completed by an elevation preassembly machine, and plate blanks can be loaded and unloaded to a press by a plate loader. The elevation preassembly machine, the trolley plate loader, a thermocompressor and a plate unloader are combined together, the loading of two blocks of plate blanks is completed by one time of rise and fall of the elevation preassembly machine, and the pressed plate blanks are pushed into the plate unloader by a plate pushing machine on the front end of a trolley type belt conveyor when the plate loader enters the thermocompressor. The amplitude surface at the width direction of a device can be realized 6 to 8 inches by adopting the structural shape of the present invention, the layer number of the thermal pressing loading and unloading plate blanks can be further increased, and the production capacity of a single line can reach more than 150, 000 cubic meters at one year.

Description

The method and the unit of artificial board production line thermopress loading and unloading
Technical field
The present invention relates to a kind of artificial board product line slab press device, particularly relate to the method for slab hot pressing loading and unloading of the hot pressing workshop section in the artificial board product line slab press device and the structure of unit.
Technical background
The prior art of middle density artificial board production line generally all adopts no backing plate loader structure, shown in (Fig. 2) is the structure that 15 layers, 4 * 16 Foot do not have the backing plate loader, and this loader is made up of dolly 01, frame 02, oil cylinder 03, cage 04, oil motor drive unit 05, individual layer transmission system 06.Cage moves up and down, and finishes from transporter toward every layer of cart transport slab.Slab of every conveying, cage lifting once, energy consumption is big, about 60 tons of cage weight, be difficult to accurate control by dried cage weight and the bulky cage location, position with respect to hot press in lifting process that causes, easily break down in dress plate process, damage equipment causes stopping production.
Summary of the invention
The market capacity of medium-density plate wood-based plate is very big, manufacturer is for enlarging output, increasing the specification kind, imagination enlarges single line output with multi-daylight press, and technical scheme of the present invention is exactly to reach purpose of the present invention by the number of plies that increases hot pressing loading and unloading unit and increase breadth.According to the structural shape 4*16 Foot of traditional loader group, 15 layers have been arrived the limit, have only the structural shape of breaking through traditional loader, enlarge single line output and just become possibility.Original machine action is divided into two: cage moves up and down and is finished by pre-installation; And loader only is responsible for toward press loading and unloading slab.Adopt this structure not only to solve a structure difficult problem, and loader need not move up and down, become a fixing bin, the position accurate positioning of relatively hot press is reliable.Technical scheme of the present invention is by following technical measures specific implementation: the method that a kind of artificial board production line thermopress loading and unloading units (Fig. 1) are adopted is: it has adopted the pre-installation 1 of lift, dolly loader 2, hot press 3 and unloader 4 combinations.Wherein: the pre-installation of lift is made up of two layers of dress plate transporter, after two layers of dress plate transporter are filled slab, moves upward to the relevant position by the motor reducer that is loaded on a top of the trellis by four chains.Two layers of dress plate transporter start the two laminate bases of packing into simultaneously in the dolly loader, packing into of two blocks of slabs finished in a lifting; The dolly loader is mainly by the trolley type transporter, drive unit, and trapped orbit and each support are formed.After filling slab on every layer of trolley type transporter, drive unit is disposable to be pushed the trolley type transporter in the hot press, also together it is withdrawed from by drive unit when the trolley type transporter retreats.When withdrawing from, the main drive roller on the trolley type transporter is equipped with ratchet mechanism and one of live-roller gear is housed, and the rack drives gear reverses live-roller synchronously, slab is stayed in the hot press suppressed; Enter hot press simultaneously at the dolly loader, the slab that the push pedal device of trolley type transporter front end will suppress pushes unloader.
