CN104070602B - Composite bed electric pole prepare maintaining process - Google Patents

Composite bed electric pole prepare maintaining process Download PDF

Info

Publication number
CN104070602B
CN104070602B CN201410279373.7A CN201410279373A CN104070602B CN 104070602 B CN104070602 B CN 104070602B CN 201410279373 A CN201410279373 A CN 201410279373A CN 104070602 B CN104070602 B CN 104070602B
Authority
CN
China
Prior art keywords
electric pole
epoxy resin
hollow lever
poured
resin layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410279373.7A
Other languages
Chinese (zh)
Other versions
CN104070602A (en
Inventor
魏明磊
孙辰军
李巍
徐磊
高冰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hengshui Power Supply Co of State Grid Hebei Electric Power Co Ltd
Original Assignee
Hengshui Power Supply Co of State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hengshui Power Supply Co of State Grid Hebei Electric Power Co Ltd filed Critical Hengshui Power Supply Co of State Grid Hebei Electric Power Co Ltd
Priority to CN201410279373.7A priority Critical patent/CN104070602B/en
Publication of CN104070602A publication Critical patent/CN104070602A/en
Application granted granted Critical
Publication of CN104070602B publication Critical patent/CN104070602B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B21/00Methods or machines specially adapted for the production of tubular articles
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/02Structures made of specified materials
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/02Structures made of specified materials
    • E04H12/12Structures made of specified materials of concrete or other stone-like material, with or without internal or external reinforcements, e.g. with metal coverings, with permanent form elements

Abstract

What the invention discloses a kind of composite bed electric pole prepares maintaining process, comprises the steps: A, first prepares regular reinforcement cement hollow lever, then at hollow lever upper epoxy resin; B, products obtained therefrom move into operation with high pressure room, and all standing joints cement layer on poured with epoxy resin layer, in the high-pressure sealed space that poured with epoxy resin layer is between cement layer and hollow lever; Bore operation is carried out in C, region, the center of circle on the cement layer of electric pole top or bottom, gets through hollow lever inner being communicated with ambient atmosphere.Electric pole of the present invention has the feature of natural curing, when winter low temperature and day and night difference variation makes hollow lever crack time, poured with epoxy resin layer outside hollow lever slowly infiltrates crackle naturally, especially when summer temp increases, epoxy resin fully infiltrates mended crack, reaches the natural curing effect of rhegma in winter, repairing in summer.

