Method for quickly mounting capsule resin on separation area of top plate Download PDF

Info

Publication number
CN102587943A
CN102587943A CN201210071935XA CN201210071935A CN102587943A CN 102587943 A CN102587943 A CN 102587943A CN 201210071935X A CN201210071935X A CN 201210071935XA CN 201210071935 A CN201210071935 A CN 201210071935A CN 102587943 A CN102587943 A CN 102587943A
Authority
CN
China
Prior art keywords
pipe
anchoring agent
resin anchoring
district
anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201210071935XA
Other languages
Chinese (zh)
Other versions
CN102587943B (en
Inventor
陈晓祥
王明中
郑钧予
徐仪昌
刘军
范增哲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Zhongkuang Weite Mining Technology Development Co ltd
Original Assignee
Henan University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan University of Technology filed Critical Henan University of Technology
Priority to CN201210071935.XA priority Critical patent/CN102587943B/en
Publication of CN102587943A publication Critical patent/CN102587943A/en
Application granted granted Critical
Publication of CN102587943B publication Critical patent/CN102587943B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The invention discloses a method for quickly mounting capsule resin on a separation area of a roadway, a stope or a chamber in an anchor bolt and anchor cable supporting process. The method includes steps of inserting a PVC (polyvinyl chloride) or PPR (pentatricopeptide repeats) or sheet iron pipe with the outer diameter of 26mm and the inner diameter larger than 24mm in drill holes in advance until the pipe penetrates through the drilled holes of upper and lower rock strata of the separation area, holding the pipe by an operator via hands, and inserting the capsule resin into the pipe until the required capsule resin are totally inserted in the pipe; and inserting an anchor bolt or anchor cable into the pipe, starting a jumbolter, mounting the anchor bolt or anchor cable to an appointed position, unplugging the pipe after 5 minutes, and then mounting an anchor bolt or anchor cable tray to realize normal supporting. If another method is used for the separation area, safe and quick construction is difficult to be guaranteed. After the method is adopted, anchor bolt or anchor cable reinforcement can be carried out safely and quickly.

Description

A kind of roof delamination district resin anchoring agent method for rapidly mounting
Technical field
The present invention relates to a kind of roof delamination district resin anchoring agent method for rapidly mounting; Especially relate to a kind of in the tunnel, stope or chamber absciss layer district carry out the resin anchoring agent method for rapidly mounting in anchor pole, the cable bolting process, be used for the big zone of absciss layer that the underground geotechnical engineering in departments such as mine, building, water conservancy, railways adopts anchor pole, cable bolting process to run into and resin anchoring agent be installed comparatively under the situation of difficult.
Background technology
In the underground geotechnical engineering of departments such as mine, building, water conservancy, railway; If the support pattern that adopts is improper, tunnel or chamber pick open the back supporting untimely or receive mining influence after, back is easy to take place absciss layer, causes roadway deformation bigger; Bring hidden danger to safety in production; Therefore, just need expand and repair and reinforce, mend dozen anchor pole and anchor cable exactly and reinforce the most frequently used method to the tunnel; Mostly common in the market resin anchoring agent is that 500mm~600mm is long; And resin anchoring agent has certain flexible and easy crooked (see figure 1), so just give the anchoring agent mounting strap certain difficulty, if this type of regional dealing with improperly; Great amount of manpower and material have not only been wasted; Influence reinforcing speed, sometimes even missed the chance of best Strengthening Roof, back safety can not get ensureing; Must take special installation measure, could safely and fast the anchoring agent be in place.
Summary of the invention
Technical problem to be solved by this invention be how big absciss layer district (being meant that generally the absciss layer height is greater than 200mm) resin anchoring agent situation about having difficulties is installed; The method of Fast Installation roof delamination district resin anchoring agent; The coal mine roadway anchor pole that the present invention relates to, cable bolting are installed bore diameter and are generally 30~32mm, and anchor pole, anchor cable diameter are generally between 18~22mm.
In order to solve the problems of the technologies described above, the present invention provides a kind of roof delamination district resin anchoring agent method for rapidly mounting, and said roof delamination district resin anchoring agent method for rapidly mounting may further comprise the steps:
Step 1, be 26mm with external diameter in advance, internal diameter becomes the length section shape more smaller than head-room greater than the pipe intercepting of 24mm, and the pipe connecting hole of wearing is brought into work plane with subsequent use respectively stamping four apart from the position of pipe two cephalic par 5mm;
Step 2, constructor stand in the boring below, pipe are inserted boring, till pipe passes the boring in the upper and lower rock stratum, absciss layer district; Not enough like a tube length; Just another root pipe is docked with it; And pass four groups of corresponding pipe connecting holes of the two tubes of butt joint and tighten with the thin wire of four 0.5mm, and continue to insert pipe, repeat this step; Pass up to pipe till the boring of upper and lower rock stratum, absciss layer district, and guarantee that pipe is retained in more than the outside 100mm of boring;
Step 3, a human are held pipe in hand, and a people inserts resin anchoring agent from tube interior, till the resin anchoring agent of needs all inserts;
Step 4, anchor pole or anchor cable are inserted from tube interior, start jumbolter, anchor pole or anchor cable are mounted in the absciss layer district mantlerock, wait for after 5 minutes that pipe is extracted, and skyhook or anchor cable pallet carry out normal supporting.
Further, said pipe is PVC, PPR or sheet iron pipe.
Further, according to said step 1-4, cycling just can be accomplished the Fast Installation that whole absciss layer district carries out resin anchoring agent in anchor pole, the cable bolting process.
Beneficial effect of the present invention is:
Technical scheme of the present invention adopts pipe to pass in the boring in the upper and lower rock stratum, absciss layer district, the anchoring agent is inserted, because the support of pipe again; It is smooth to add tube wall, is beneficial to the anchoring agent and inserts fast, like this; Realized rapid construction, thereby back safety is protected.
Below in conjunction with the accompanying drawing and the specific embodiment the present invention is described in further detail.
Description of drawings
Fig. 1 is the sketch map that prior art is installed resin anchoring agent;
Fig. 2 is the sketch map that the present invention installs resin anchoring agent;
Fig. 3 is PVC, PPR or the sheet iron pipe butt joint sketch map that adopts among the present invention;
Fig. 4 is the A-A sectional view of Fig. 3.
Among the figure: 1, absciss layer district; 2, boring; 3, resin anchoring agent; 4, pipe; 5, pipe connecting hole; 6, thin wire.
The specific embodiment
As shown in Figure 2; Roof delamination provided by the invention district resin anchoring agent method for rapidly mounting; This method may further comprise the steps: the first step, be 26mm with external diameter in advance; Internal diameter becomes the length section shape more smaller than head-room (oversizely to be not easy to bring into working space greater than pipe 4 (this pipe is PVC, PPR or the sheet iron pipe) intercepting of 24mm; Too short section with section be connected more time-consuming), and four hole (see figure 3)s of wearing are brought into work plane with subsequent use respectively stamping apart from the position of 4 liang of cephalic par 5mm of pipe;
Second step: the constructor stands in boring 2 belows, pipe 4 is inserted boring 2, till pipe passes the boring 2 in the 1 upper and lower rock stratum, absciss layer district; Not enough like pipe 4 length; Just another root pipe 4 is docked with it; And pass four groups of corresponding pipe connecting holes 5 of the two tubes 4 of butt joint and tighten with the thin wire 6 of four 0.5mm, and continue to insert pipe 4, repeat this step; Pass up to pipe till the boring of upper and lower rock stratum, absciss layer district, and guarantee that pipe is retained in more than the outside 100mm of boring;
The 3rd step: a human is held pipe in hand, and a people inserts resin anchoring agent 3 from pipe 4 inside, till the resin anchoring agent 3 of needs all inserts;
The 4th step: anchor pole or anchor cable are inserted from pipe 4 inside, start jumbolter, anchor pole or anchor cable are mounted in the absciss layer district mantlerock, wait for after 5 minutes that pipe is extracted, and skyhook or anchor cable pallet carry out normal supporting;
The 5th step: according to aforementioned 1-4 step, cycling just can be accomplished the Fast Installation that whole absciss layer district 1 carries out resin anchoring agent 3 in anchor pole, the cable bolting process.
Protection domain of the present invention is not limited to the foregoing description, and every conspicuous technology distortion of doing according to know-why of the present invention all falls within protection scope of the present invention.

Claims (3)

1. a roof delamination district resin anchoring agent method for rapidly mounting is characterized in that, said roof delamination district resin anchoring agent method for rapidly mounting may further comprise the steps:
Step 1, be 26mm with external diameter in advance, internal diameter becomes the length section shape more smaller than head-room greater than the pipe intercepting of 24mm, and the pipe connecting hole of wearing is brought into work plane with subsequent use respectively stamping four apart from the position of pipe two cephalic par 5mm;
Step 2, constructor stand in the boring below, pipe are inserted boring, till pipe passes the boring in the upper and lower rock stratum, absciss layer district; Not enough like a tube length; Just another root pipe is docked with it; And pass four groups of corresponding pipe connecting holes of the two tubes of butt joint and tighten with the thin wire of four 0.5mm, and continue to insert pipe, repeat this step; Pass up to pipe till the boring of upper and lower rock stratum, absciss layer district, and guarantee that pipe is retained in more than the outside 100mm of boring;
Step 3, a human are held pipe in hand, and a people inserts resin anchoring agent from tube interior, till the resin anchoring agent of needs all inserts;
Step 4, anchor pole or anchor cable are inserted from tube interior, start jumbolter, anchor pole or anchor cable are mounted in the absciss layer district mantlerock, wait for after 5 minutes that pipe is extracted, and skyhook or anchor cable pallet carry out normal supporting.
2. roof delamination according to claim 1 district resin anchoring agent method for rapidly mounting is characterized in that, said pipe is PVC, PPR or sheet iron pipe.
3. roof delamination according to claim 1 and 2 district resin anchoring agent method for rapidly mounting is characterized in that, according to said step 1-4, cycling just can be accomplished the Fast Installation that whole absciss layer district carries out resin anchoring agent in anchor pole, the cable bolting process.
CN201210071935.XA 2012-03-19 2012-03-19 Method for quickly mounting capsule resin on separation area of top plate Expired - Fee Related CN102587943B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210071935.XA CN102587943B (en) 2012-03-19 2012-03-19 Method for quickly mounting capsule resin on separation area of top plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210071935.XA CN102587943B (en) 2012-03-19 2012-03-19 Method for quickly mounting capsule resin on separation area of top plate

Publications (2)

Publication Number Publication Date
CN102587943A true CN102587943A (en) 2012-07-18
CN102587943B CN102587943B (en) 2014-03-05

Family

ID=46477110

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210071935.XA Expired - Fee Related CN102587943B (en) 2012-03-19 2012-03-19 Method for quickly mounting capsule resin on separation area of top plate

Country Status (1)

Country Link
CN (1) CN102587943B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967509A (en) * 2014-05-15 2014-08-06 中国矿业大学(北京) Anchor pipe cable supporting structure capable of bearing lateral shear force
CN108678787A (en) * 2018-07-19 2018-10-19 开滦能源化工股份有限公司范各庄矿业分公司 Resin anchoring agent rapid installation device and construction method
CN109555547A (en) * 2018-11-22 2019-04-02 中国平煤神马能源化工集团有限责任公司 A kind of mounting device and installation method for wearing goaf resin explosive roll

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109441508B (en) * 2018-12-27 2020-02-04 中国矿业大学(北京) Device and method for anchoring large-diameter drill hole by using small-diameter anchor cable

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4139323A (en) * 1976-06-01 1979-02-13 Gebirgssicherung - Ges.M.B.H. Rock anchor
US4664555A (en) * 1985-03-05 1987-05-12 Dyckerhoff & Widmann Aktiengesellschaft Tension member for a rock anchor or the like
US5919005A (en) * 1997-07-02 1999-07-06 Integrated Stabilzation Technologies Inc. Ground anchor device for penetrating an underground rock formation
CN1734057A (en) * 2004-08-03 2006-02-15 神华集团有限责任公司 Mounting method for anchor cable support apparatus
CN200968218Y (en) * 2006-11-10 2007-10-31 李松强 Anchoring agent mounting device for mining
CN201013393Y (en) * 2007-01-16 2008-01-30 王海云 Mining resin roll holding pad
CN101250876A (en) * 2008-04-07 2008-08-27 中铁十三局集团第四工程有限公司 Method for installation of medicine volume anchor bar anchorage agent
CN202144592U (en) * 2011-07-04 2012-02-15 北京鑫实路桥建设有限公司 Seamless steel pipe type anchor rod for strengthening road rock slope

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4139323A (en) * 1976-06-01 1979-02-13 Gebirgssicherung - Ges.M.B.H. Rock anchor
US4664555A (en) * 1985-03-05 1987-05-12 Dyckerhoff & Widmann Aktiengesellschaft Tension member for a rock anchor or the like
US5919005A (en) * 1997-07-02 1999-07-06 Integrated Stabilzation Technologies Inc. Ground anchor device for penetrating an underground rock formation
CN1734057A (en) * 2004-08-03 2006-02-15 神华集团有限责任公司 Mounting method for anchor cable support apparatus
CN200968218Y (en) * 2006-11-10 2007-10-31 李松强 Anchoring agent mounting device for mining
CN201013393Y (en) * 2007-01-16 2008-01-30 王海云 Mining resin roll holding pad
CN101250876A (en) * 2008-04-07 2008-08-27 中铁十三局集团第四工程有限公司 Method for installation of medicine volume anchor bar anchorage agent
CN202144592U (en) * 2011-07-04 2012-02-15 北京鑫实路桥建设有限公司 Seamless steel pipe type anchor rod for strengthening road rock slope

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967509A (en) * 2014-05-15 2014-08-06 中国矿业大学(北京) Anchor pipe cable supporting structure capable of bearing lateral shear force
CN103967509B (en) * 2014-05-15 2016-03-02 中国矿业大学(北京) The anchor tube rope supporting and protection structure of cross shear can be born
CN108678787A (en) * 2018-07-19 2018-10-19 开滦能源化工股份有限公司范各庄矿业分公司 Resin anchoring agent rapid installation device and construction method
CN109555547A (en) * 2018-11-22 2019-04-02 中国平煤神马能源化工集团有限责任公司 A kind of mounting device and installation method for wearing goaf resin explosive roll

Also Published As

Publication number Publication date
CN102587943B (en) 2014-03-05

Similar Documents

Publication Publication Date Title
CN102678117B (en) Directional hydraulic fracturing method based on energizing blasting
CN102536239B (en) Long-wall working face coal pillar-free mining method
CN102182471B (en) Advance support method for coal mine tunnel high-risk area
CN105952451A (en) Air cushion type space-reserving approach road type mining device and method
WO2013102309A1 (en) Longwall working face, non-pillared mining method
CN103321654A (en) Method for managing roof collapse of coal mine roadway by aid of flexible air bags
CN100593630C (en) Caving zone edge inclined drill hole bushing burying method for extracting and discharging gas for goaf and adjacent layer
CN102322262A (en) Colliery isolated island coal column crossheading bump control method
CN104329113B (en) A kind of method of surface drilling standing seat earth release mash gas extraction
CN103032086A (en) Method for filling resin explosive cartridge in drilled hole of tunnel roof anchor rod
CN109209490B (en) Working face withdrawing method for gangue filling auxiliary end mining stage
CN105909254A (en) Outburst coal seam floor pitch-up through-bed directional hole leading area shield coal roadway driving method
CN103573270A (en) TBM (Tunnel Boring Machine) arc-shaped top shield and method for carrying out surrounding rock supporting by using top shield
CN102587943A (en) Method for quickly mounting capsule resin on separation area of top plate
CN102135005B (en) Method for supporting roof of roadway under coal pillar and gob transition section
CN102383728A (en) Coal mine rockburst defect segmentation and control method
CN107165661A (en) A kind of high-ground stress weak surrounding rock large deformation tunnel overlength enlarged footing anchor cable construction method
CN106014415A (en) Air cushion type space-reserved drift and fill type mining device and method
CN106121689A (en) A kind of excavation method of non-coal mine underground large stable chamber
CN103277129A (en) Technology preventing gas on upper corner of coal mining working face from exceeding limit
CN111502662A (en) Prevention and control method for deep pressure relief shallow part reinforcement of rock burst mine advanced coal body
CN102155249A (en) Method for supporting tunnel roof below mined-out area
CN204082088U (en) The sleeve pipe partition apparatus of cementing stage can be realized
US10774644B2 (en) System and method for forming a cavity in a backfilled stope
CN204552773U (en) Soft-broken rock body inbreak tunnelling combination steel bracket suspension device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20200527

Address after: 046000 No.4 commercial house, building 9, Beicheng street, Changzhi City, Shanxi Province (No.34, Xinying Street)

Patentee after: Shanxi Zhongkuang Weite Mining Technology Development Co.,Ltd.

Address before: 454003 No. 2001 Century Road, hi tech Zone, Henan, Jiaozuo

Patentee before: HENAN POLYTECHNIC University

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140305

CF01 Termination of patent right due to non-payment of annual fee