The unit of forming according to the method for above-mentioned artificial board production line thermopress loading and unloading, it is characterized in that described unit comprises the pre-installation 1 of lift, dolly loader 2, hot press 3 and unloader, wherein: a, the pre-installation of lift 1 (Fig. 3): the drive unit 101 that is loaded on whole frame top is connected four sprocket wheels connections by axle and driven chain by decelerator finishes two layers of dress plate transporter 105 lifting action, four columns 103 that are welded by H shaped steel connect whole drive unit 101 and put 102 on the shelf in order to supports in parallel, on four root posts, be welded with guide plate, in order to lifting dress plate transporter 105 guiding and positioning actions, at the drive unit chain other end counterweight 104 is housed, connect a lifting with two layers of dress plate transporter 105, two layers of dress plate transporter are fixedly installed in the support 106, in the support side directive wheel is housed and is used to prevent adorn the gas circuit deviation correcting device 107 of plate transporter 105 belt deviations, the control stroke is housed in the middle of two root posts, the travel switch frame 108 of position; B, dolly loader 2 (Fig. 4): will pack in the hot press 3 by the pre-installation of lift 1 slab of packing dolly loader 2 into, the slab that to suppress pushes unloader 4 simultaneously, dolly loader 2 is by putting 201 on the shelf, 12 root posts 202, the trolley track 203 and the trolley type transporter 204 that are fixed on column two limits are formed, trolley type transporter 204 is in order to the shipment slab and release the slab that has been pressed into, this trolley type transporter 204 is self-powered, when the dress plate transporter in the pre-installation 1 of lift starts, trolley type transporter 204 starts synchronously, a gear 205 that the band ratchet mechanism is housed at the main drive roller of trolley type transporter, whole trolley type transporter is under drive unit drives, in hot press 3, send slab and production board is released hot press, when retreating, gear 205 on the drive roll is under ratchet effect, the counter-rotating of drive drive roll, slab is stayed in the press, finish and once load and unload the slab process, drive unit is used as power by oil motor, by the reduction box driven gear, the tooth bar of gear driven trolley type transporter 204 2 sides and realize that the forward (FWD) of trolley type transporter 204 moves out; C, hot press 3 (Fig. 5): the blank flat that will be sent into by dolly loader 2 is through pressurization, heat and form slab, the frame 301 of hot press 3 is born all gross pressures of press, multilayer fixed cross beam 302 and heating platen 303 are installed in the frame 301, main conduction heat and the pressure of rising, position control 304 is also put in frame 301, be used for controlling the press total kilometres, and the thickness of every layer of blank flat of control, the gross pressure that moved cross beam 305 transmits from oil cylinder, bottom girder 306 and oil cylinder 307, whole press rack 301, fixed cross beam 302, heating platen 303, position control 304, moved cross beam 305, bottom girder 306 and oil cylinder 307 all are installed on the base, base is a reference for installation, in-line 308 connect oil cylinders 307 and in the future the hydraulic oil distribution of self-hydraulic system to every oil cylinder 307, the oil heating pipe line will import every heating platen 303 from the deep fat of heating system, and simultaneous opening and closing device guarantees in the press uphill process, every laminate base is pressurized simultaneously, be heated, and keep the stressed unanimity of every laminate base; D, unloader 4 (Fig. 6): unloader and hot press are fused by link 401, guarantee that unloader has enough rigidity and stability, four root posts, 402 main support cages 403, the weight of oil cylinder 408 and do cage on, the effect of following guiding, cage 403, oil cylinder 408 and travel switch 404 are installed in the middle of four root posts 402, travel switch 404 is used for controlling the position of cage, ejecting plate transporter 405 is installed in the right side, slab in the cage 403 is sent unloader 4, longitudinally guiding wheel 406 both sides, column 402 outside that are installed under the cage 403, make cage last, following process plays stabilization, the synchromesh gear of balanced controls 407, tooth bar is installed on directive wheel 406 times and 402 liang of lateral surfaces of column, assurance avoids cage 403 because of reasons such as unbalance loading cause the inhomogeneous rising in cage 403 left and right sides, make cage 403 can be parallel about; The piston rod of oil cylinder 408 is connected in cage 403, under the driving of oil pressure, makes cage upper and lower; Baffle plate frame 409 is installed in the middle of hot press 3 and the unloader 4, is used for avoiding skidding off in press decline process slab accident.