Description

Composite bed electric pole prepare maintaining process
Technical field
The present invention relates to electrical equipment technical field, especially a kind of high strength, composite bed electric pole prepare maintaining process.
Background technology
Concrete wire pole belongs to reinforced concrete structure.Concrete tensile strength is about 1/10th of compression strength.Concrete wire pole during load, be subject to the effect of tension in defeated, distribution line.The pulling force produced is throughout each position of concrete wire pole, and whole electric pole all belongs to tensile region.So concrete wire pole the whole body all needs to put into reinforcing bar, generally with round steel or screw-thread steel.Armored concrete can ftracture owing to creating tension in maintenance with during shrinking.If obtain meticulous maintenance, then both can prevent cracking, the qualification rate of product can have been improved again.Although present problem is complete in technological procedure well construction and maintenance aborning, product before dispatching from the factory through close inspection can be also all qualified, but in use still there will be crackle, and the degree of depth of crackle, width and length can be got over along with the increase of service life serious.Especially close in ground level less than about one meter this segment distance, the degree of crackle is more serious.What have has even been covered with a large amount of iron rust around crackle.
The area had, winter minimum temperature can reach subzero 30-40 degree sometimes, and day and night temperature can reach more than 15 DEG C.Under such weather conditions, because reinforcing bar is different with the rate of expanding with heat and contract with cold of cement, be easy to crack due to stress difference, the general undulate of crackle instead of rectilinear reason, then that the adhesion of these sands and stone surface is generally less than the adhesion of sand and stone inside owing to containing a large amount of sands and stone in concrete.Concrete is when stressed cracking, and crackle must appear at the surface of sand and stone, seldom appears at the centre of sand and stone, and naturally crackle also can be only waveform instead of rectilinear.In addition, the moisture infiltrated in crackle will freeze at night, turned to water again by day.In this change, because the volume of the volume ratio water of ice is large, so will make a volumetric work to external world when water becomes ice, often make a volumetric work, crackle will be broadened a bit, in the course of time, substantially reduces the service life of concrete wire pole.
Summary of the invention
The technical problem to be solved in the present invention be to provide a kind of high strength, composite bed electric pole prepare maintaining process.
For solving the problems of the technologies described above, the technical solution used in the present invention is as follows.
The preparation technology of composite bed electric pole, the method comprises the steps:
A, first prepare regular reinforcement cement hollow lever, then at hollow lever upper epoxy resin;
B, steps A products obtained therefrom move into operation with high pressure room, the air pressure controlling operation with high pressure indoor is 0.5-5MPa, under hyperbaric environment on poured with epoxy resin layer all standing joints cement layer, the top of this cement layer complete parcel poured with epoxy resin layer and hollow lever and bottom, in the high-pressure sealed space that poured with epoxy resin layer is between cement layer and hollow lever;
Bore operation is carried out in C, region, the center of circle on the cement layer of electric pole top or bottom, gets through hollow lever inner being communicated with ambient atmosphere.
As a preferred technical solution of the present invention, the ratio of the thickness three of the thickness of described cement layer, the thickness of poured with epoxy resin layer, hollow lever is 2:(0.4-0.7): (7.5-10).
As a preferred technical solution of the present invention, the ratio between cement layer thickness, poured with epoxy resin layer thickness, hollow lever thickness three is 2:0.6:8.4.
As a preferred technical solution of the present invention, the gross thickness of described cement layer, poured with epoxy resin layer, hollow lever three is determined according to following formula, unit employing centimetre:
Wherein, year maximum temperature difference be the annual temperature difference maximum that electric pole makes land used, unit adopt DEG C; Annual minimum temperature is the lowest temperature in winter that electric pole makes land used, and this numerical value is if positive number, then unification is designated as 1, as being negative, then gets its absolute value, unit employing DEG C; The whole height of electric pole is the design height of electric pole, and unit is centimetre; Body of rod thickness optimization constant value is 160000-170000.
As a preferred technical solution of the present invention, the value of described body of rod thickness optimization constant is 162000-168000.
As a preferred technical solution of the present invention, the value of described body of rod thickness optimization constant is 165000.
As a preferred technical solution of the present invention, in step B, the air pressure of described operation with high pressure indoor is 2MPa.
As a preferred technical solution of the present invention, in step C, the aperture of bore operation gained intercommunicating pore is 3-10mm.
As a preferred technical solution of the present invention, in step C, the aperture of bore operation gained intercommunicating pore is 5mm.
The maintaining process of above-mentioned composite bed electric pole, its main points comprise:
A, first take natural curing technique according to the design feature of electric pole, it mainly comprises: 1. cement layer and poured with epoxy resin layer play temperature buffer effect to the hollow lever as main stress mechanism, avoid hollow lever at low temperature and day and night difference variation is excessive time due to internal water silt particle grain and reinforcing bar stress difference and crack; 2. along with the growth of service life, when winter low temperature and day and night difference variation make the change of hollow lever internal stress finally cause cracking, poured with epoxy resin layer outside hollow lever slowly infiltrates crackle naturally, when summer temp increases, epoxy resin fully infiltrates mended crack, reaches the natural curing effect of rhegma in winter, repairing in summer;
