CN104078893A - Vertical well cable construction device used for high-rise building - Google Patents

Vertical well cable construction device used for high-rise building Download PDF

Info

Publication number
CN104078893A
CN104078893A CN201410327601.3A CN201410327601A CN104078893A CN 104078893 A CN104078893 A CN 104078893A CN 201410327601 A CN201410327601 A CN 201410327601A CN 104078893 A CN104078893 A CN 104078893A
Authority
CN
China
Prior art keywords
piece
cable
spacing
skyscraper
spacing single
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410327601.3A
Other languages
Chinese (zh)
Other versions
CN104078893B (en
Inventor
田志家
孔永昌
汤浪洪
刘洋
鲁黎明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fifth Bureau Installation Engineering Co Ltd
Original Assignee
China Construction Fifth Bureau Third Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fifth Bureau Third Construction Co Ltd filed Critical China Construction Fifth Bureau Third Construction Co Ltd
Priority to CN201410327601.3A priority Critical patent/CN104078893B/en
Publication of CN104078893A publication Critical patent/CN104078893A/en
Application granted granted Critical
Publication of CN104078893B publication Critical patent/CN104078893B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention provides a vertical well cable construction device used for a high-rise building. The vertical well cable construction device comprises fender bracket units. Each fender bracket unit comprises a bent frame crosspiece, a first limiting part and a second limiting part, wherein each first limiting part comprises two first limiting units, the first limiting units are arranged between the bent frame crosspieces and the wall of the high-rise building, each second limiting part comprises two second limiting units, the two ends of the second limiting units are arranged on the first limiting units respectively, through holes are formed between the first limiting units and the second limiting units, and the through holes in every two adjacent fender bracket units are coaxially arranged. The vertical well cable construction device is simplified in overall structure; rows of cables can be constructed and laid from one end to the other end through the design of installation holes, and the construction efficiency is improved; the through holes are formed between the first limiting units and the second limiting units, large-amplitude shifting in the cable or cable set lifting process can be prevented, the damage probability of the cables is reduced, and the construction efficiency is further improved.