Good effect of the present invention is to provide reliable example for designing bigger single line output equipment later on.The structure of this artificial board production line thermopress loading and unloading unit has solved large format, big output wood-based plate (particularly medium density fibre board (MDF)) dockboard difficult problem.Adopt structural shape of the present invention, can make plant width direction breadth can accomplish 6 Foot even 8 Foot, the hot pressing dockboard unit number of plies also can further improve, and single line production capacity can reach to be produced per year more than 15 ten thousand steres.
Description of drawings
The structural representation of Fig. 1, the artificial board assembly line hot pressing loading and unloading of the present invention unit;
The loader structure diagram of Fig. 2, prior art;
The pre-installation structural representation of Fig. 3, the artificial board assembly line hot pressing loading and unloading of the present invention unit;
The dolly loader structural representation of Fig. 4, the artificial board assembly line hot pressing loading and unloading of the present invention unit;
The hot press structural representation of Fig. 5, the artificial board assembly line hot pressing loading and unloading of the present invention unit;
The unloader structural representation of Fig. 6, the artificial board assembly line hot pressing loading and unloading of the present invention unit.
The parts that legend mark in the accompanying drawing is expressed as follows respectively
The 1----lift is installed in advance, 2----dolly loader, 3----hot press, the 4----unloader, 01----trolley type transporter, 02----column, the 03----oil cylinder, 04----cage, 05----driven wheel, 06----individual layer drive unit, the 101----drive unit, 102----puts on the shelf, the 103----column, 104----counterweight, 105----dress plate transporter, the 106----support, 107----gas circuit deviation correcting device, 108----travel switch frame, 201----puts on the shelf, 202----column, 203----trolley track, 204----trolley type transporter, 205----gear, 301-----frame, the 302----fixed cross beam, 303----heating platen, 304----position control, the 305----moved cross beam, 306----bottom girder, 307----oil cylinder, the 308----in-line, 401----link, 402----column, the 403----cage, 404----travel switch frame, 405----ejecting plate transporter, the 406----directive wheel, the 407----balanced controls, 408----oil cylinder, 409----baffle plate frame.
The specific embodiment
A kind of specific embodiment of the present invention is to be applied in the artificial board production line thermopress loading and unloading unit of producing 6*18 English Foot, annual production 10 ten thousand stere medium density fibre board (MDF)s.
According to accompanying drawing 1,3,4, the artificial board production line thermopress loading and unloading unit that 5 and 6 structure assembles, it is characterized in that: in pre-installation (Fig. 3), the drive unit 101 that is loaded on whole frame top is mainly by speed ratio 61.02, the axle that the motor reducer of power 22kw is made by four 45# steels of shaft coupling connection drives the sprocket wheel of four pitches 31.75, chain is finished two layers of dress plate transporter 105 lifting action, rising or falling speed reaches 23.8 m/mins, trolley type transporter speed reaches 60 meters per minutes, all frequency conversion is adjustable, satisfy and produce book plate cycle needs, four root posts 103 are welded by H shaped steel, in order to support whole drive unit 101 and to put 102 on the shelf.On four root posts, weld, be processed with guide plate, in order to the guiding and the positioning action of lifting dress plate transporter 105.At the drive unit chain other end counterweight 104 is housed.Being equal in weight of the counterweight weight that HT200 cast iron is made and two layers of dolly transporter and fixed support 106, because of one lifting of two layers of dress plate transporter, be fixed in the support 106, in the support side directive wheel be housed and be used to prevent adorn the gas circuit deviation correcting device 107 of plate transporter 105 belt deviations.This device has the QGB-1-E80-100 cylinder, and pneumatic elements such as the travel switch of model 3SE3120-1UA are formed, and the travel switch frame 108 of control stroke, position is housed in the middle of two root posts.
Dolly loader (Fig. 4) mainly puts 201 on the shelf by what shaped steel was welded, 12 H shaped steel columns 202, be fixed on the trolley track 203 of column two limits by the processing of 160*160*12 angle steel, trolley type transporter 204 is formed, the trolley type transporter is by motor reducer (power 3kw, rotating speed 92r/min, model KF67DM100L4) diameter 200mm rubber driven roller, the tooth bar of modulus 8, framework, diameter is the driven voller of 30mm, width 2000mm belt, the gear of ratchet mechanism (modulus 8, the number of teeth 20) composition such as, in order to load and transport slab and to release the slab that has been pressed into, travelling speed reaches 60 meters per minutes, and frequency conversion is adjustable, when pre-installation (Fig. 3) transporter started, the trolley type transporter started maintenance speed unanimity synchronously under electrical equipment control.A gear 205 that the band ratchet mechanism is housed at the main drive roller of trolley type transporter, whole trolley type transporter is under drive unit drives, in hot press, send plate and production board is released hot press, when retreating, gear 205 on the drive roll is under ratchet effect, the counter-rotating of drive drive roll, slab is stayed in the press, finish and once load and unload the slab process, drive unit is used as power by oil motor, by the reduction box driven gear, the tooth bar of gear driven dress plate transporter two sides and realize the dress plate of trolley type transporter unloading plate.
The blank flat that hot press (Fig. 5) will be sent into by no backing plate dolly loader (Fig. 4) through pressurization, heating forms slab.Hot press mainly contains frame 301, this frame 301 is born all gross pressures of press, four piece together frame altogether, every assembly frame is welded into by gusset by two high-quality steel (thickness 70mm), fixed cross beam 302, heating platen (thickness 130mm) 303, heating platen is that steel plate boring (diameter 28mm) forms return passage, position control 304, be used for controlling the press total kilometres, and the thickness of every layer of blank flat of control, its principle is the rack drives gear is controlled moved cross beam 305 again by the rotary encoder counting a stroke, the gross pressure that moved cross beam 305 transmits from oil cylinder, bottom girder 306 usefulness steel plates welding annealing destressing forms the diameter 480mm of eight oil cylinders 307, oil pressure 26Mpa, produce four kiloton pressure.The frame 301 of whole press, fixed cross beam 302, heating platen 303, position control 304, moved cross beam 305, oil cylinder 307 all are installed on the base, and base is a reference for installation.In-line 308 hydraulic oil distribution of self-hydraulic system in the future arrives every oil cylinder 307, the metal hose that the oil heating pipe line will pass through diameter 28mm from the deep fat of heating system imports every heating platen 303, and simultaneous opening and closing device guarantees in the press uphill process, every laminate base simultaneously pressurized, be heated, and keep the stressed unanimity of every laminate base.
Unloader (Fig. 6) is fused unloader and hot press by link 401, guarantees that unloader has the weight of enough rigidity and stability, column 402 main support cages 403, piston oil-cylinder 408 (diameter 140/90mm, stroke 4500mm) and does the effect of the upper and lower guiding of cage.The position, ejecting plate transporter (power 2.2kw, 50 meters speed of per minute) 405 that the travel switch 404 of model 3SE3120-1UA is used for controlling cage sent synchromesh gear, the tooth bars (modulus 6) that unloader, longitudinally guiding wheel 406 make cage play stabilization, balanced controls 407 in upper and lower process with the slab in the cage and guaranteed to avoid cage because of reasons such as unbalance loading cause the inhomogeneous rising in the cage left and right sides, make cage can be parallel about; The piston rod of oil cylinder 408 is connected in cage, under the driving of oil pressure, makes cage upper and lower; The baffle plate frame 409 that shaped steel is welded is mainly used in avoids that the slab accident skids off in press decline process.

Claims (2)

1. the method for artificial board production line thermopress loading and unloading, it is characterized in that: lift is installed in advance [1], dolly loader [2], hot press [3] and unloader [4] combination, wherein: lift install in advance [1] form by two layers of dress plate transporter, after two layers of dress plate transporter are filled slab, move upward to the relevant position by the motor reducer that is loaded on a top of the trellis by four chains, two layers of dress plate transporter start the two laminate bases of packing into simultaneously in loader, packing into of two blocks of slabs finished in a lifting; Dolly loader [2] is made up of trolley type transporter, drive unit, trapped orbit and each support, after filling slab on every layer of trolley type transporter, drive unit is disposable to be pushed the trolley type transporter in the hot press, when retreating, also together it is withdrawed from by the trolley type transporter by drive unit, when withdrawing from, main drive roller on the trolley type transporter is equipped with ratchet mechanism and one of live-roller gear is housed, the rack drives gear, live-roller is reversed synchronously, slab is stayed in the hot press suppressed; When dolly loader [2] entered hot press [3], the slab that the push pedal device of trolley type transporter front end will suppress pushed unloader [4].
2. the unit of forming according to the method for the described artificial board production line thermopress of claim 1 loading and unloading is characterized in that described unit comprises that lift is installed [1] in advance, dolly loader [2], hot press [3] and unloader [4], wherein:
A, lift is installed [1] in advance: the drive unit [101] that is loaded on whole frame top connects four sprocket wheels drive chains by decelerator by axle and finishes liftable the connection with two layers of dress plate transporter [105], four columns that are welded by H shaped steel [103] and whole drive unit [101] and put on the shelf [102] are done to support and are connected, on four root posts, be welded with the guide plate of lifting dress plate transporter [105], at the drive unit chain other end counterweight [104] is housed, two layers of dress plate transporter [105] are fixed in the support [106], in support [106] side directive wheel is housed and is used to prevent adorn the gas circuit deviation correcting device [107] of plate transporter [105] belt deviation, travel switch frame [108] is housed in the middle of two root posts;
B, dolly loader [2]: form by put on the shelf [201], 12 root posts [202], the trolley track [203] that is fixed on column two limits, trolley type transporter [204], at a gear [205] that the band ratchet mechanism is housed of the main drive roller of trolley type transporter;
C, hot press [3]: the frame [301] of bearing all gross pressures of press is the structural members that are welded into by steel plate, multilayer fixed cross beam [302] and heating platen [303] are installed in the frame [301], [3041 connect with press and control the press total kilometres and control the thickness of every layer of blank flat by hydraulic pressure and electric control gear position control, whole press rack [301], fixed cross beam [302], heating platen [303], position control [304], moved cross beam [305], bottom girder [306] and oil cylinder [307] all are installed on the base of reference for installation, and in-line [308] joins with oil cylinder [307];
D, unloader [4]: link [401] fuses unloader [4] and hot press [3], upper and lower cage that slides [403] and oil cylinder [408] are installed in the centre of four root posts [402], the travel switch [404] that is used for controlling the position of cage is installed on cage [403] limit, the ejecting plate transporter [405] of slab in the cage being sent unloader is installed in the right side, longitudinally guiding wheel [406] is installed in cage, and [Bu And is near column [402] Di 403], and synchromesh gear, the tooth bar of balanced controls [407] is installed under the directive wheel [406] and two lateral surfaces of column [402]; The piston rod of oil cylinder [408] is connected in cage; Baffle plate frame [409] places between hot press [3] and the unloader [4].
CNB200510025367XA 2005-04-25 2005-04-25 Method of artificial board production line thermopress loading and unloading and machine set Expired - Fee Related CN100398285C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB200510025367XA CN100398285C (en) 2005-04-25 2005-04-25 Method of artificial board production line thermopress loading and unloading and machine set

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB200510025367XA CN100398285C (en) 2005-04-25 2005-04-25 Method of artificial board production line thermopress loading and unloading and machine set

Publications (2)

Publication Number Publication Date
CN1686690A CN1686690A (en) 2005-10-26
CN100398285C true CN100398285C (en) 2008-07-02

Family

ID=35304732

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB200510025367XA Expired - Fee Related CN100398285C (en) 2005-04-25 2005-04-25 Method of artificial board production line thermopress loading and unloading and machine set

Country Status (1)

Country Link
CN (1) CN100398285C (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100374266C (en) * 2006-03-30 2008-03-12 苏州苏福马机械有限公司 Method of reducing hydraulic system power of multi layer hot press and practical appts
CN101323126B (en) * 2007-06-11 2010-09-29 浙江贝亚克木业有限公司 Plate-accessing device in working procedure for pressing and sticking wood composite flooring
CN101288970B (en) * 2008-05-20 2011-11-16 马友成 Special device for manufacturing inorganic non-inflammable fire-resisting door
CN102211338A (en) * 2010-04-09 2011-10-12 赵星 Method for pressing bamboo curtain plywood by using plate blank assembly
IT1401172B1 (en) * 2010-07-02 2013-07-12 Imal Srl APPARATUS FOR HEATING OF MATTRESSES BASED ON INCORERENT WOODEN MATERIAL
CN102490242B (en) * 2011-12-28 2013-12-25 云南民汇投资开发有限公司 Cushion-plate-free loader for bamboo flakeboard
CN103252811B (en) * 2012-12-17 2015-04-29 宜兴市一洲木业有限公司 Hot-pressing production system for plywood for container bottom plates
CN106671219A (en) * 2017-01-16 2017-05-17 青岛豪润达木业有限公司 Hot press automatic production line
CN107030810A (en) * 2017-01-16 2017-08-11 青岛豪润达木业有限公司 A kind of hot press goes up board device and automatic assembly line automatically
CN107650235A (en) * 2017-04-28 2018-02-02 扬州快乐机械有限公司 A kind of oriented wood chipboard hot pressing unit
CN107053371B (en) * 2017-06-16 2022-06-28 漳州鑫华成机械制造有限公司 Low-carbon type plywood processing assembly line
CN107718229A (en) * 2017-11-21 2018-02-23 河南鑫饰板业有限公司 A kind of shovel board head on installation trolley
CN112092135A (en) * 2020-09-14 2020-12-18 广州飞柯科技有限公司 Wood fiberboard pressing device and production method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4042125A (en) * 1974-10-23 1977-08-16 Defibrator Ab Method and apparatus for stacking and feeding blanks to a tiered multi-opening press for the production of pressed board
US5044913A (en) * 1985-06-13 1991-09-03 Swanboard Masonite Ab Device at multi platen presses
CN2352317Y (en) * 1998-11-18 1999-12-08 福建省大田县金门油压机制造有限公司 Non-packing sheet type loading-unloading machine for artificial board hot-press
CN2509136Y (en) * 2001-10-16 2002-09-04 上海人造板机器厂 Super-thick layer copper-foil sheet coated dockboard
CN2622130Y (en) * 2003-06-19 2004-06-30 上海人造板机器厂有限公司 Lifting type conveyance machine for material feeding or discharging
CN2834846Y (en) * 2005-04-25 2006-11-08 上海人造板机器厂有限公司 A hot pressing unloading set of panel production line

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4042125A (en) * 1974-10-23 1977-08-16 Defibrator Ab Method and apparatus for stacking and feeding blanks to a tiered multi-opening press for the production of pressed board
US5044913A (en) * 1985-06-13 1991-09-03 Swanboard Masonite Ab Device at multi platen presses
CN2352317Y (en) * 1998-11-18 1999-12-08 福建省大田县金门油压机制造有限公司 Non-packing sheet type loading-unloading machine for artificial board hot-press
CN2509136Y (en) * 2001-10-16 2002-09-04 上海人造板机器厂 Super-thick layer copper-foil sheet coated dockboard
CN2622130Y (en) * 2003-06-19 2004-06-30 上海人造板机器厂有限公司 Lifting type conveyance machine for material feeding or discharging
CN2834846Y (en) * 2005-04-25 2006-11-08 上海人造板机器厂有限公司 A hot pressing unloading set of panel production line

Also Published As

Publication number Publication date
CN1686690A (en) 2005-10-26

Similar Documents

Publication Publication Date Title
CN100398285C (en) Method of artificial board production line thermopress loading and unloading and machine set
CN2834846Y (en) A hot pressing unloading set of panel production line
CN102328829B (en) Pallet loading and unloading device
CN101327662B (en) Mould-exchanging system of machine for coating and pressing vehicle door cover
CN107139280A (en) Plank charging discharging lift assembly
CN105501989B (en) Inorganic fire expanded perlite thermal-nsulation plate automatic docking device
CN204021950U (en) Translation stacker
CN203582045U (en) Lifting type drip irrigation tape loading machine
CN202943111U (en) Correcting device for bottom door of wagon
CN102626945B (en) Heat preservation block machine
CN107381079A (en) Robot palletizer
CN102490242B (en) Cushion-plate-free loader for bamboo flakeboard
CN202245359U (en) Automatic stacking device
CN103611904A (en) Transverse steel moving and billet discharging device
CN203359543U (en) Universal automatic plate stacking device suitable for block making machines of different types
CN203033295U (en) Conveying device
CN109353827B (en) Automatic precise spacing marshalling method for rail steel
CN206622536U (en) A kind of metal board beader feed mechanism
FI115616B (en) Method and apparatus for assembling and delivering a plywood veneer package to a veneer laminate press
CN105174263B (en) Continuous demolding mechanism and automatic casting molding assembly line comprising same
CN101734480A (en) Online vehicle upender
CN207273463U (en) A kind of special slab chain type pusher of stalk board
CN212266094U (en) Movable automatic plate loading machine of multilayer hot press
CN202428517U (en) Base plate-free loader for bamboo flake board
CN209887842U (en) Self-insulation building block production line

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080702

Termination date: 20150425