B, detect electric pole there is serious crackle or deformation and fail nature maintenance time, carry out artificial maintenance, concrete grammar comprises: 1. heat and promote that epoxy resin infiltrates crackle and carries out nature reparation; 2. physics is reinforced; Do when being 3. difficult to reparation or high cost and scrap process.
The beneficial effect adopting technique scheme to produce is: electric pole of the present invention has excellent anti-crack effect, and service life increases greatly.First, cement layer and the poured with epoxy resin layer of electric pole play temperature buffer effect to the hollow lever as main stress mechanism, avoid hollow lever at low temperature and day and night difference variation is excessive time due to internal water silt particle grain and reinforcing bar stress difference and crack.Secondly, the present invention obtains following formula by a large amount of theory analysises and verification experimental verification,
According to the integral thickness of above-mentioned formula determination electric pole, the production for electric pole and similar devices has to be instructed and reference value greatly, is expected to be formed professional standard or country, international standard.Again, electric pole of the present invention also has the effect of self-maintenance, along with the growth of service life, when winter low temperature and day and night difference variation make the change of hollow lever internal stress finally cause cracking, epoxy resin outside hollow lever (reaches as high as more than 5MPa) and naturally slowly infiltrates crackle under High Pressure, when summer temp increases, epoxy resin fully infiltrates mended crack, reaches the natural curing effect of rhegma in winter, repairing in summer.
Accompanying drawing explanation
Fig. 1 is schematic appearance of the present invention.
Fig. 2 is the cross sectional representation of electric pole of the present invention.
In figure: 1, hollow lever; 2, poured with epoxy resin layer; 3, cement layer; 4, intercommunicating pore.
Detailed description of the invention
Referring to accompanying drawing, the structure of the present invention's specific embodiment comprises regular reinforcement cement hollow lever 1, poured with epoxy resin layer 2 and cement layer 3 is set gradually outside hollow lever 1, cement layer 3 carries out covering parcel to electric pole bottom and top simultaneously, in the confined space of poured with epoxy resin layer 2 between cement layer 3 and hollow lever 1, the pressure in this confined space is 2MPa; The ratio of cement layer 3 thickness, poured with epoxy resin layer 2 thickness, hollow lever 1 thickness three is 2:0.6:8.4.
The preparation technology of above-mentioned high strength cement electric pole, comprises the steps:
A, first prepare regular reinforcement cement hollow lever 1, then at hollow lever 1 upper epoxy resin;
B, steps A products obtained therefrom move into operation with high pressure room, the air pressure controlling operation with high pressure indoor is 2MPa, under hyperbaric environment on poured with epoxy resin layer 2 all standing joints cement layer 3, the top of this cement layer 3 complete parcel poured with epoxy resin layer 2 and hollow lever 1 and bottom, in the high-pressure sealed space that poured with epoxy resin layer 2 is between cement layer 3 and hollow lever 1;
Bore operation is carried out in C, region, the center of circle on the cement layer 3 of electric pole top or bottom, gets through hollow lever 1 inner being communicated with ambient atmosphere; The aperture of bore operation gained intercommunicating pore 4 is 5mm;
Wherein, the ratio between cement layer 3 thickness, poured with epoxy resin layer 2 thickness, hollow lever 1 thickness three is 2:0.6:8.4; The gross thickness of cement layer 3, poured with epoxy resin layer 2, hollow lever 1 three is determined according to following formula, unit employing centimetre:
Wherein, year maximum temperature difference be the annual temperature difference maximum that electric pole makes land used, unit adopt DEG C; Annual minimum temperature is the lowest temperature in winter that electric pole makes land used, and this numerical value is if positive number, then unification is designated as 1, as being negative, then gets its absolute value, unit employing DEG C; The whole height of electric pole is the design height of electric pole, and unit is centimetre; Body of rod thickness optimization constant value is 165000; Such as, North China, annual minimum temperature is about-10 DEG C, maximum temperature difference is about 10 DEG C, bar height 1000cm, then have 10 × 10 × 1000/16500=6.06cm, is the gross thickness of electric pole three-decker, respective thickness value can be obtained again, unit employing centimetre according to the thickness proportion of three layers.
The maintaining process of above-mentioned high strength cement electric pole, its main points comprise: A, first take natural curing technique according to the design feature of electric pole, 1. cement layer 3 and poured with epoxy resin layer 2 play temperature buffer effect to the hollow lever 1 as main stress mechanism, avoid hollow lever 1 at low temperature and day and night difference variation is excessive time due to internal water silt particle grain and reinforcing bar stress difference and crack; 2. along with the growth of service life, when winter low temperature and day and night difference variation make the change of hollow lever 1 internal stress finally cause cracking, poured with epoxy resin layer 2 outside hollow lever 1 slowly infiltrates crackle naturally, when summer temp increases, epoxy resin fully infiltrates mended crack, reaches the natural curing effect of rhegma in winter, repairing in summer.B, detect electric pole there is serious crackle or deformation and fail nature maintenance time, carry out artificial maintenance, concrete grammar comprises: 1. heat and promote that epoxy resin infiltrates crackle and carries out nature reparation; 2. physics is reinforced; Do when being 3. difficult to reparation or high cost and scrap process.
No matter for the improvement of wire pole structure, or to the exploration of its preparation technology, the present invention, all to the innovative design that the prior art of industry is given prominence to, has obvious facilitation for electric pole manufacturing technology field, is expected to the planning equalization standard becoming the industry.
Foregoing description only proposes, not as the single restrictive condition to its technical scheme itself as the enforceable technical scheme of the present invention.