Description

A kind of borehole cable constructing device for skyscraper
Technical field
The present invention relates to Architectural Equipment field, especially, relate to a kind of borehole cable constructing device for skyscraper.
Background technology
Along with economic development, skyscraper is more and more in daily life, and the power supply of skyscraper, communication cable and the device for installing cables seem particularly important.
For the laying installation of high-rise borehole cable, in prior art, be on cable, to adhere to steel wire, adopt hoist engine haulage cable, reach the object of trailing cable, but because cable does not limit hanging its running route in the process of liter, cable easily produces and rocks, the cable causing with pipe well floor collision and the fixture of steel wire knocks or the situation of scratch cable skin occurs often, therefore, need to be each storey setting nurse personnel, adopt the mode of crawl hoist engine to carry out crane cable, though this kind of mode can prevent that cable is damaged to a certain extent, but efficiency of construction is low, hoisting cost is high.
Therefore, design and a kind ofly can guarantee that the not impaired while of cable can be improved again efficiency of construction and be reduced the device of hoisting cost and have great importance.
Summary of the invention
The object of the invention is to provide a kind of can guarantee that the not impaired while of cable can improve again efficiency of construction and reduce the borehole cable constructing device for skyscraper of hoisting cost, and concrete technical scheme is as follows:
For a borehole cable constructing device for skyscraper, comprise 1 group or at least 2 group fender bracket single-pieces, two adjacent groups fender bracket single-piece is connected or separate setting successively along the short transverse of skyscraper;
Described fender bracket single-piece comprises framed bent crosspiece, first group of limiting component and second group of limiting component, and described framed bent crosspiece equal intervals is provided with at least 2 installing holes; Described first group of limiting component comprises two the first spacing single-pieces that are set up in parallel and parallel with horizontal plane, and the front end of described the first spacing single-piece is connected with described installing hole by positioner is movable, and its end is arranged on the metope of skyscraper;
Described second group of limiting component comprise be set up in parallel and all with mutually vertically disposed two the second spacing single-pieces of described the first spacing single-piece, the two ends of described the second spacing single-piece are separately positioned in described the first spacing single-piece;
Between described the first spacing single-piece and described the second spacing single-piece, form through hole, described through hole be of a size of cable or cable group size 1.2-20 doubly;
Described through hole concentric in two adjacent groups fender bracket single-piece arranges.
Preferred in above technical scheme, described the first spacing single-piece is gag lever post, and described the second spacing single-piece is roller.
Preferred in above technical scheme, the nut that described the second spacing single-piece matches by screw rod and with it is arranged in described the first spacing single-piece.
Preferred in above technical scheme, described the first spacing single-piece is provided with the slotted hole along its axis direction, and described slotted hole setting is run through at the two ends of described screw rod, and described nut is arranged on described screw rod and is positioned at the outside of described the first spacing single-piece.
Preferred in above technical scheme, in described the first spacing single-piece, be equipped with scratch resistant guard block.
Preferred in above technical scheme, described scratch resistant guard block is the guard ring of PET material.
Preferred in above technical scheme, described scratch resistant guard block is fixed in described the first spacing single-piece by welding manner.
Preferred in above technical scheme, the two ends of described framed bent crosspiece are fixed on the metope of skyscraper by fixed part respectively.
Preferred in above technical scheme, described positioner is movably arranged on described framed bent crosspiece by bolt.
The present invention has following beneficial effect:
(1) the borehole cable constructing device for skyscraper of the present invention, comprise 1 group or at least 2 group fender bracket single-pieces, two adjacent groups fender bracket single-piece is connected or separate setting successively along the short transverse of skyscraper, fender bracket single-piece comprises framed bent crosspiece, first group of limiting component and second group of limiting component, and overall structure is simplified; Described framed bent crosspiece equal intervals is provided with at least 2 installing holes, can realize fender bracket single-piece and be moved along framed bent crosspiece axial direction, realizes cable in a row and discharges toward the other end from one end, improves efficiency of construction, reduces costs; Between described the first spacing single-piece and described the second spacing single-piece, form through hole, described through hole be of a size of cable or cable group size 1.2-20 doubly, can guarantee cable or cable group from through hole through and not damaged; Described through hole concentric in two adjacent groups fender bracket single-piece arranges, and organizes when fender bracket single-piece arranges more and keeps concentric, prevents that cable or cable group hoisting process from significantly skew occurring, and reduces its impaired probability, further improves efficiency of construction.
(2) in the present invention, the first spacing single-piece is gag lever post, the second spacing single-piece is roller, in view of cable or cable group are rocked taking front and back as main in uphill process, adopt arranging of roller to reduce the phase mutual friction in lifting process, greatly reduce cable or the impaired probability of cable group.
(3) nut that in the present invention, the second spacing single-piece matches by screw rod and with it is arranged in described the first spacing single-piece, easy for installation.
(4) in the present invention, the first spacing single-piece is provided with along the slotted hole of its axis mode, described slotted hole setting is run through at the two ends of described screw rod, described nut is arranged on described screw rod and is positioned at the outside of described the first spacing single-piece, the design of slotted hole is convenient to adjust according to the actual requirements 2 distances between the second spacing single-piece, ensure that cable or cable group can keep vertical-lift, reduce its rocking in lifting process, further improve efficiency of construction.
(5) in the present invention, in the first spacing single-piece, be equipped with scratch resistant guard block, the design of scratch resistant guard block, has avoided cable or cable group that left and right rocking occurs in lifting process and with the first spacing single-piece, the damage that friction causes has occurred; Scratch resistant guard block is selected the guard ring of PET material, when cable or cable group are in contact with it, rubs little; Scratch resistant guard block is fixed in described the first spacing single-piece by welding manner, difficult drop-off, and steadiness is good.
(6) in the present invention, the two ends of framed bent crosspiece are fixed on the metope of skyscraper by fixed part respectively, easy for installation, and bear part active force, good stability by fixed part.
(7) in the present invention, positioner is movably arranged on described framed bent crosspiece by bolt, and installation and removal are convenient.
Except object described above, feature and advantage, the present invention also has other object, feature and advantage.Below with reference to figure, the present invention is further detailed explanation.
Brief description of the drawings
The accompanying drawing that forms the application's a part is used to provide a further understanding of the present invention, and schematic description and description of the present invention is used for explaining the present invention, does not form inappropriate limitation of the present invention.In the accompanying drawings:
Fig. 1 is the structural representation of the borehole cable constructing device use procedure for skyscraper of the preferred embodiment of the present invention 1;
Fig. 2 is that the A of Fig. 1 is to view;
Fig. 3 is the B-B cutaway view of Fig. 1;
11-framed bent crosspiece, 111-installing hole, first group of limiting component of 12-, the spacing single-piece of 121-first, 122-slotted hole, second group of limiting component of 13-, the spacing single-piece of 131-second, 132-screw rod, 133-nut, 14-positioner, 141-bolt, 15-through hole, 16-fixed part, 01-skyscraper, 02-ladder, 03-cable or cable group.
Embodiment
Below in conjunction with accompanying drawing, embodiments of the invention are elaborated, but the multitude of different ways that the present invention can limit and cover according to claim is implemented.
Embodiment 1:
A kind of borehole cable constructing device for skyscraper; structural representation when it is installed on skyscraper 01 metope refers to Fig. 1, Fig. 2 and Fig. 3; specifically comprise 1 group or at least 2 group fender bracket single-pieces; two adjacent groups fender bracket single-piece can separately arrange along the short transverse of skyscraper 01; also can connect successively, can also adopt other mode to connect.
Described fender bracket single-piece comprises framed bent crosspiece 11, first group of limiting component 12 and second group of limiting component 13, and overall structure is simplified.
Ladder 02 concentric setting on described framed bent crosspiece 11 and skyscraper 01, and 1.2-2.0 times of its length L 2 length L 1 that be ladder 02; Described framed bent crosspiece 11 equal intervals are provided with at least 2 installing holes 111; Described first group of limiting component 12 comprises two the first spacing single-pieces 121 that are set up in parallel and parallel with horizontal plane, the front end of described the first spacing single-piece 121 is movably arranged on by bolt 141 in described installing hole 111 through positioner 14, its end is arranged on the metope of skyscraper 01, can realize fender bracket single-piece is moved along framed bent crosspiece 11 axial directions, realizing cable in a row discharges toward the other end from one end, improve efficiency of construction, reduce costs; By bolt 141, installation and removal are convenient.
Described second group of limiting component 13 comprise be set up in parallel and all with mutual vertically disposed two the second spacing single-pieces 131 of described the first spacing single-piece 121, the two ends of described the second spacing single-piece 131 are separately positioned in described the first spacing single-piece 121; Between described the first spacing single-piece 121 and described the second spacing single-piece 131, form through hole 15, described through hole 15 be of a size of cable or cable group 03 size 1.2-20 doubly, can guarantee cable or cable group 03 from through hole 15 through and not damaged.
Described through hole 15 concentric settings in two adjacent groups fender bracket single-piece, organize when fender bracket single-piece arranges more and keep concentric, prevent that cable or cable group 03 hoisting process from significantly skew occurring, and reduce its impaired probability, further improve efficiency of construction.
Described the first spacing single-piece 121 is selected gag lever post, and on it, be equipped with scratch resistant guard block, described scratch resistant guard block is the guard ring of PET material, described guard ring is fixed in described the first spacing single-piece 121 by welding manner, the design of scratch resistant guard block, has avoided cable or cable group 03 that left and right rocking occurs in lifting process and with the first spacing single-piece, the damage that friction causes has occurred; Scratch resistant guard block is selected the guard ring of PET material, when cable or cable group 03 are in contact with it, rubs little; Scratch resistant guard block is fixed in described the first spacing single-piece 121 by welding manner, difficult drop-off, and steadiness is good.
Described the second spacing single-piece 131 is selected roller, can also select according to the actual requirements the parts that are similar to roller and so on, in view of cable or cable group 03 are rocked taking front and back as main in uphill process, adopt arranging of roller to reduce the phase mutual friction in lifting process, greatly reduce cable or the impaired probability of cable group 03.
Described the second spacing single-piece 131 is arranged in described the first spacing single-piece 121 by screw rod 132 and the nut 133 that matches with it, concrete set-up mode is: described the first spacing single-piece 121 is provided with along the slotted hole 122 of its axis L direction, the two ends of described screw rod 132 are run through described slotted hole 122 and are arranged, described nut 133 is arranged on described screw rod 132 and is positioned at the outside of described the first spacing single-piece 121, be fixed by screw rod 132 and nut 133, be convenient to installation and removal; In conjunction with the design of slotted hole 122, be convenient to adjust according to the actual requirements 2 distances between the second spacing single-piece again, ensure that cable or cable group 03 can keep vertical-lift, reduce its rocking in lifting process, further improve efficiency of construction.
The two ends of described framed bent crosspiece 11 are fixed on the metope of skyscraper 01 by fixed part 16 respectively, easy for installation, and bear part active force, good stability by fixed part 16.
Apply the borehole cable constructing device for skyscraper of the present invention, concrete installation process is as follows:
The end of the first spacing single-piece 121 is fixed on the metope of skyscraper 01, its front end is fixed on installing hole 111 places of described framed bent crosspiece 11 by bolt 141 by positioner 14; The guard ring of PET material is welded in the first spacing single-piece 121; The second spacing single-piece 131 is fixed between two the first spacing single-pieces 121 by screw rod 132 and nut 133, forms the through hole 15 of 1.2-20 times of the size that is of a size of cable or cable group 03 between described the first spacing single-piece 121 and described the second spacing single-piece 131; The two ends of described framed bent crosspiece 11 are fixed on by fixed part 16 on the metope of skyscraper 01, and the ladder 02 concentric setting on described framed bent crosspiece 11 and skyscraper 01, described fixed part 16 and described framed bent crosspiece 11 form the overall structure of a sealing.
Borehole cable constructing device use procedure for skyscraper of the present invention is as follows:
(1) first fender bracket single-piece is assembled on the floor metope of 3 layers at skyscraper 01, the borehole cable that forms skyscraper 01 use discharges guiding framed bent;
(2) while discharging cable or cable group 03, cable or cable group 03 are passed from through hole 15, do not contact with each wall of through hole 15 as far as possible;
(3) in cable or cable group 03 lifting process, if generation double swerve, be limited in moving in two the first spacing single-piece 121 scopes, because being welded with the guard ring of PET material on it, can avoid scratching in lifting process the skin of cable or cable group 03; If rock before and after occurring, the scope that is limited in two the second spacing single-pieces 131 is interior mobile, generally the spacing between two the second spacing single-pieces 131 is less than two spacing between the first spacing single-piece 121, cable or cable group 03 are generally rocked taking front and back as main, the second spacing single-piece 131 adopts roller design, the rolling effect that it has can reduce the friction of lifting process, the skin that can avoid scratching in lifting process cable or cable group 03, can also play certain guide effect.
Therefore, apply the borehole cable constructing device for skyscraper of the present invention, there is following technique effect:
1, simplify for the overall structure of the borehole cable constructing device of skyscraper, production cost is low.
2, the spacing and guide effect of playing by the first spacing single-piece 121 and the second spacing single-piece 131, greatly reduce cable or cable group 03 lifts resistance and lateral shift, and make cable or cable group 03 lay one-time-reach-place, avoid rocking in cable or cable group 03 lifting process, thus avoid cable or cable group 03 damaged.
3, the spacing and guide effect of playing by the first spacing single-piece 121 and the second spacing single-piece 131, cable or cable group 03 scratching in hoistway are stopped, do not need to nurse personnel in storey setting while construction as traditional cable, reducing labour drops into, evade the potential safety hazard of construction, increased work efficiency.
4, in cable or cable group 03 lifting process, do not need to adopt crawl hoist engine but once lifting put in place, accelerated cable or cable group 03 installation rate, increase work efficiency.
The foregoing is only the preferred embodiments of the present invention, be not limited to the present invention, for a person skilled in the art, the present invention can have various modifications and variations.Within the spirit and principles in the present invention all, any amendment of doing, be equal to replacement, improvement etc., within all should being included in protection scope of the present invention.

Claims (9)

1. for a borehole cable constructing device for skyscraper, it is characterized in that: comprise 1 group or at least 2 group fender bracket single-pieces, two adjacent groups fender bracket single-piece is connected or separate setting successively along the short transverse of skyscraper;
Described fender bracket single-piece comprises framed bent crosspiece (11), first group of limiting component (12) and second group of limiting component (13), and described framed bent crosspiece (11) equal intervals is provided with at least 2 installing holes (111); Described first group of limiting component (12) comprises two the first spacing single-pieces (121) that are set up in parallel and parallel with horizontal plane, the front end of described the first spacing single-piece (121) is connected with described installing hole (111) by positioner (14), and its end is arranged on the metope of skyscraper;
Described second group of limiting component (13) comprise be set up in parallel and all with mutually vertically disposed two the second spacing single-pieces (131) of described the first spacing single-piece (121), the two ends of described the second spacing single-piece (131) are separately positioned in described the first spacing single-piece (121);
Between described the first spacing single-piece (121) and described the second spacing single-piece (131), form through hole (15), described through hole (15) be of a size of cable or cable group size 1.2-20 doubly;
Described through hole (15) concentric setting in two adjacent groups fender bracket single-piece.
2. the borehole cable constructing device for skyscraper according to claim 1, is characterized in that: described the first spacing single-piece (121) is gag lever post, and described the second spacing single-piece (131) is roller.
3. the borehole cable constructing device for skyscraper according to claim 2, is characterized in that: described the second spacing single-piece (131) is arranged in described the first spacing single-piece (121) by screw rod (132) and the nut (133) that matches with it.
4. the borehole cable constructing device for skyscraper according to claim 3, it is characterized in that: described the first spacing single-piece (121) is provided with along the slotted hole (122) of its axis (L) direction, described slotted hole (122) setting is run through at the two ends of described screw rod (132), and described nut (133) is arranged on described screw rod (132) above and is positioned at the outside of described the first spacing single-piece (121).
5. according to the borehole cable constructing device for skyscraper described in claim 1-4 any one, it is characterized in that: in described the first spacing single-piece (121), be equipped with scratch resistant guard block.
6. the borehole cable constructing device for skyscraper according to claim 5, is characterized in that: described scratch resistant guard block is the guard ring of PET material.
7. the borehole cable constructing device for skyscraper according to claim 6, is characterized in that: described scratch resistant guard block is fixed in described the first spacing single-piece (121) by welding manner.
8. the borehole cable constructing device for skyscraper according to claim 5, is characterized in that: the two ends of described framed bent crosspiece (11) are fixed on the metope of skyscraper by fixed part (16) respectively.
9. the borehole cable constructing device for skyscraper according to claim 5, is characterized in that: described positioner (14) is movably arranged on described framed bent crosspiece (11) by bolt (141).
CN201410327601.3A 2014-07-10 2014-07-10 Vertical well cable construction device used for high-rise building Active CN104078893B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410327601.3A CN104078893B (en) 2014-07-10 2014-07-10 Vertical well cable construction device used for high-rise building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410327601.3A CN104078893B (en) 2014-07-10 2014-07-10 Vertical well cable construction device used for high-rise building

Publications (2)

Publication Number Publication Date
CN104078893A true CN104078893A (en) 2014-10-01
CN104078893B CN104078893B (en) 2017-01-25

Family

ID=51600008

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410327601.3A Active CN104078893B (en) 2014-07-10 2014-07-10 Vertical well cable construction device used for high-rise building

Country Status (1)

Country Link
CN (1) CN104078893B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110323704A (en) * 2019-07-01 2019-10-11 浙江省建设机械集团有限公司 A kind of fixed device of cable and its application method
CN113036662A (en) * 2021-03-11 2021-06-25 湖南天禹设备安装有限公司 Spacing, guider are used in high-rise shaft cable direction construction

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6729606B1 (en) * 1999-08-10 2004-05-04 I.C.M. Group Device for guiding at least a flexible elongated element such as a cable or the like, with substantially closed contour
JP2009171820A (en) * 2008-01-10 2009-07-30 Higashida Shoko Kk Cable laying method using cable grip
CN102332691A (en) * 2011-09-19 2012-01-25 中建五局工业设备安装有限公司 Auxiliary device capable of paying off cable from top to bottom in building construction and cable paying off method
CN202217968U (en) * 2011-09-08 2012-05-09 河南省电力公司周口供电公司 Lifting type paying-off tackle for wires in power distribution lines
CN202633834U (en) * 2012-04-27 2012-12-26 中国一冶集团有限公司 Cable laying positioner
CN102969676A (en) * 2012-11-12 2013-03-13 嘉兴电力局 Cable laying device adopting guiding type control of fixed pulleys
CN203033597U (en) * 2013-01-18 2013-07-03 广州市京龙工程机械有限公司 Inclined ladder cable protection device
CN203951106U (en) * 2014-07-10 2014-11-19 中建五局工业设备安装有限公司 A kind of borehole cable constructing device for skyscraper

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6729606B1 (en) * 1999-08-10 2004-05-04 I.C.M. Group Device for guiding at least a flexible elongated element such as a cable or the like, with substantially closed contour
JP2009171820A (en) * 2008-01-10 2009-07-30 Higashida Shoko Kk Cable laying method using cable grip
CN202217968U (en) * 2011-09-08 2012-05-09 河南省电力公司周口供电公司 Lifting type paying-off tackle for wires in power distribution lines
CN102332691A (en) * 2011-09-19 2012-01-25 中建五局工业设备安装有限公司 Auxiliary device capable of paying off cable from top to bottom in building construction and cable paying off method
CN202633834U (en) * 2012-04-27 2012-12-26 中国一冶集团有限公司 Cable laying positioner
CN102969676A (en) * 2012-11-12 2013-03-13 嘉兴电力局 Cable laying device adopting guiding type control of fixed pulleys
CN203033597U (en) * 2013-01-18 2013-07-03 广州市京龙工程机械有限公司 Inclined ladder cable protection device
CN203951106U (en) * 2014-07-10 2014-11-19 中建五局工业设备安装有限公司 A kind of borehole cable constructing device for skyscraper

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110323704A (en) * 2019-07-01 2019-10-11 浙江省建设机械集团有限公司 A kind of fixed device of cable and its application method
CN113036662A (en) * 2021-03-11 2021-06-25 湖南天禹设备安装有限公司 Spacing, guider are used in high-rise shaft cable direction construction
CN113036662B (en) * 2021-03-11 2021-10-26 湖南天禹设备安装有限公司 Spacing, guider are used in high-rise shaft cable direction construction

Also Published As

Publication number Publication date
CN104078893B (en) 2017-01-25

Similar Documents

Publication Publication Date Title
CN201758254U (en) Horizontal double-roller cable guiding device
CN203951106U (en) A kind of borehole cable constructing device for skyscraper
CN104078893A (en) Vertical well cable construction device used for high-rise building
CN105570539A (en) Construction method of pipeline protection structure
CN103287997A (en) Double-layer winding hoisting mechanism
CN202766111U (en) Anti-swing lifting mechanism
CN105401733A (en) Channel connecting core barrel with peripheral steel structure and construction method for channel
CN204139627U (en) The anti-wear cover cage of wire rope
CN203722180U (en) Cable pay-off rack and cable laying device
CN204847642U (en) Construction elevator stop device
CN204342333U (en) The plain line rope guide of lifting mechanism of tower crane
CN203782575U (en) Stay cable hanging and tension construction device
CN103334592B (en) Step-type sliding installation construction method for convex structure of high-rise building
CN203624768U (en) Construction hoist capable of carrying climbing formwork
CN208015272U (en) C-PVC power cable conduits
CN205015532U (en) Novel optical cable stores up line device
CN201225002Y (en) Climbing apparatus capable of traversing barrier
CN204675715U (en) A kind of full Terrain Cranes surpasses lift winch rope arranging automatically control setup
CN214755430U (en) Steel rail passing structure of cable trench
CN203639031U (en) Tubular unwinding device
CN204311724U (en) A kind of hanging basket suspension device away from structure limit
CN205369245U (en) Pressure dispersion formula anchor rope
CN204947514U (en) A kind of substation secondary device room cable laying device
CN204001010U (en) Cone is grabbed in a kind of punching
CN205243034U (en) Passageway of a contact core section of thick bamboo and peripheral steel construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 410004 No. 158 Zhongyi Road, Yuhua District, Changsha, Hunan

Patentee after: CHINA CONSTRUCTION FIFTH ENGINEERING INSTALLATION Co.,Ltd.

Address before: 410004 20, Zhongjian mansion, 158 Zhongyi Road, Changsha, Hunan.

Patentee before: CCFEB INDUSTRIAL EQUIPMENT INSTALLATION Co.,Ltd.

CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 518000 Floor 9, new Zhoubang science and technology building, No. 9, Changye Road, Liulian community, Pingshan street, Pingshan District, Shenzhen, Guangdong Province

Patentee after: CHINA CONSTRUCTION FIFTH ENGINEERING INSTALLATION Co.,Ltd.

Address before: 410004 No. 158 Zhongyi Road, Yuhua District, Changsha, Hunan

Patentee before: CHINA CONSTRUCTION FIFTH ENGINEERING INSTALLATION Co.,Ltd.

CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 518000 Floor 9, new Zhoubang science and technology building, No. 9, Changye Road, Liulian community, Pingshan street, Pingshan District, Shenzhen, Guangdong Province

Patentee after: CHINA CONSTRUCTION FIFTH ENGINEERING INSTALLATION Co.,Ltd.

Address before: 410004 No. 158 Zhongyi Road, Yuhua District, Changsha, Hunan

Patentee before: CHINA CONSTRUCTION FIFTH ENGINEERING INSTALLATION Co.,Ltd.