Claims (9)

1. the preparation technology of composite bed electric pole, is characterized in that: the method comprises the steps:
A, first prepare regular reinforcement cement hollow lever (1), then at hollow lever (1) upper epoxy resin;
B, steps A products obtained therefrom move into operation with high pressure room, the air pressure controlling operation with high pressure indoor is 0.5-5MPa, at the upper all standing joints cement layer (3) of poured with epoxy resin layer (2) under hyperbaric environment, the top of this cement layer (3) complete parcel poured with epoxy resin layer (2) and hollow lever (1) and bottom, in the high-pressure sealed space that poured with epoxy resin layer (2) is between cement layer (3) and hollow lever (1);
Bore operation is carried out in C, region, the center of circle on the cement layer (3) of electric pole top or bottom, gets through hollow lever (1) inner being communicated with ambient atmosphere;
The gross thickness of described cement layer (3), poured with epoxy resin layer (2), hollow lever (1) three is determined according to following formula, unit employing centimetre:
Wherein, year maximum temperature difference be the annual temperature difference maximum that electric pole makes land used, unit adopt DEG C; Annual minimum temperature is the lowest temperature in winter that electric pole makes land used, and this numerical value is if positive number, then unification is designated as 1, as being negative, then gets its absolute value, unit employing DEG C; The whole height of electric pole is the design height of electric pole, and unit is centimetre; Body of rod thickness optimization constant value is 160000-170000, and the unit of body of rod thickness optimization constant is DEG C -2.
2. the preparation technology of composite bed electric pole according to claim 1, is characterized in that: the ratio of the thickness three of the thickness of described cement layer (3), the thickness of poured with epoxy resin layer (2), hollow lever (1) is 2:(0.4-0.7): (7.5-10).
3. the preparation technology of composite bed electric pole according to claim 2, is characterized in that: the ratio between cement layer (3) thickness, poured with epoxy resin layer (2) thickness, hollow lever (1) thickness three is 2:0.6:8.4.
4. the preparation technology of composite bed electric pole according to claim 1, is characterized in that: the value of described body of rod thickness optimization constant is 162000-168000.
5. the preparation technology of composite bed electric pole according to claim 1, is characterized in that: the value of described body of rod thickness optimization constant is 165000.
6. high strength cement electric pole according to claim 1, is characterized in that: in step B, and the air pressure of described operation with high pressure indoor is 2MPa.
7. the preparation technology of composite bed electric pole according to claim 1, is characterized in that: in step C, and the aperture of bore operation gained intercommunicating pore (4) is 3-10mm.
8. the preparation technology of composite bed electric pole according to claim 7, is characterized in that: in step C, and the aperture of bore operation gained intercommunicating pore (4) is 5mm.
9. the maintaining process of electric pole prepared by claim 1, is characterized in that:
A, first take natural curing technique according to the design feature of electric pole, it mainly comprises: 1. cement layer (3) and poured with epoxy resin layer (2) play temperature buffer effect to the hollow lever (1) as main stress mechanism, avoid hollow lever (1) at low temperature and day and night difference variation is excessive time due to internal water silt particle grain and reinforcing bar stress difference and crack; 2. along with the growth of service life, when winter low temperature and day and night difference variation make the change of hollow lever (1) internal stress finally cause cracking, the poured with epoxy resin layer (2) in hollow lever (1) outside slowly infiltrates crackle naturally, when summer temp increases, epoxy resin fully infiltrates mended crack, reaches the natural curing effect of rhegma in winter, repairing in summer;
B, detect electric pole there is serious crackle or deformation and fail nature maintenance time, carry out artificial maintenance, concrete grammar comprises: 1. heat and promote that epoxy resin infiltrates crackle and carries out nature reparation; 2. physics is reinforced; Do when being 3. difficult to reparation or high cost and scrap process.
CN201410279373.7A 2014-06-20 2014-06-20 Composite bed electric pole prepare maintaining process Active CN104070602B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410279373.7A CN104070602B (en) 2014-06-20 2014-06-20 Composite bed electric pole prepare maintaining process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410279373.7A CN104070602B (en) 2014-06-20 2014-06-20 Composite bed electric pole prepare maintaining process

Publications (2)

Publication Number Publication Date
CN104070602A CN104070602A (en) 2014-10-01
CN104070602B true CN104070602B (en) 2016-03-02

Family

ID=51592414

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410279373.7A Active CN104070602B (en) 2014-06-20 2014-06-20 Composite bed electric pole prepare maintaining process

Country Status (1)

Country Link
CN (1) CN104070602B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108915340A (en) * 2018-04-03 2018-11-30 合肥海银杆塔有限公司 A kind of novel and multifunctional shaft tower in city

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04191041A (en) * 1990-11-27 1992-07-09 Nkk Corp Heat resistant plastic-clad steel pipe
US5556673A (en) * 1991-07-08 1996-09-17 Compagnie Generale D'innovation Et De Developpement Cogidev Transparent composite structural elements and methods for producing same
JP2002054766A (en) * 2000-08-09 2002-02-20 Nittetsu Corrosion Prevention Co Ltd Steel pipe covered with highly anticorrosion metal and manufacturing method therefor
CN101870799A (en) * 2010-07-07 2010-10-27 淮北科奥工程建设有限公司 Modified epoxy resin composite for strengthening concrete pole
CN101967901A (en) * 2010-10-20 2011-02-09 常熟风范电力设备股份有限公司 Composite tower
CN202064678U (en) * 2010-11-18 2011-12-07 常熟风范电力设备股份有限公司 Novel electric pole
CN202493070U (en) * 2012-04-04 2012-10-17 张雪燕 Pouring cement telegraph pole
CN103711354A (en) * 2013-12-27 2014-04-09 曾义强 Composite telegraph pole/street lamp pole and manufacturing method of street lamp pole

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04191041A (en) * 1990-11-27 1992-07-09 Nkk Corp Heat resistant plastic-clad steel pipe
US5556673A (en) * 1991-07-08 1996-09-17 Compagnie Generale D'innovation Et De Developpement Cogidev Transparent composite structural elements and methods for producing same
JP2002054766A (en) * 2000-08-09 2002-02-20 Nittetsu Corrosion Prevention Co Ltd Steel pipe covered with highly anticorrosion metal and manufacturing method therefor
CN101870799A (en) * 2010-07-07 2010-10-27 淮北科奥工程建设有限公司 Modified epoxy resin composite for strengthening concrete pole
CN101967901A (en) * 2010-10-20 2011-02-09 常熟风范电力设备股份有限公司 Composite tower
CN202064678U (en) * 2010-11-18 2011-12-07 常熟风范电力设备股份有限公司 Novel electric pole
CN202493070U (en) * 2012-04-04 2012-10-17 张雪燕 Pouring cement telegraph pole
CN103711354A (en) * 2013-12-27 2014-04-09 曾义强 Composite telegraph pole/street lamp pole and manufacturing method of street lamp pole

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
孙俊毅.水泥电线杆裂纹的成因及防治.《阴山学刊&#8226 *
自然科学版》.1998,第14卷(第3期),第157-159页. *

Also Published As

Publication number Publication date
CN104070602A (en) 2014-10-01

Similar Documents

Publication Publication Date Title
CN103867019A (en) Assembly type external prestressing active powder concrete wind power tower
CN102493602A (en) Ductile concrete column capable of delaying local buckling of steel bars and manufacturing method thereof
CN103015414B (en) A kind of precast concrete post grouting pile and grouting process
CN104070602B (en) Composite bed electric pole prepare maintaining process
CN104278794A (en) Prefabricated thermal insulation laminated wallboard with spatial three-dimensional structure and manufacturing method of laminated wallboard
CN104005407A (en) Partially prestressed concrete structure foundation pile
CN203977957U (en) A kind of high strength cement electric pole
CN103452326B (en) Overlength davit is along way construction method and equipment thereof
CN203514143U (en) Precast cement road panel for rapid maintenance of pavement
CN104074387B (en) High strength cement electric pole and maintaining process thereof
CN103741708A (en) Prefabricated concrete pole sleeve base
CN204282845U (en) Buildings in cold roof insulating structure
CN204238264U (en) A kind of sole plate post-poured strip structure
CN202658947U (en) Annular concrete-filled steel tube strut for catenary
CN202214986U (en) Carbon fiber composite material arm support for concrete pump truck
CN203684258U (en) Prefabricated concrete rod sleeve foundation
CN204703363U (en) Energy-saving wall heat insulation building block
CN204401627U (en) To pull-type prestressed pipe pile pit supporting construction
CN204001926U (en) Light-duty complex cement bar
CN103498573B (en) Set up the existing frame strengthening method of band frame bracing members
CN202265839U (en) Glass reinforced plastic underground magnetic room for earthquake monitoring
CN103696611A (en) Base structure for steel tube tower
CN205314128U (en) Plastic power communication well of integral type
CN204152073U (en) A kind of prefabricated thermal insulation composite wallboard of carrying space three-dimensional structure
CN103465357B (en) A kind of precast hollow concrete structure inner chamber core tire

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant