US20080172330A1 - Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment - Google Patents

Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment Download PDF

Info

Publication number
US20080172330A1
US20080172330A1 US11/958,346 US95834607A US2008172330A1 US 20080172330 A1 US20080172330 A1 US 20080172330A1 US 95834607 A US95834607 A US 95834607A US 2008172330 A1 US2008172330 A1 US 2008172330A1
Authority
US
United States
Prior art keywords
consumer
power
cpe
lender
renewable energy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US11/958,346
Inventor
Gary Kremen
David G. Coleman
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Clean Power Finance Inc
Original Assignee
Clean Power Finance Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from US11/653,325 external-priority patent/US20080091590A1/en
Priority claimed from US11/653,167 external-priority patent/US20080091626A1/en
Priority claimed from US11/653,052 external-priority patent/US7890436B2/en
Priority claimed from US11/653,043 external-priority patent/US20080091580A1/en
Priority claimed from US11/652,712 external-priority patent/US20080091589A1/en
Priority claimed from US11/653,044 external-priority patent/US20080091581A1/en
Application filed by Clean Power Finance Inc filed Critical Clean Power Finance Inc
Priority to US11/958,346 priority Critical patent/US20080172330A1/en
Assigned to CLEAN POWER FINANCE, INC. reassignment CLEAN POWER FINANCE, INC. ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: KREMEN, GARY, COLEMAN, DAVID G.
Publication of US20080172330A1 publication Critical patent/US20080172330A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q40/00Finance; Insurance; Tax strategies; Processing of corporate or income taxes
    • G06Q40/06Asset management; Financial planning or analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q20/00Payment architectures, schemes or protocols
    • G06Q20/08Payment architectures
    • G06Q20/10Payment architectures specially adapted for electronic funds transfer [EFT] systems; specially adapted for home banking systems
    • G06Q20/102Bill distribution or payments
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q40/00Finance; Insurance; Tax strategies; Processing of corporate or income taxes
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q40/00Finance; Insurance; Tax strategies; Processing of corporate or income taxes
    • G06Q40/02Banking, e.g. interest calculation or account maintenance
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S50/00Market activities related to the operation of systems integrating technologies related to power network operation or related to communication or information technologies
    • Y04S50/12Billing, invoicing, buying or selling transactions or other related activities, e.g. cost or usage evaluation

Definitions

  • the present invention relates to financing renewable energy equipment and more particularly to the ability to increase the likelihood that a consumer will repay a loan for such renewable energy equipment in accordance with an agreement to pay such a loan or will make payments for power generated by renewable energy equipment in accordance with an agreement for the purchase of such power.
  • FIG. 1 illustrates a diagram of a power system of the prior art. As is shown, the utilities deliver power generated by power plants through a network of transmission and distribution lines. This network is hereinafter referred to as the “power transmission and distribution grid,” “the electric grid,” “the grid” or “power grid.” Electricity production, demand and costs are discussed in detail in numerous publications. For this reason, these details will be described herein. Suffice it to say, renewable energy is a practical and environmentally conscious alternative to traditional utility production. One of the more desirable renewable sources is solar power.
  • PPA Power Purchase Agreement
  • a PPA Power Purchase Agreement
  • Citizenre company see Domain page: renu.citizenre.com
  • a party known as the PPA Investor purchases, installs and maintains solar equipment on a consumer's premises.
  • the PPA Investor owns the equipment.
  • the consumer agrees to purchase power generated by the solar equipment for a period of up to 25 years).
  • a PPA may include a lease. Depending on the arrangement a PPA might be treated as a capital lease or operating lease.
  • a PPA the consumer makes no investment, needs to perform no repairs, need not wait for any rebates and locks in prices for power.
  • the PPA Investor also receives benefits from this arrangement.
  • the PPA Investor may receive financial benefits including investment tax credits (ITC), accelerated depreciation, rebates, subsidies and possibly other benefits (besides consumer payments).
  • ITC investment tax credits
  • rebates subsidies
  • others possibly other benefits (besides consumer payments).
  • the financing options discussed above (loans, PPA, etc.) unfortunately have disadvantages.
  • the main disadvantage is that there is really no means by which the lender or PPA investor (PPA is a form of financing, in which the PPA investor is a lender) may insure, or increase the likelihood, that the consumer will repay a loan, i.e., make payments for power purchased under a PPA agreement (both lender and PPA investor are also lending entities).
  • PPA is a form of financing, in which the PPA investor is a lender
  • the only threat or incentive for timely payment is a non-judicial foreclosure for real property, a judicial foreclosure for real property repossession for personal property or a breach of contract for violating the agreements behind a PPA.
  • foreclosure and/or repossession require taking possession (physically) of the collateral in question.
  • the method or mechanism involves a starter interrupt device.
  • Passtime Corporation and Payment Protection Systems, Inc. are companies that offer such devices. Such devices are used in automobile financing or leasing agreements to ensure repayment.
  • a starter interrupt device merely prevents an owner or lessee from starting a vehicle until he/she has made an incremental payment.
  • the device functions to “interrupt” electricity flow from vehicle starter to its ignition (making the vehicle inoperable).
  • starter interrupt devices There are different types of starter interrupt devices. The more simple devices use activation codes to permit vehicle use.
  • a creditor supplies the codes after the creditor receives a periodic payment from the owner/lessee. More sophisticated devices incorporate GPS tracking technology and other features.
  • U.S. Pat. Nos. 6,195,648, 6,828,692, and 6,870,467 are examples of vehicle interruption devices/systems. The advantage of using a starter interrupt devices is there is generally no interaction between creditor (and its agents) and the consumer when the device is used. A direct confrontation with the consumer is therefore minimized. Consequently, the devices appear to reduce the likelihood of a breach of the peace. State law ultimately determines permitted use and operation.
  • a lender will likely require direct access to the subject property to prevent a consumer from using such property until he or she has made the appropriate payments.
  • a lender may require the permission, power or authorization to enter a consumer's premises (real property) and/or disable the personal property of the consumer to discontinue the use of such personal property.
  • Utilities typically have the power and authority to enter the premises of a consumer and access the power equipment and/or discontinue power supply in the event that a consumer has failed to make a payment (utilities are required to follow rules set forth by the State PUCs concerning shut-off).
  • Such power and authorization is provided in the published tariff agreements between a utility and consumer for power supply.
  • the threat of utility service shut-off provides a real incentive to make timely payments to a lender.
  • lenders currently do not have the power and authorization, like a utility, to enter a consumer's premises and access personal property such as renewable energy CPE under the existing financing arrangements between lender and consumer.
  • starter interrupt devices appear to be quite advantageous for a creditor involved in a vehicle financing arrangement.
  • the lender e.g., creditor, PPA Investor
  • the lender under a financing agreement for renewable energy equipment to increase the likelihood of receiving payments from a consumer.
  • the lender there is no means by which a lender has authorization to access the renewable energy consumer premises equipment in the event a consumer fails to make a period payment under the financing arrangement.
  • a business method is disclosed of increasing the probability of timely receiving payment for financing renewable energy consumer premises equipment (CPE) by a consumer for power generation at a consumer premises, the renewable energy CPE adapted to deliver power onto a power grid.
  • the method comprises creating an agreement between a consumer and an entity financing renewable energy CPE, wherein creating the agreement includes creating a provision that allows the entity to control power at the consumer premises if a default of the agreement by the consumer occurs.
  • An agreement is disclosed between a consumer and an entity suitable for financing the purchase, installation, and/or maintenance of consumer premises equipment (CPE) by the consumer, the CPE suitable for installation and power generation upon a consumer premises, the CPE adapted to deliver power onto a power grid.
  • the agreement comprises a provision including a right provided to the entity to shut off power generated by the CPE in the event a default of the agreement occurs.
  • a method is disclosed of financing a purchase of renewable energy consumer premises equipment (CPE) by a consumer for power generation at a consumer premises.
  • the method comprises creating a financial instrument supporting a loan for the purchase of the renewable energy CPE by the consumer, wherein creating the financial instrument includes creating a right to shut off the CPE from generating power in the event a default of agreement by the consumer occurs.
  • CPE renewable energy consumer premises equipment
  • a business method is disclosed of enforcing payment of a power purchase agreement for renewable energy using consumer premises equipment (CPE) by a consumer for power generation at a consumer premises, the CPE adapted to deliver power onto a power grid.
  • the method comprises creating a power purchase agreement (PPA) in which a consumer purchase power from the entity generated by the CPE for a period of time, wherein creating the PPA includes creating a provision providing the entity with an easement to permit access to the CPE and a right to shut off the CPE from generating power when a default of the PPA occurs by the consumer.
  • PPA power purchase agreement
  • a business method is of increasing the probability of timely receiving payment for financing renewable energy consumer premises equipment (CPE) by a consumer for power generation at a consumer premises, the renewable energy CPE adapted to deliver power onto a power grid.
  • the method comprises creating an agreement in which the lender agrees to provide a loan to the consumer for the consumer's purchase of the renewable energy CPE, wherein creating the agreement includes creating a provision that allows the lender to shut off power at the consumer premises if default of the agreement by the consumer occurs; triggering a default of the agreement by the consumer; and shutting off power generated by the CPE as a result of the default.
  • CPE renewable energy consumer premises equipment
  • a system for increasing a likelihood of timely receiving payment for financing renewable energy consumer premises equipment (CPE) by a consumer for power generation at a consumer premises.
  • the system comprises a renewable energy CPE installed at a consumer premises for power generation, the renewable energy CPE coupled to a power grid to enable delivery of power generated by the renewable energy CPE onto the power grid; a control device operable to control power at the consumer premises; an agreement between the consumer and a lender enabling the consumer to purchase the renewable energy CPE with a loan provided by the lender to the consumer and enabling the lender to control power at the consumer premises by operating the control device.
  • CPE renewable energy consumer premises equipment
  • a system which comprises a renewable energy consumer premises equipment (CPE) installed at a consumer premises for power generation and coupled to a power grid to enable power delivery onto the power grid, the CPE purchased by the consumer with a loan provided by the lender according to an agreement granting the lender rights to control power at the consumer premises; a main service panel located at the consumer premises; a first control device coupled between the CPE and the main service panel, the first control device operable by the lender according to the agreement; a second control device coupled between the main service panel and a power grid providing power to the consumer premises, the second control device operable by the lender according to the agreement.
  • CPE renewable energy consumer premises equipment
  • a business method is disclosed of increasing the probability of timely receiving payment for financing renewable energy consumer premises equipment (CPE) by a consumer for power generation at a consumer premises, the renewable energy CPE adapted to deliver power onto a power grid.
  • the method comprises providing a loan to a consumer by a lender for the consumer's purchase of renewable energy CPE; making payments incrementally by a consumer to the lender over a period of time to repay the loan; and controlling the power generated by the renewable energy CPE.
  • CPE renewable energy consumer premises equipment
  • FIG. 1 illustrates a diagram of a prior art power system.
  • FIG. 2 illustrates a block diagram of a power system incorporating consumer premises equipment (CPE) for a real property structure.
  • CPE consumer premises equipment
  • FIGS. 2A-B illustrates net and dual metering arrangements, respectively.
  • FIG. 3 illustrates a block diagram of an agreement between lender and consumer/borrower in accordance with an embodiment of the present invention.
  • FIG. 4 is a flowchart illustrating the steps of the method for contemplating shutting power off upon default in accordance with an embodiment of the present invention.
  • FIG. 1 illustrates consumer premises equipment 10 (also known or referred to as “CPE,” “consumer premises equipment.” “renewable energy consumer premises equipment” and “renewable energy CPE”) that resides on a residential building, but may alternatively reside on a business, institution or other real property. It is noted that many of the terms used in this application are defined herein (including the Appendix), and such definitions (meaning) shall control in any conflict or inconsistency with a conventional definition or meaning provided in any priority or other application or document.
  • CPE 10 incorporates renewable energy equipment that is used by the consumer for energy generation.
  • CPE 10 includes solar components as the renewable energy equipment (source).
  • any renewable equipment may be used such as wind, biomass or water (hydroelectric) energy generation equipment as well as non-renewable energy sources.
  • PV photovoltaic
  • solar equipment or system
  • PV systems that interact with the utility power grid with no battery backup capability
  • systems that interact with the power grid and include battery backup In addition, there are other systems that do not interact with the grid.
  • the PV system (equipment) interacts with the power grid 32 but does not include a battery backup.
  • this system operates only when the utility is available.
  • This PV system will typically provide the greatest amount of savings to a consumer per dollar of investment. However, the system will shut down during an outage, and will remain that way until utility power is restored.
  • the consumer is a homeowner or resident for this discussion, but may alternatively be a business, institution, entity or other user or purchaser of power (electricity).
  • CPE 10 comprises several components including a PV (photovoltaic) array 12 along with the appropriate mounting equipment.
  • PV array 12 is made up of PV modules, which are environmentally sealed collections of PV cells. These cells convert the sunlight into electricity.
  • PV modules are 5-25 square feet in size. Usually four or more smaller modules are framed together by struts called a panel. A panel spanning 20-35 square feet in area may be used for more easily handling on a roof.
  • CPE 10 includes mounting and wiring systems used to integrate the solar modules into the electrical systems of a residence or alternatively a business, institution or other consumer.
  • CPE 10 includes (as part of the wiring system) PV array circuit combiner 14 , ground fault protector 16 , DC fused switch 18 and DC/AC inverter 20 connected in series.
  • PV array circuit combiner 14 is connected to PV array 12 .
  • DC fused switch 18 is used as over-current protection for the solar (PV) modules.
  • Ground fault protection 16 is a circuit breaker.
  • Combiner 14 is used since PV array 12 (modules) requires fusing for each module source circuit. Some inverters alternatively include the fusing and combining function within the inverter housing.
  • Inverter 20 is designed to take the DC power from PV array 12 and convert it into standard AC power used by devices that consumes standard AC power.
  • CPE 10 further includes AC fused switch 22 and utility switch 24 connected in series (and connected to DC/AC inverter 20 ).
  • AC fused switch 22 is used as a power disconnect (i.e., as an over-current protective device (OCPD)).
  • Utility switch 24 is used by the utility to switch off PV array 12 .
  • Most utilities require a visible-blade, lockable open switch or disconnect in the inverter's output circuit.
  • the utility switch 24 is usually located within sight of the service-entrance meter for ease of locating by emergency response people.
  • CPE 10 may include additional components or fewer components than described herein depending on power and installation requirements. In addition to the above shut off mechanisms (e.g., switches), power shut off may be accomplished by disconnecting the leads of the power grid from the CPE and capping such leads to ensure the safety of those near the power leads.
  • the components of CPE 10 are connected to original components including main service panel 26 , consumer loads or usage (or consumption) 28 , meter 30 and a local segment of the utility power grid 32 .
  • utility switch 24 is fused and is connected to main service panel 26 .
  • the maintenance service panel 26 includes among other things the residential circuit breakers.
  • Main panel 26 is coupled to the residential wiring and loads 28 .
  • Meter 30 is coupled between power grid 32 and main service panel 26 .
  • Meter 30 is a device for measuring electricity consumption.
  • meter 30 is capable of net metering (or other alternative metering schemes discussed below). This is shown in FIG. 2A .
  • CPE 10 is shown interconnected to power grid 32 to enable the consumer to feed any surplus or excess power (electricity) to grid 32 .
  • Meter 30 will spin forward when power (electricity) flows from power grid 32 into the residence and backward when CPE 10 (solar components) produces surplus electricity that is not immediately used. Excess power (electricity) is “loaded” on power grid 32 .
  • Utilities may require an agreement for consumers to qualify for net-metering. This is known as net metering to those skilled in the state of the art.
  • FIG. 2B meter 36 and meter 38 are shown in series.
  • Meter 36 is used as a measuring device for power consumed or used and meter 38 is used as a measuring device for power generated by the consumer's CPE.
  • This “dual metering” convention may be desired by a consumer or required by a utility. This is because in some cases, the purchase price of power is different than the rate the utilities buy the power from the consumer.
  • the solar components or equipment of CPE 10 that is subject to or may be borrowed against (may be secured) includes PV array 12 , circuit combiner 14 , ground fault protector 16 , DC switch 18 , DC/AC converter 20 and possibly other components including the mounting equipment. Note that these components may be considered fixtures depending on implementation and local laws.
  • shut off device 23 is coupled between utility switch 24 and main service panel 26 .
  • Shut off device 23 has two functions. First, shut off device 23 (under control) may be used to prevent a consumer from consuming electricity (by way of consumer loads 28 ). Second, shut off device 23 may also be used to prevent a consumer from generating electricity (from CPE 10 ) and delivering it onto power grid 32 . In addition to shut off device 23 , there is another component used to interrupt power. That device is shut off device 27 , and it is coupled between main service panel 26 and meter 30 .
  • shut off device 27 may be used to shut off power supplied to the consumer.
  • Shut off devices 23 and 27 may be a local device such as a switch or similar component or a device that is remotely controlled.
  • the switch or similar component may be mechanical or electronic wherein codes may be entered (for example) for continued operation.
  • shut off devices 25 and 27 may be remotely controlled by wired or wireless communication (coupling with control source 29 ).
  • Conventional wireless communication includes satellite, radio (e.g., UHF/VHF) and cellular technology.
  • shut off may be accomplished by deactivation or reactivation.
  • CPE 10 is shut off when appropriate codes are sent.
  • the lender may send such codes when the consumer fails to make an incremental payment by a default cure date set forth in a written notification sent to the consumer.
  • CPE 10 automatically shuts off and cannot generate power until control device 29 sends a reactivation codes.
  • the lender shall send such codes when the consumer makes an incremental payment by a default cure date.
  • a utility may also shut off power supplied to the consumer under similar circumstances (as provided in the agreement between lender/creditor and consumer). This is described in more detail below.
  • Shut off device 27 may be used to interrupt/shut off (1) electricity supplied to the consumer and (2) electricity generated by CPE 10 and delivered onto power grid 32 . In this configuration, shut off device 27 may prevent electricity from flowing toward grid 32 . However, in this configuration, shut off device 27 is not capable of preventing a consumer from consuming electricity (via consumer loads 28 ) generated by CPE 10 . For this purpose, shut off device 23 is used. If a configuration incorporates control source 29 for shut off (as opposed to a switch), control source 29 may remotely control and shut off device 23 to cut off power consumed by consumer loads 28 . It is noted that there may be many other types of shut off and controlling components and configurations to achieve power interruption.
  • a lender may do so in several ways. As indicated above, a lender may use control source 29 to control the operation of shut off devices 23 and 27 . In addition, either DC fused switch 18 or AC fused switch 22 may be “switched” or disconnected to stop power generation and delivery. In addition, DC/AC inverter may be removed to ensure that power is not generated and consumed or delivered onto power grid 32 . There may be other switches or components that may be incorporated into CPE 10 or outside of CPE 10 . For example, a switch may be used between meter 30 and main service panel 26 .
  • shut off device 27 may be used to cut off supplied power.
  • FIG. 3 wherein an arrangement, i.e., an agreement between the lender 15 (also known and referred to herein as “creditor,” “vendor” and “PPA Investor”) and consumer/borrower 25 for financing consumer premises equipment (CPE) is shown.
  • the relationship is commemorated or represented by a written contract such as financial instrument 35 in accordance with an embodiment of the present invention.
  • Financial instrument 15 may take many forms including, without limitation, a power purchase agreement (PPA).
  • PPA power purchase agreement
  • the agreement or relationship may alternatively be represented by any other legal arrangement (in accordance with the present invention) between a financing entity and a consumer to achieve the same result. Regardless of the type of arrangement, the agreement must abide by applicable State and Federal law.
  • Sections 814-816 enable small and medium-sized licensors of software to enforce their contractual rights quickly and efficiently without resort to judicial process.
  • Today, only Maryland and Virginia have adopted this Act (applicable UCITA sections are based on proposed Section 2B of the UCC which ultimately was not passed into law).
  • State law dictates the rules and regulations of shutting off power (whether manually or electronically performed).
  • Most States also have laws relating to consumer credit. Examples of such Federal laws may include “The Truth in Lending Act,” “Equal Credit Opportunity Act,” “Fair Credit Reporting Act” and several other Federal laws.
  • Financial instrument 35 shall include several provisions or features relating to the transaction between lender 15 and consumer/borrower 25 .
  • financial instrument 35 shall include a provision (i.e., language) describing the collateral against which the loan is secured.
  • Collateral may be personal property or real property.
  • collateral may be CPE 10 , rebates, credits and subsidies, and/or the real property upon which CPE 10 is disposed. These are examples of collateral.
  • Financial instrument 35 shall also give the lender 15 the authority to foreclose or make a claim to the collateral in the event the consumer defaults on the loan or breaches the agreement in other ways.
  • provision shall mean any portion, text, section or language of an agreement between a consumer and lender for financing CPE.
  • provision and “section” are used interchangeably in this application.
  • provision may be in the body of the agreement, or alternatively, it may be set forth in an attachment to the agreement. In this respect, the agreement shall incorporate the attachment by reference therein.
  • a default is a legal term that means the failure to make a payment when due, which can lead to a notice of default and the start of foreclosure proceedings if the debt is secured by real property or a repossession if secured by personal property.
  • default shall also include any breach (violation) by the consumer of one or more provisions or conditions of the contractual arrangement between the lender and consumer (e.g., a PPA or other legal arrangement).
  • An example of this is a consumer's failure to maintain insurance coverage on the CPE as required by the agreement. The agreement will determine what ultimately constitutes a default.
  • State law may provide limitations on a default provision in the agreement.
  • the lender will notify the borrower of the default (or missed payment depending on required language) and afford the borrower the opportunity to cure the default within a period of time.
  • This notification may include other information including the specific clause breached and/or State law requiring such notification. Notification will likely be in written form, but could be sent by email or other communication recited in the agreement or required by State law.
  • the consumer In order to cure a default as indicated above, the consumer must “fix” their breach/violation of their legal obligations under the financial instrument (including a PPA) or other contractual arrangement. In the event a consumer fails to make a payment for example, the consumer may cure the breach of contract by tendering to the lender/creditor the missed loan payment (plus any late fees as required by the loan) or power purchase payment under a PPA. If cure is specifically provided (under the contract or State law), a financial instrument (including a PPA) or other contractual arrangement usually states a time period in which the consumer (or borrower) may cure the default.
  • the lender may have other remedies prescribed in the agreement and/or by State law (e.g., UCC). Foreclosure, however, is expensive and time consuming. For this reason, the financial instrument 35 (including PPA) or other legal financing agreement shall include provisions permitting the lender to (1) enter the consumer's premises (by way of an easement or license), (2) inspect CPE 10 and/or act upon CPE 10 including shutting the power off of (using shut off device 23 for example) and possibly shutting off power supplied to a consumer by a utility using device 27 ). This is discussed in detail below with respect to FIGS. 3 and 4 .
  • financial instrument 35 shall also include one or more provisions or language describing the loan amount, the interest rate, what constitutes a default, the rights of the lender 15 (creditor) and consumer upon default including shut off remedies, maintenance of CPE 10 , insurance for the equipment and/or other terms.
  • financial instrument 35 shall also include a provision(s) or language granting an easement or license to enable lender 15 or its agent to enter the real property of the consumer/borrower 25 and to act upon CPE 10 in some way (shut off, inspect, modify CPE 10 as described below).
  • An easement (the one herein discussed is historically called easement in appurtenant or covenant) is a legal right or restriction that attaches to the property in which CPE 10 is disposed.
  • lender 15 may enforce his right to enter the real property against all who own or lease the real property on which the CPE 10 is disposed (particularly if the loan agreement (or PPA) is transferred to the new owner or lessee). It is not a personal right or restriction that cannot be transferred (i.e., the personal right or restriction typically extinguishes when the real property is sold to another).
  • the provision with the easement may be in the body of the agreement between lender and consumer or may be part of an attachment incorporated by reference into the agreement. Under state law, it is likely that such as easement must be recorded with the appropriate state governmental recording agency.
  • the easement may additionally or alternatively grant the lender 15 a right to continue operation of the CPE 10 on the real property of the consumer/borrower 25 , in the case of default and/or repossession of the CPE 10 .
  • This provides the lender 15 an ability to continue generation of power and direct it onto a power grid or another location or storage facility/unit.
  • CPE 10 may generate revenue even in the case of default and/or repossession of the CPE 10 .
  • financial instrument 35 may provide a license granting the right to enter the real property of consumer 25 and act upon CPE 10 .
  • licenses to enter property are personal and do not run with the land. Therefore, the easement is more advantageous to lender 15 .
  • financial instrument 35 including a PPA or other arrangement shall set forth the length of time in which lender 15 shall have the right to access the property. In most cases, the right shall extend for the loan period or other period in which payment must be made (e.g., PPA periodic payments for power generated by CPE 10 ).
  • the agreement shall grant access to enter the consumer's real property (premises) even if the lender expects to remotely shut off a consumer's power (in the event of default).
  • Property access will permit lender 15 , upon its sole discretion, to inspect CPE 10 and either modify CPE 10 or instruct the consumer to make such modifications, as required by financial instrument 35 . This will ensure that CPE 10 will optimally generate power during the course of the arrangement between lender 15 and consumer 25 (until lender determines otherwise in accordance with the agreement and/or State law).
  • lender 15 shall require that consumer 25 execute any additional legal real property documents necessary to enable lender 15 to secure the easement or other legal rights (to enter the property) and to perfect such rights against third parties. Such documents may require notarization.
  • lender 15 shall typically file such documents (e.g, easements) at the government recordation office in which the real property is located.
  • the appropriate governmental office may be a county recorder's office, Secretary of State or department of corporation's office. However, State law ultimately governs recordation procedure and filing.
  • financial instrument 35 shall include a provision(s) or language granting lender 15 the right to (1) inspect the CPE 10 , (2) remove the CPE 10 , (3) shut off (also known as disconnected, interrupted or “intervention”) power locally or remotely generated by CPE 10 based on specified breaches (violations of financial instrument 35 ) and/or (3) modify and maintain the CPE 10 to ensure maximum power generation.
  • lender 15 decides to shut off consumer power under the agreement, lender 15 shall notify consumer 25 and give a certain period to cure the breach of agreement to avoid shut off. Financial instrument 15 will likely require such notification (even if State law does not require it).
  • the provisions described herein granting rights to enter the consumer premises and act upon the CPE 10 may apply to agents (or other third parties such as the trustee in a deed of trust) acting on behalf of lender 15 including installers, inspectors or other entities instructed to perform services for lender 15 .
  • agents granted such rights may also include a utility, as a third party beneficiary, supplying power to consumer 25 .
  • the utility would have the right (and may be required as authorized in the agreement between lender 15 and consumer 25 ) to enter the property and/or to shut off power (i.e., power intervention or interruption) supplied to the consumer by the utility (for breaches of the agreement between lender 15 and consumer 25 ).
  • Financial Instrument 35 shall also include a provision or section requiring the consumer to notify lender 15 if for legal reasons why lender 15 shall not shut off power in the event of a default by the consumer. For example, a consumer may legally require life support equipment to stay alive. Such equipment requires power for operation. Lender 15 may check a consumer's meter tags (indicating that power must not be shut off) and/or the utility company database for people on life support. Such provisions may require a lender to check a consumer's meter tags and/or check the utility company database for people on life support. See PG&E's Service for Medical Baseline and Life Support Customers. (See domain page at pge.com/res/financial_assistance/medical baseline_life_support/) In addition, the agreement provision or section may provide a specific email, postal or other address to which the notification shall be sent.
  • Financial instrument 35 may also include a provision or section with a power of attorney.
  • This power of attorney will govern communication between the consumer 25 and the utility, relevant State PUC and possibly other entities. The language may state that this power of attorney is irrevocable. Note that State law ultimately governs such provisions.
  • power interruption or shut off is the desired action by any authorized party under any contractual arrangement, power may be interrupted or shut off locally or (alternatively) remotely. If action is performed locally, lender 15 , its agent or any contractually authorized party may enter the property to perform the task mechanically (using shut off devices 23 and 27 ).
  • shut office devices 23 and 27 may be a key or switch to interrupt power.
  • lender 15 may remove inverter 20 or any other component provided such removal does not damage CPE 10 or the real property on which CPE 10 is positioned. (It should be noted that power might be shut off for safety reasons.)
  • lender 15 may achieve this goal electronically by wire or wireless connection as described above (using shut off devices 23 and 27 ).
  • lender 15 may interrupt or shut off power by means of a codes/software deactivation or reactivation.
  • CPE 10 purchased (or used or leased under a PPA) by consumer 25 may include software under license to consumer 25 . If consumer 25 fails to make a loan payment (or other default as described herein), lender 15 (agent or another authorized to act on its behalf such as a vendor) may deactivate CPE 10 remotely (traditionally via software execution). Alternatively, such software may require periodic reactivation codes or keys to enable consumer 25 to continue to use CPE 10 to generate power. In the event consumer 25 fails to make a loan payment, consumer 15 will not receive reactivation codes until consumer 25 cures the breach.
  • a medallion guarantee is a special signature guarantee for the transfer of securities. It is a guarantee by the transferring financial institution that the signature is genuine and the financial institution accepts liability for any forgery. Signature guarantees protect shareholders by preventing unauthorized transfers and possible investor losses. They also limit the liability of the transfer agent who accepts the certificates.)
  • execution of the agreement i.e., the transaction
  • FIG. 4 a flowchart is shown that illustrates the steps of a method for either shutting off or maintaining power generation on a consumer's premises (real property).
  • a lender has provided a loan to a consumer for the purchase of CPE 10 .
  • consumer 25 will make payments to lender 15 on an incremental basis. Terms typically require monthly payment increments but any period may be required.
  • Payments are shown at step 35 .
  • Execution then moves to decision step 45 wherein it is determined whether consumer 25 has made the relevant incremental payment. If the consumer has made the relevant payment, execution returns to step 45 . If consumer 25 fails to make a payment, consumer 25 is in default for failure to make the appropriate incremental payment.
  • decision step 55 it is determined if consumer's failure to make a payment has triggered a default-remedy provision under the terms of financial instrument 35 . Such a provision will be triggered if notice is provided to consumer 25 with appropriate information and cure date.
  • lender 15 shall notify consumer 25 at step 65 of the failed payment, (2) the default provision breached, (3) the deadline in which payment must be received (cure date), (4) the location in which payment must be delivered or sent and (5) the remedies provided under the agreement and State law that lender may use to enforce the agreement. There may be other information set forth in the notification.
  • lender 15 shall notify consumer 25 that consumer 25 is in default, consumer 25 has breached the agreement by his/her failure to make payment by the cure date, the default-remedy provision(s) of financial instrument 35 are triggered and that power generated by CPE 10 may be interrupted or shut off by a specified date, or alternatively the CPE 10 must be continued in operation for the benefit of the lender 15 , unless payment is not received immediately.
  • lender 15 has all of the available remedies provided under financial instrument (agreement) 35 as well as under State law.
  • lender 15 determines whether it wishes to interrupt or shut off power, or alternatively continue operation for the benefit of the lender 15 . If the answer is no, lender 15 may wish to take advantage of other remedies such as garnishing employment wages of consumer at step 95 or alternatively foreclosing on the consumer's property or taking other action to obtain the money to repay the loan. Lender 15 may also enter the property to perform maintenance on CPE 10 to ensure CPE 10 continues to generate power at steps 105 and 115 , respectively, for the following reason. Lender 15 may desire to claim the collateral in accordance with financial instrument 35 .
  • the collateral may include the CPE 10 for example, the power generated by the CPE 10 , the receivables paid/credited by a utility for power generated by the CPE 10 or other property.
  • lender 15 may be receiving payments from utility directly. As indicated, lender wants to ensure that CPE 10 generates power to receive the benefits from that power (e.g., receivables). Lender 15 may have other options against consumer 25 to repay the loan.
  • step 85 In the event the answer to decision step 85 is yes and lender 15 decides to interrupt or shut off power (CPE 10 ), execution moves to decision step 125 wherein lender decides if it will interrupt or shut off power locally (mechanically). If the answer is yes, lender 15 shall enter the real property at step 135 and interrupt or shut off power at the consumer's premises a step 145 . This may be accomplished by switch, component removal or other mechanical or electro-mechanical means. In the event the answer is no to decision step 125 and lender 15 desires to interrupt or shut off power remotely, lender 15 has several options to accomplish this task, but such options will depend on the system components of CPE 10 and the specific provisions (e.g., easements, licenses etc.) of financial instrument 35 and any related documents.
  • lender 15 may deactivate CPE 10 remotely as described above by sending codes/software (using shut off device 23 ). Alternatively, lender 15 may not transmit activation codes or keys to ensure continuous operation of CPE 10 (until payment is received). Interruption/shut off may be by wired or wireless communication (remotely). Shut off may, however, be accomplished in many ways (described above).
  • a utility may also be authorized (and required) to interrupt or shut off power. This is shown in decision step 155 connected in parallel to step 85 (dashed lines).
  • the utility will also have the choice of interrupting power locally or remotely (steps 125 and 155 ) as described above depending on the grid connection and system used.
  • the utility may choose not to shut off power, but may wish to enter the real property to access the equipment (for inspection or modification. This equipment may be utility owned equipment or possibly CPE 10 .
  • any breach of a condition or provision may be cause for property entry and/or power interruption or shut off.
  • any failure to maintain insurance for CPE 10 or pay real or personal property taxes as required by financial instrument 35 may be subject to power shut off.
  • the arrangement described with respect to the method in FIG. 4 is a financial instrument (e.g., a PPA or other security agreement).
  • any legal arrangement may be used for this method including a PPA or any other legal arrangement.
  • “collateral” shall mean any property or asset pledged by a borrower to secure a loan or other credit, and subject it to seizure in the event of default.
  • “consumer” shall mean a user or purchaser of power (electricity).
  • “computer implementation” (also known referred to “computer implemented”) shall mean the execution of any or all process steps by computer.
  • CPE consumer premises equipment
  • CPE consumer premises equipment
  • renewable energy consumer premises equipment shall mean the physical assets of the CPE such as any and all renewable energy equipment that resides (or is disposed) on or near a residential building, business, institution or other real property.
  • CPE shall include solar components as the renewable energy equipment (source) and any and all mounting equipment.
  • CPE may include any other renewable equipment such as wind, biomass or water (hydroelectric) energy generation equipment as well as non-renewable energy sources.
  • seed of trust shall mean a document which pledges real property to secure a loan by a consumer.
  • the property is deeded by a title holder (trustor) to a trustee (often a title or escrow company), which holds the title in trust for the beneficiary (the lender of the money).
  • the trustor requests the trustee to return the title by reconveyance. If the loan becomes delinquent or is in default, the beneficiary can file a notice of default and, if the loan is not brought current, the trustee can demand that the trustee begin foreclosure on the property so that the beneficiary may either be paid or obtain title.
  • “default” shall mean the failure to make a payment when due, which can lead to a notice of default and the start of foreclosure proceedings if the debt is secured by real property or a repossession if secured by personal property. Default shall also include any breach (violation) by the consumer of one or more provisions or conditions of the contractual arrangement (e.g., a PPA or other legal arrangement) between the lender and consumer. An example of this is a consumer's failure to maintain insurance coverage on the CPE as required by the agreement.
  • a PPA or other legal arrangement An example of this is a consumer's failure to maintain insurance coverage on the CPE as required by the agreement.
  • easement shall mean the legal right or restriction that enables an entity to enter the real property of another entity. An easement attaches to the real property and therefore may be enforced against all who own or lease the real property.
  • Entity shall mean any person, group of persons, company, division, agency, partnership or other entity (private or government). Entity includes, without limitation, a consumer, lender or other party.
  • financial instrument shall mean any real or virtual document representing a legal agreement involving some sort of monetary value. Such financial instrument shall include an agreement between a lender (also known and referred to herein as “creditor,” “vendor” and “PPA Investor”) and consumer/borrower for financing consumer premises equipment (CPE). A power purchase agreement (PPA) is an example of a financial instrument. Financial instruments shall include “notes.” Financial instruments are also known as securities.
  • foreclosure shall mean a method of enforcing a security interest in real property.
  • intervention means the interference of or the ability (i.e., the right) to interfere with a consumer's ability to use power generated by the CPE or provided by a utility.
  • lender (also referred to as “creditor,” “vendor,” and “PPA Investor”) shall mean an entity that provides the financing for the CPE.
  • a lender shall include an entity that provides a loan to a consumer for the purchase of the CPE or a PPA investor that actually purchases CPE for power generation and purchase by a consumer.
  • license shall mean the right of one entity to enter the real property of another. A license does not attach to the real property and therefore cannot be enforced against all who own or lease the real property.
  • loan shall mean an arrangement in which a lender gives money to a borrower (e.g., the consumer), and the borrower agrees to repay the money, usually along with interest, at some future point(s) in time.
  • a loan is usually evidenced by a specific financial instrument (or financial instruments).
  • “mortgage” (or “mortgages”) shall mean a debt financial instrument by which the borrower (mortgagor or consumer) gives the lender (mortgagee) a lien on property as security for the repayment of a loan.
  • Personal property shall mean property of any kind except real property.
  • personal property may be tangible, having physical existence, or intangible, having no physical existence, such as financial instruments.
  • personal property shall include, without limitation, receivables, credits, subsidiaries.
  • power purchase agreement (also known as “PPA”) shall mean an agreement in which a PPA Investor agrees to purchase and install CPE, and the consumer agrees to purchase the power generated by the CPE for a period of time.
  • a power purchase agreement may be treated as or incorporate a lease of the CPE by the consumer.
  • power shall mean electricity. Power is also known as or referred to as “electricity” or “energy.”
  • power grid also known as the “power transmission and distribution grid,” “electric grid” or “grid” shall mean the network of transmission and distribution lines (and the step-up and step-down transformers) that is used to deliver electricity to consumers.
  • PPA Investor shall mean an entity that provides the financing for CPE in connection with a power purchase agreement with a consumer.
  • provision shall mean any portion, text, section or language of an agreement between a consumer and lender for financing CPE.
  • provision and “section” are used interchangeably in this application.
  • a provision may be in the body of the agreement, or alternatively, it may be set forth in an attachment to the agreement.
  • “rebates” shall mean a deduction from the amount due or a return of part of an amount given in payment.
  • “receivables” shall mean any payment, instrument or other valuable consideration owed to an entity (e.g., consumer) for the power generated by the CPE, whether or not such payment, instrument or other valuable consideration is currently due.
  • the receivables may be provided by a utility or other entity.
  • Receivables shall include, without limitation, any credit, money certificate or other quantifiable value for power generated by a CPE.
  • renewable energy shall mean power supplied by energy sources that are naturally and continually replenished such as wind, solar power, geothermal, hydropower, and various forms of biomass.
  • renewable energy source shall mean sources of renewable energy such as water (hydroelectric power), wind, biomass and solar energy.
  • shut off (also known as “disconnected”, “interrupted” and “intervention”) shall mean the interference with a consumer's use of power generated by the CPE or provided by a utility.
  • “subsidies” shall mean a monetary grant given by government to lower the price of a good such as CPE, generally because they are considered to be in the public interest.
  • “utility” shall mean any entity that purchases, sells or markets power to (or from) the consumer of power or has the primary relationship with that consumer.

Abstract

A business method is disclosed of increasing the probability of timely receiving payment for financing renewable energy consumer premises equipment (CPE) by a consumer for power generation at a consumer premises, the renewable energy CPE adapted to deliver power onto a power grid. The method comprises creating an agreement between a consumer and an entity financing renewable energy CPE, wherein creating the agreement includes creating a provision that allows the entity to control power at the consumer premises if a default of the agreement by the consumer occurs.

Description

    CROSS-REFERENCE TO RELATED APPLICATIONS
  • The present invention claims priority to and is a divisional patent application of U.S. Ser. No. 11/750,941, filed May 18, 2007, entitled METHODS, SYSTEMS AND AGREEMENTS FOR INCREASING THE LIKELIHOOD OF REPAYMENTS UNDER A FINANCING AGREEMENT FOR RENEWABLE ENERGY EQUIPMENT which is a continuation-in-part of patent applications: (1) U.S. application Ser. No. 11/653,167, filed Jan. 12, 2007, entitled SYSTEMS, METHODS AND FINANCIAL INSTRUMENTS FOR RENEWABLE ENERGY CONSUMER PREMISES EQUIPMENT FINANCING, (2) U.S. application Ser. No. 11/653,052, filed Jan. 12, 2007, entitled BILLING AND PAYMENT METHODS AND SYSTEMS ENABLING CONSUMER PREMISES EQUIPMENT, (3) U.S. application Ser No. 11/653,043, filed Jan. 12, 2007, entitled METHODS FOR COST REDUCTION AND UNDERWRITING CONSIDERATIONS FOR FINANCING RENEWABLE ENERGY CONSUMER PREMISES EQUIPMENT (CPE), (4) U.S. application Ser. No. 11/652,712, filed Jan. 12, 2007, entitled METHOD FOR UNDERWRITING THE FINANCING OF SOLAR CONSUMER PREMISES EQUIPMENT, (5) U.S. application Ser. No. 11/653,044, filed Jan. 12, 2007, entitled SYSTEMS AND METHODS OF REDUCING FINANCING COSTS FOR RENEWABLE ENERGY CONSUMER PREMISES EQUIPMENT and (6) U.S. application Ser. No. 11/653,325, filed Jan. 12, 2007, entitled METHODS, SYSTEMS AND FINANCIAL INSTRUMENTS FOR FINANCING RENEWABLE ENERGY CONSUMER PREMISES EQUIPMENT, all of such applications being incorporated by reference herein.
  • STATEMENT REGARDING FEDERALLY SPONSORED RESEARCH OR DEVELOPMENT
  • Not applicable.
  • THE NAMES OF THE PARTIES TO A JOINT RESEARCH AGREEMENT
  • Not applicable.
  • INCORPORATION-BY-REFERENCE OF MATERIAL SUBMITTED ON A COMPACT DISC
  • Not applicable.
  • BACKGROUND OF THE INVENTION
  • The present invention relates to financing renewable energy equipment and more particularly to the ability to increase the likelihood that a consumer will repay a loan for such renewable energy equipment in accordance with an agreement to pay such a loan or will make payments for power generated by renewable energy equipment in accordance with an agreement for the purchase of such power.
  • BRIEF DESCRIPTION OF THE INVENTION
  • Electricity or power is an essential part of modern life. In residences, in businesses, in institutions and in other locations, consumers use electricity in a variety of ways. Utilities typically supply power to consumers as needed. FIG. 1 illustrates a diagram of a power system of the prior art. As is shown, the utilities deliver power generated by power plants through a network of transmission and distribution lines. This network is hereinafter referred to as the “power transmission and distribution grid,” “the electric grid,” “the grid” or “power grid.” Electricity production, demand and costs are discussed in detail in numerous publications. For this reason, these details will be described herein. Suffice it to say, renewable energy is a practical and environmentally conscious alternative to traditional utility production. One of the more desirable renewable sources is solar power. For one thing, local solar energy can essentially be harnessed in most developed country locations with solar access. For another, solar equipment consumes no fossil fuels and generates no air pollutants. The use of solar power is generally regarded as environmentally safe. Utilities in many States are required (or voluntarily do so) for public policy reasons to credit or actually buy excess power generated by a consumer. General rules and requirements of such a purchase are not discussed herein. Suffice it to say, solar energy is quite desirable and beneficial to a consumer. Unfortunately, solar power equipment is quite expensive for a consumer. While the Federal and State incentives are significant, the remaining costs for the purchase of solar equipment may be beyond the amount of cash a consumer has on hand or wishes to commit.
  • To date, there are limited financing options for the consumer of solar power equipment. These options are predominantly based on traditional financing products known as a mortgage, a secured loan in real property or deed of trust. Such products rely on a security interest in the consumer/borrower's real property. There are other financing options. Secured personal property loans (sometimes referred to as chattel mortgages or loans) and unsecured personal loans are also available for the purchase of solar equipment. Secured personal property loans are typically secured by the personal property. Unsecured loans are not secured at all.
  • There is yet another financing option available for the consumer. It is known as a Power Purchase Agreement (“PPA”). There are several varieties of a PPA. One example of a PPA is offered by Citizenre company (see Domain page: renu.citizenre.com). In a typical PPA arrangement such as that offered by Citizenre, a party known as the PPA Investor purchases, installs and maintains solar equipment on a consumer's premises. The PPA Investor owns the equipment. In exchange for such equipment, the consumer agrees to purchase power generated by the solar equipment for a period of up to 25 years). A PPA may include a lease. Depending on the arrangement a PPA might be treated as a capital lease or operating lease. In a PPA, the consumer makes no investment, needs to perform no repairs, need not wait for any rebates and locks in prices for power. The PPA Investor also receives benefits from this arrangement. The PPA Investor may receive financial benefits including investment tax credits (ITC), accelerated depreciation, rebates, subsidies and possibly other benefits (besides consumer payments).
  • The financing options discussed above (loans, PPA, etc.) unfortunately have disadvantages. The main disadvantage is that there is really no means by which the lender or PPA investor (PPA is a form of financing, in which the PPA investor is a lender) may insure, or increase the likelihood, that the consumer will repay a loan, i.e., make payments for power purchased under a PPA agreement (both lender and PPA investor are also lending entities). Currently, the only threat or incentive for timely payment is a non-judicial foreclosure for real property, a judicial foreclosure for real property repossession for personal property or a breach of contract for violating the agreements behind a PPA. Traditionally, foreclosure and/or repossession require taking possession (physically) of the collateral in question. These procedures, however, are time consuming and costly. For matters involving personal property, a creditor may repossess (also known as self-help) described collateral from a consumer without resorting to the courts as long as it does not involve breaching the peace. The Uniform Commercial Code (U.C.C.) Article 9 regulates the manner in which secured creditors exercise self-help repossession to recover collateral (goods) after a default. Some states have enacted statutes governing notice requirements in consumer credit transactions that may require the creditor to send notices in connection with repossession.
  • For certain types of personal property such as automobiles, there exists a method or mechanism by which a creditor may increase his/her chances of receiving payments under specific financing arrangements. The method or mechanism involves a starter interrupt device. Passtime Corporation and Payment Protection Systems, Inc. (See passtimeusa.com and ppsontime.com) are companies that offer such devices. Such devices are used in automobile financing or leasing agreements to ensure repayment. A starter interrupt device merely prevents an owner or lessee from starting a vehicle until he/she has made an incremental payment. The device functions to “interrupt” electricity flow from vehicle starter to its ignition (making the vehicle inoperable). There are different types of starter interrupt devices. The more simple devices use activation codes to permit vehicle use. A creditor supplies the codes after the creditor receives a periodic payment from the owner/lessee. More sophisticated devices incorporate GPS tracking technology and other features. U.S. Pat. Nos. 6,195,648, 6,828,692, and 6,870,467 are examples of vehicle interruption devices/systems. The advantage of using a starter interrupt devices is there is generally no interaction between creditor (and its agents) and the consumer when the device is used. A direct confrontation with the consumer is therefore minimized. Consequently, the devices appear to reduce the likelihood of a breach of the peace. State law ultimately determines permitted use and operation.
  • Without the use of a starter device or other means to access personal property remotely such as the PV system (that is subject to financing), a lender will likely require direct access to the subject property to prevent a consumer from using such property until he or she has made the appropriate payments. In order to directly access personal property, a lender may require the permission, power or authorization to enter a consumer's premises (real property) and/or disable the personal property of the consumer to discontinue the use of such personal property.
  • Utilities, for example, typically have the power and authority to enter the premises of a consumer and access the power equipment and/or discontinue power supply in the event that a consumer has failed to make a payment (utilities are required to follow rules set forth by the State PUCs concerning shut-off). Such power and authorization is provided in the published tariff agreements between a utility and consumer for power supply. The threat of utility service shut-off provides a real incentive to make timely payments to a lender. The same incentive holds true for the other companies including the telephone company. However, lenders currently do not have the power and authorization, like a utility, to enter a consumer's premises and access personal property such as renewable energy CPE under the existing financing arrangements between lender and consumer.
  • In short, starter interrupt devices appear to be quite advantageous for a creditor involved in a vehicle financing arrangement. However, there are currently no devices, systems or methods used to enable the lender (e.g., creditor, PPA Investor) under a financing agreement for renewable energy equipment to increase the likelihood of receiving payments from a consumer. Further, there is no means by which a lender has authorization to access the renewable energy consumer premises equipment in the event a consumer fails to make a period payment under the financing arrangement.
  • It would be desirable to provide a method, system and/or agreement that would overcome the disadvantages described above.
  • SUMMARY OF THE INVENTION
  • A business method is disclosed of increasing the probability of timely receiving payment for financing renewable energy consumer premises equipment (CPE) by a consumer for power generation at a consumer premises, the renewable energy CPE adapted to deliver power onto a power grid. The method comprises creating an agreement between a consumer and an entity financing renewable energy CPE, wherein creating the agreement includes creating a provision that allows the entity to control power at the consumer premises if a default of the agreement by the consumer occurs.
  • An agreement is disclosed between a consumer and an entity suitable for financing the purchase, installation, and/or maintenance of consumer premises equipment (CPE) by the consumer, the CPE suitable for installation and power generation upon a consumer premises, the CPE adapted to deliver power onto a power grid. The agreement comprises a provision including a right provided to the entity to shut off power generated by the CPE in the event a default of the agreement occurs.
  • A method is disclosed of financing a purchase of renewable energy consumer premises equipment (CPE) by a consumer for power generation at a consumer premises. The method comprises creating a financial instrument supporting a loan for the purchase of the renewable energy CPE by the consumer, wherein creating the financial instrument includes creating a right to shut off the CPE from generating power in the event a default of agreement by the consumer occurs.
  • A business method is disclosed of enforcing payment of a power purchase agreement for renewable energy using consumer premises equipment (CPE) by a consumer for power generation at a consumer premises, the CPE adapted to deliver power onto a power grid. The method comprises creating a power purchase agreement (PPA) in which a consumer purchase power from the entity generated by the CPE for a period of time, wherein creating the PPA includes creating a provision providing the entity with an easement to permit access to the CPE and a right to shut off the CPE from generating power when a default of the PPA occurs by the consumer.
  • A business method is of increasing the probability of timely receiving payment for financing renewable energy consumer premises equipment (CPE) by a consumer for power generation at a consumer premises, the renewable energy CPE adapted to deliver power onto a power grid. The method comprises creating an agreement in which the lender agrees to provide a loan to the consumer for the consumer's purchase of the renewable energy CPE, wherein creating the agreement includes creating a provision that allows the lender to shut off power at the consumer premises if default of the agreement by the consumer occurs; triggering a default of the agreement by the consumer; and shutting off power generated by the CPE as a result of the default.
  • A system is disclosed for increasing a likelihood of timely receiving payment for financing renewable energy consumer premises equipment (CPE) by a consumer for power generation at a consumer premises. The system comprises a renewable energy CPE installed at a consumer premises for power generation, the renewable energy CPE coupled to a power grid to enable delivery of power generated by the renewable energy CPE onto the power grid; a control device operable to control power at the consumer premises; an agreement between the consumer and a lender enabling the consumer to purchase the renewable energy CPE with a loan provided by the lender to the consumer and enabling the lender to control power at the consumer premises by operating the control device.
  • A system is disclosed which comprises a renewable energy consumer premises equipment (CPE) installed at a consumer premises for power generation and coupled to a power grid to enable power delivery onto the power grid, the CPE purchased by the consumer with a loan provided by the lender according to an agreement granting the lender rights to control power at the consumer premises; a main service panel located at the consumer premises; a first control device coupled between the CPE and the main service panel, the first control device operable by the lender according to the agreement; a second control device coupled between the main service panel and a power grid providing power to the consumer premises, the second control device operable by the lender according to the agreement.
  • A business method is disclosed of increasing the probability of timely receiving payment for financing renewable energy consumer premises equipment (CPE) by a consumer for power generation at a consumer premises, the renewable energy CPE adapted to deliver power onto a power grid. The method comprises providing a loan to a consumer by a lender for the consumer's purchase of renewable energy CPE; making payments incrementally by a consumer to the lender over a period of time to repay the loan; and controlling the power generated by the renewable energy CPE.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • The accompanying drawings, which are incorporated herein and constitute a part of the specification, illustrate embodiments of the invention, and together with the general description given above and the detailed description of the embodiments, serve to explain the principals of the invention.
  • FIG. 1 illustrates a diagram of a prior art power system.
  • FIG. 2 illustrates a block diagram of a power system incorporating consumer premises equipment (CPE) for a real property structure.
  • FIGS. 2A-B illustrates net and dual metering arrangements, respectively.
  • FIG. 3 illustrates a block diagram of an agreement between lender and consumer/borrower in accordance with an embodiment of the present invention.
  • FIG. 4 is a flowchart illustrating the steps of the method for contemplating shutting power off upon default in accordance with an embodiment of the present invention.
  • DETAILED DESCRIPTION OF THE INVENTION
  • FIG. 1 is described above. FIG. 2 illustrates consumer premises equipment 10 (also known or referred to as “CPE,” “consumer premises equipment.” “renewable energy consumer premises equipment” and “renewable energy CPE”) that resides on a residential building, but may alternatively reside on a business, institution or other real property. It is noted that many of the terms used in this application are defined herein (including the Appendix), and such definitions (meaning) shall control in any conflict or inconsistency with a conventional definition or meaning provided in any priority or other application or document. According to the embodiment of FIG. 2, CPE 10 incorporates renewable energy equipment that is used by the consumer for energy generation. In this embodiment, CPE 10 includes solar components as the renewable energy equipment (source). Alternatively, any renewable equipment may be used such as wind, biomass or water (hydroelectric) energy generation equipment as well as non-renewable energy sources.
  • The solar components described herein are collectively known as photovoltaic (“PV” or “solar”) equipment (or system). In general, there are two types of PV systems: systems that interact with the utility power grid with no battery backup capability and systems that interact with the power grid and include battery backup. In addition, there are other systems that do not interact with the grid. In the embodiment shown in FIG. 2, the PV system (equipment) interacts with the power grid 32 but does not include a battery backup. As a result, this system operates only when the utility is available. This PV system will typically provide the greatest amount of savings to a consumer per dollar of investment. However, the system will shut down during an outage, and will remain that way until utility power is restored. Note that the consumer is a homeowner or resident for this discussion, but may alternatively be a business, institution, entity or other user or purchaser of power (electricity).
  • CPE 10 comprises several components including a PV (photovoltaic) array 12 along with the appropriate mounting equipment. PV array 12 is made up of PV modules, which are environmentally sealed collections of PV cells. These cells convert the sunlight into electricity. One of the most common PV modules is 5-25 square feet in size. Usually four or more smaller modules are framed together by struts called a panel. A panel spanning 20-35 square feet in area may be used for more easily handling on a roof. CPE 10 includes mounting and wiring systems used to integrate the solar modules into the electrical systems of a residence or alternatively a business, institution or other consumer.
  • CPE 10 includes (as part of the wiring system) PV array circuit combiner 14, ground fault protector 16, DC fused switch 18 and DC/AC inverter 20 connected in series. PV array circuit combiner 14 is connected to PV array 12. DC fused switch 18 is used as over-current protection for the solar (PV) modules. Ground fault protection 16 is a circuit breaker. Combiner 14 is used since PV array 12 (modules) requires fusing for each module source circuit. Some inverters alternatively include the fusing and combining function within the inverter housing. Inverter 20 is designed to take the DC power from PV array 12 and convert it into standard AC power used by devices that consumes standard AC power.
  • CPE 10 further includes AC fused switch 22 and utility switch 24 connected in series (and connected to DC/AC inverter 20). AC fused switch 22 is used as a power disconnect (i.e., as an over-current protective device (OCPD)). Utility switch 24 is used by the utility to switch off PV array 12. Most utilities require a visible-blade, lockable open switch or disconnect in the inverter's output circuit. The utility switch 24 is usually located within sight of the service-entrance meter for ease of locating by emergency response people. It should be noted that CPE 10 may include additional components or fewer components than described herein depending on power and installation requirements. In addition to the above shut off mechanisms (e.g., switches), power shut off may be accomplished by disconnecting the leads of the power grid from the CPE and capping such leads to ensure the safety of those near the power leads.
  • The components of CPE 10 are connected to original components including main service panel 26, consumer loads or usage (or consumption) 28, meter 30 and a local segment of the utility power grid 32. Specifically, utility switch 24 is fused and is connected to main service panel 26. The maintenance service panel 26 includes among other things the residential circuit breakers. Main panel 26 is coupled to the residential wiring and loads 28.
  • Meter 30 is coupled between power grid 32 and main service panel 26. Meter 30 is a device for measuring electricity consumption. In this instance, meter 30 is capable of net metering (or other alternative metering schemes discussed below). This is shown in FIG. 2A. CPE 10 is shown interconnected to power grid 32 to enable the consumer to feed any surplus or excess power (electricity) to grid 32. Meter 30 will spin forward when power (electricity) flows from power grid 32 into the residence and backward when CPE 10 (solar components) produces surplus electricity that is not immediately used. Excess power (electricity) is “loaded” on power grid 32.
  • Utilities may require an agreement for consumers to qualify for net-metering. This is known as net metering to those skilled in the state of the art. In certain embodiments (similar to embodiments shown in FIG. 2A herein), there might be two separate meters as shown in FIG. 2B. In FIG. 2B, meter 36 and meter 38 are shown in series. Meter 36 is used as a measuring device for power consumed or used and meter 38 is used as a measuring device for power generated by the consumer's CPE. This “dual metering” convention may be desired by a consumer or required by a utility. This is because in some cases, the purchase price of power is different than the rate the utilities buy the power from the consumer.
  • The solar components or equipment of CPE 10 that is subject to or may be borrowed against (may be secured) includes PV array 12, circuit combiner 14, ground fault protector 16, DC switch 18, DC/AC converter 20 and possibly other components including the mounting equipment. Note that these components may be considered fixtures depending on implementation and local laws.
  • In the embodiment shown in FIG. 2, there are additional components used to shut off power in the event a consumer fails to make an incremental payment to a lender. To this end, shut off device 23 is coupled between utility switch 24 and main service panel 26. Shut off device 23 has two functions. First, shut off device 23 (under control) may be used to prevent a consumer from consuming electricity (by way of consumer loads 28). Second, shut off device 23 may also be used to prevent a consumer from generating electricity (from CPE 10) and delivering it onto power grid 32. In addition to shut off device 23, there is another component used to interrupt power. That device is shut off device 27, and it is coupled between main service panel 26 and meter 30. A utility or its agent may use shut off device 27 to shut off power supplied to the consumer. Shut off devices 23 and 27 may be a local device such as a switch or similar component or a device that is remotely controlled. The switch or similar component may be mechanical or electronic wherein codes may be entered (for example) for continued operation. As indicated above, shut off devices 25 and 27 may be remotely controlled by wired or wireless communication (coupling with control source 29). Conventional wireless communication includes satellite, radio (e.g., UHF/VHF) and cellular technology.
  • Whether wired or wireless communication (remote) is used, shut off (using devices 23 and 27) may be accomplished by deactivation or reactivation. With deactivation, CPE 10 is shut off when appropriate codes are sent. The lender may send such codes when the consumer fails to make an incremental payment by a default cure date set forth in a written notification sent to the consumer. With reactivation, CPE 10 automatically shuts off and cannot generate power until control device 29 sends a reactivation codes. The lender shall send such codes when the consumer makes an incremental payment by a default cure date. A utility may also shut off power supplied to the consumer under similar circumstances (as provided in the agreement between lender/creditor and consumer). This is described in more detail below.
  • Shut off device 27 may be used to interrupt/shut off (1) electricity supplied to the consumer and (2) electricity generated by CPE 10 and delivered onto power grid 32. In this configuration, shut off device 27 may prevent electricity from flowing toward grid 32. However, in this configuration, shut off device 27 is not capable of preventing a consumer from consuming electricity (via consumer loads 28) generated by CPE 10. For this purpose, shut off device 23 is used. If a configuration incorporates control source 29 for shut off (as opposed to a switch), control source 29 may remotely control and shut off device 23 to cut off power consumed by consumer loads 28. It is noted that there may be many other types of shut off and controlling components and configurations to achieve power interruption.
  • Now, if a lender (under an arrangement as discussed below) desires to shut off power generated by the CPE in accordance with an embodiment of the present invention, a lender may do so in several ways. As indicated above, a lender may use control source 29 to control the operation of shut off devices 23 and 27. In addition, either DC fused switch 18 or AC fused switch 22 may be “switched” or disconnected to stop power generation and delivery. In addition, DC/AC inverter may be removed to ensure that power is not generated and consumed or delivered onto power grid 32. There may be other switches or components that may be incorporated into CPE 10 or outside of CPE 10. For example, a switch may be used between meter 30 and main service panel 26. Any switch discussed may have a locking or key mechanism in place to prevent unauthorized “turn on” or “shut off.” If a lender desires to shut off utility power as authorized by a consumer under an agreement (discussed below) or a utility desires to shut off supplied power on its own volition, shut off device 27 may be used to cut off supplied power.
  • Reference is made to FIG. 3 wherein an arrangement, i.e., an agreement between the lender 15 (also known and referred to herein as “creditor,” “vendor” and “PPA Investor”) and consumer/borrower 25 for financing consumer premises equipment (CPE) is shown. The relationship is commemorated or represented by a written contract such as financial instrument 35 in accordance with an embodiment of the present invention. Financial instrument 15 may take many forms including, without limitation, a power purchase agreement (PPA). The agreement or relationship may alternatively be represented by any other legal arrangement (in accordance with the present invention) between a financing entity and a consumer to achieve the same result. Regardless of the type of arrangement, the agreement must abide by applicable State and Federal law.
  • Examples of such State laws include the Uniform Commercial Code (UCC) and the Uniform Computer Information Transactions ACT (UCITA). With respect to the UCC, power shut off may constitute a form of self-help repossession under the Uniform Commercial Code (UCC). Under Article 9 of the UCC, the law provides creditors who have secured a loan (with a consumer) against certain designated collateral (goods) the right to seize the collateral in the event the consumer defaults on the loan without resorting to the judicial system. In addition, the use of self-help repossession in a software context (e.g., embedding the licensed software with code to disable use) may also be governed by sections 814-816 of UCITA (depending on the State). Sections 814-816 enable small and medium-sized licensors of software to enforce their contractual rights quickly and efficiently without resort to judicial process. Today, only Maryland and Virginia have adopted this Act (applicable UCITA sections are based on proposed Section 2B of the UCC which ultimately was not passed into law). State law dictates the rules and regulations of shutting off power (whether manually or electronically performed). Most States also have laws relating to consumer credit. Examples of such Federal laws may include “The Truth in Lending Act,” “Equal Credit Opportunity Act,” “Fair Credit Reporting Act” and several other Federal laws.
  • Financial instrument 35 shall include several provisions or features relating to the transaction between lender 15 and consumer/borrower 25. For one thing, financial instrument 35 shall include a provision (i.e., language) describing the collateral against which the loan is secured. Collateral may be personal property or real property. For example, collateral may be CPE 10, rebates, credits and subsidies, and/or the real property upon which CPE 10 is disposed. These are examples of collateral. Financial instrument 35 shall also give the lender 15 the authority to foreclose or make a claim to the collateral in the event the consumer defaults on the loan or breaches the agreement in other ways. For purposes of this application, the term “provision” shall mean any portion, text, section or language of an agreement between a consumer and lender for financing CPE. The terms “provision” and “section” are used interchangeably in this application. When discussing a provision of the agreement between the lender and consumer herein, the provision may be in the body of the agreement, or alternatively, it may be set forth in an attachment to the agreement. In this respect, the agreement shall incorporate the attachment by reference therein.
  • In particular, when a consumer fails to make a loan payment (for example) by its due date, is in non-financial default of the loan agreement (for example not paying for insurance), or alternatively, when a consumer fails to pay a PPA payment by its due, a “default” typically occurs. In general, a default is a legal term that means the failure to make a payment when due, which can lead to a notice of default and the start of foreclosure proceedings if the debt is secured by real property or a repossession if secured by personal property. However, default shall also include any breach (violation) by the consumer of one or more provisions or conditions of the contractual arrangement between the lender and consumer (e.g., a PPA or other legal arrangement). An example of this is a consumer's failure to maintain insurance coverage on the CPE as required by the agreement. The agreement will determine what ultimately constitutes a default. In addition, State law may provide limitations on a default provision in the agreement.
  • In many legal arrangements, consumers may have the right to “cure” a default. State law also may require the right to cure. For example, Title 9-A, Sections 5-110 and 5-111 of Maine's Consumer Credit Code provides a right to cure for a default based on the consumer's first failure to make a required payment under a consumer credit transaction. Under Sections 5-110 and 5-110, a creditor may neither accelerate maturity of an unpaid balance of the obligation, nor take possession of or otherwise enforce a security interest in goods that are collateral until fourteen days after a notice of the consumer's right to cure is sent, as provided in section 5-110. Many States laws prescribe detail steps with respect to consumer credit, default, notification and collateral repossession.
  • In the event a right to cure a default is conferred by agreement and/or or State law, the lender will notify the borrower of the default (or missed payment depending on required language) and afford the borrower the opportunity to cure the default within a period of time. This notification may include other information including the specific clause breached and/or State law requiring such notification. Notification will likely be in written form, but could be sent by email or other communication recited in the agreement or required by State law.
  • In order to cure a default as indicated above, the consumer must “fix” their breach/violation of their legal obligations under the financial instrument (including a PPA) or other contractual arrangement. In the event a consumer fails to make a payment for example, the consumer may cure the breach of contract by tendering to the lender/creditor the missed loan payment (plus any late fees as required by the loan) or power purchase payment under a PPA. If cure is specifically provided (under the contract or State law), a financial instrument (including a PPA) or other contractual arrangement usually states a time period in which the consumer (or borrower) may cure the default. If the consumer does not cure in accordance with the loan agreement (financial instrument) and/or State law, the lender must decide how to obtain the money it is owed or to fix a non-monetary default. Typically, enforcement of a loan upon a default is done by foreclosure (usually refers to real property) or repossession (personal property). Under a PPA, there is no such thing as foreclosure or repossession. However, a “remedy” is likely provided in the agreement. For purposes of this application, a remedy in a PPA is treated the same as a foreclosure or repossession. Foreclosure is a method of enforcing a security interest in property. Repossession is another method of enforcing a security interest in personal property (depending on state law). The lender may have other remedies prescribed in the agreement and/or by State law (e.g., UCC). Foreclosure, however, is expensive and time consuming. For this reason, the financial instrument 35 (including PPA) or other legal financing agreement shall include provisions permitting the lender to (1) enter the consumer's premises (by way of an easement or license), (2) inspect CPE 10 and/or act upon CPE 10 including shutting the power off of (using shut off device 23 for example) and possibly shutting off power supplied to a consumer by a utility using device 27). This is discussed in detail below with respect to FIGS. 3 and 4.
  • Returning to FIG. 3, in summary, financial instrument 35 shall also include one or more provisions or language describing the loan amount, the interest rate, what constitutes a default, the rights of the lender 15 (creditor) and consumer upon default including shut off remedies, maintenance of CPE 10, insurance for the equipment and/or other terms. In addition (as described above), financial instrument 35 shall also include a provision(s) or language granting an easement or license to enable lender 15 or its agent to enter the real property of the consumer/borrower 25 and to act upon CPE 10 in some way (shut off, inspect, modify CPE 10 as described below). An easement (the one herein discussed is historically called easement in appurtenant or covenant) is a legal right or restriction that attaches to the property in which CPE 10 is disposed.
  • In this respect (i.e., easement), lender 15 may enforce his right to enter the real property against all who own or lease the real property on which the CPE 10 is disposed (particularly if the loan agreement (or PPA) is transferred to the new owner or lessee). It is not a personal right or restriction that cannot be transferred (i.e., the personal right or restriction typically extinguishes when the real property is sold to another). As described above, the provision with the easement may be in the body of the agreement between lender and consumer or may be part of an attachment incorporated by reference into the agreement. Under state law, it is likely that such as easement must be recorded with the appropriate state governmental recording agency.
  • In another embodiment, the easement may additionally or alternatively grant the lender 15 a right to continue operation of the CPE 10 on the real property of the consumer/borrower 25, in the case of default and/or repossession of the CPE 10. This provides the lender 15 an ability to continue generation of power and direct it onto a power grid or another location or storage facility/unit. Thus, CPE 10 may generate revenue even in the case of default and/or repossession of the CPE 10.
  • As an alternative to an easement, financial instrument 35 may provide a license granting the right to enter the real property of consumer 25 and act upon CPE 10. Typically, licenses to enter property, however, are personal and do not run with the land. Therefore, the easement is more advantageous to lender 15. Whatever the mechanism is used to grant property entry and access to CPE 10 (e.g., easement, license or other ingress rights), financial instrument 35 (including a PPA) or other arrangement shall set forth the length of time in which lender 15 shall have the right to access the property. In most cases, the right shall extend for the loan period or other period in which payment must be made (e.g., PPA periodic payments for power generated by CPE 10).
  • It should be noted that the agreement (financial instrument 35 including PPA or other arrangement) shall grant access to enter the consumer's real property (premises) even if the lender expects to remotely shut off a consumer's power (in the event of default). Property access will permit lender 15, upon its sole discretion, to inspect CPE 10 and either modify CPE 10 or instruct the consumer to make such modifications, as required by financial instrument 35. This will ensure that CPE 10 will optimally generate power during the course of the arrangement between lender 15 and consumer 25 (until lender determines otherwise in accordance with the agreement and/or State law).
  • As part of the agreement, lender 15 shall require that consumer 25 execute any additional legal real property documents necessary to enable lender 15 to secure the easement or other legal rights (to enter the property) and to perfect such rights against third parties. Such documents may require notarization. In order to perfect such security document, lender 15 shall typically file such documents (e.g, easements) at the government recordation office in which the real property is located. The appropriate governmental office may be a county recorder's office, Secretary of State or department of corporation's office. However, State law ultimately governs recordation procedure and filing.
  • As indicated above, financial instrument 35 shall include a provision(s) or language granting lender 15 the right to (1) inspect the CPE 10, (2) remove the CPE 10, (3) shut off (also known as disconnected, interrupted or “intervention”) power locally or remotely generated by CPE 10 based on specified breaches (violations of financial instrument 35) and/or (3) modify and maintain the CPE 10 to ensure maximum power generation. In the event lender 15 decides to shut off consumer power under the agreement, lender 15 shall notify consumer 25 and give a certain period to cure the breach of agreement to avoid shut off. Financial instrument 15 will likely require such notification (even if State law does not require it).
  • In addition, the provisions described herein granting rights to enter the consumer premises and act upon the CPE 10 may apply to agents (or other third parties such as the trustee in a deed of trust) acting on behalf of lender 15 including installers, inspectors or other entities instructed to perform services for lender 15. These agents granted such rights may also include a utility, as a third party beneficiary, supplying power to consumer 25. In this respect, the utility would have the right (and may be required as authorized in the agreement between lender 15 and consumer 25) to enter the property and/or to shut off power (i.e., power intervention or interruption) supplied to the consumer by the utility (for breaches of the agreement between lender 15 and consumer 25).
  • In the event a consumer defaults and financial instrument 35 grants lender 15 the right to force a utility to shut off power, financial instrument should reference and possibly incorporate the utility agreement (between consumer and utility). Financial instrument 35 shall also require that lender 15 to follow the rules and requirements of such utility agreement with respect to power discontinuance. PG & E of California, for example, has a tariff agreement in which power discontinuance rules are prescribed. See domain page at pge.com/tariffs/ER.SHTML#ER. This agreement is incorporated herein by reference.
  • Financial Instrument 35 shall also include a provision or section requiring the consumer to notify lender 15 if for legal reasons why lender 15 shall not shut off power in the event of a default by the consumer. For example, a consumer may legally require life support equipment to stay alive. Such equipment requires power for operation. Lender 15 may check a consumer's meter tags (indicating that power must not be shut off) and/or the utility company database for people on life support. Such provisions may require a lender to check a consumer's meter tags and/or check the utility company database for people on life support. See PG&E's Service for Medical Baseline and Life Support Customers. (See domain page at pge.com/res/financial_assistance/medical baseline_life_support/) In addition, the agreement provision or section may provide a specific email, postal or other address to which the notification shall be sent.
  • Financial instrument 35 may also include a provision or section with a power of attorney. This power of attorney will govern communication between the consumer 25 and the utility, relevant State PUC and possibly other entities. The language may state that this power of attorney is irrevocable. Note that State law ultimately governs such provisions.
  • While the discussion above pertains to a financial instrument involving a loan, the contractual provisions or language pertaining to the right to enter the property (e.g., easement) and the right to act upon CPE 10 (e.g., interrupt CPE functions, inspect CPE and modify CPE, etc.) may be included in any other legal agreement between the parties concerning the purchase of power generated by the CPE 10, or lease or use of CPE 10 to generate power. In the event that power interruption or shut off is the desired action by any authorized party under any contractual arrangement, power may be interrupted or shut off locally or (alternatively) remotely. If action is performed locally, lender 15, its agent or any contractually authorized party may enter the property to perform the task mechanically (using shut off devices 23 and 27). For example, shut office devices 23 and 27 may be a key or switch to interrupt power. Alternatively, lender 15 may remove inverter 20 or any other component provided such removal does not damage CPE 10 or the real property on which CPE 10 is positioned. (It should be noted that power might be shut off for safety reasons.)
  • In the event interruption or shut off is to be performed remotely, lender 15 may achieve this goal electronically by wire or wireless connection as described above (using shut off devices 23 and 27). For example, lender 15 may interrupt or shut off power by means of a codes/software deactivation or reactivation. Specifically, CPE 10 purchased (or used or leased under a PPA) by consumer 25 may include software under license to consumer 25. If consumer 25 fails to make a loan payment (or other default as described herein), lender 15 (agent or another authorized to act on its behalf such as a vendor) may deactivate CPE 10 remotely (traditionally via software execution). Alternatively, such software may require periodic reactivation codes or keys to enable consumer 25 to continue to use CPE 10 to generate power. In the event consumer 25 fails to make a loan payment, consumer 15 will not receive reactivation codes until consumer 25 cures the breach.
  • Financial Instrument 35 (including a PPA) or any other agreement between the consumer and lender for financing renewable energy CPE will not only be executed by the parties, but will likely be also be notarized. Alternatively, lender 15 may use a medallion guarantee to guarantee financial instrument 15 from forgery. (In the United States, a medallion signature guarantee is a special signature guarantee for the transfer of securities. It is a guarantee by the transferring financial institution that the signature is genuine and the financial institution accepts liability for any forgery. Signature guarantees protect shareholders by preventing unauthorized transfers and possible investor losses. They also limit the liability of the transfer agent who accepts the certificates.) In addition, execution of the agreement (i.e., the transaction) may be evidenced by electronic recordation including videotape or other means of proof.
  • Reference is now made to FIG. 4 wherein a flowchart is shown that illustrates the steps of a method for either shutting off or maintaining power generation on a consumer's premises (real property). In this method, it is presumed that a lender has provided a loan to a consumer for the purchase of CPE 10. In the normal course of any financing mechanism or process, consumer 25 will make payments to lender 15 on an incremental basis. Terms typically require monthly payment increments but any period may be required. Payments are shown at step 35. Execution then moves to decision step 45 wherein it is determined whether consumer 25 has made the relevant incremental payment. If the consumer has made the relevant payment, execution returns to step 45. If consumer 25 fails to make a payment, consumer 25 is in default for failure to make the appropriate incremental payment. Execution moves to decision step 55 wherein it is determined if consumer's failure to make a payment has triggered a default-remedy provision under the terms of financial instrument 35. Such a provision will be triggered if notice is provided to consumer 25 with appropriate information and cure date.
  • If a default-remedy provision is not yet triggered, lender 15 shall notify consumer 25 at step 65 of the failed payment, (2) the default provision breached, (3) the deadline in which payment must be received (cure date), (4) the location in which payment must be delivered or sent and (5) the remedies provided under the agreement and State law that lender may use to enforce the agreement. There may be other information set forth in the notification.
  • Now, if consumer 25 failed to make the payment by the cure date, lender 15 shall notify consumer 25 that consumer 25 is in default, consumer 25 has breached the agreement by his/her failure to make payment by the cure date, the default-remedy provision(s) of financial instrument 35 are triggered and that power generated by CPE 10 may be interrupted or shut off by a specified date, or alternatively the CPE 10 must be continued in operation for the benefit of the lender 15, unless payment is not received immediately. At this time, lender 15 has all of the available remedies provided under financial instrument (agreement) 35 as well as under State law.
  • Execution then moves to decision step 85 wherein lender 15 determines whether it wishes to interrupt or shut off power, or alternatively continue operation for the benefit of the lender 15. If the answer is no, lender 15 may wish to take advantage of other remedies such as garnishing employment wages of consumer at step 95 or alternatively foreclosing on the consumer's property or taking other action to obtain the money to repay the loan. Lender 15 may also enter the property to perform maintenance on CPE 10 to ensure CPE 10 continues to generate power at steps 105 and 115, respectively, for the following reason. Lender 15 may desire to claim the collateral in accordance with financial instrument 35. The collateral may include the CPE 10 for example, the power generated by the CPE 10, the receivables paid/credited by a utility for power generated by the CPE 10 or other property. Alternatively, lender 15 may be receiving payments from utility directly. As indicated, lender wants to ensure that CPE 10 generates power to receive the benefits from that power (e.g., receivables). Lender 15 may have other options against consumer 25 to repay the loan.
  • In the event the answer to decision step 85 is yes and lender 15 decides to interrupt or shut off power (CPE 10), execution moves to decision step 125 wherein lender decides if it will interrupt or shut off power locally (mechanically). If the answer is yes, lender 15 shall enter the real property at step 135 and interrupt or shut off power at the consumer's premises a step 145. This may be accomplished by switch, component removal or other mechanical or electro-mechanical means. In the event the answer is no to decision step 125 and lender 15 desires to interrupt or shut off power remotely, lender 15 has several options to accomplish this task, but such options will depend on the system components of CPE 10 and the specific provisions (e.g., easements, licenses etc.) of financial instrument 35 and any related documents. As described above, lender 15 may deactivate CPE 10 remotely as described above by sending codes/software (using shut off device 23). Alternatively, lender 15 may not transmit activation codes or keys to ensure continuous operation of CPE 10 (until payment is received). Interruption/shut off may be by wired or wireless communication (remotely). Shut off may, however, be accomplished in many ways (described above).
  • In addition to the lenders authority to interrupt or shut off power (step 85), a utility may also be authorized (and required) to interrupt or shut off power. This is shown in decision step 155 connected in parallel to step 85 (dashed lines). The utility will also have the choice of interrupting power locally or remotely (steps 125 and 155) as described above depending on the grid connection and system used. The utility may choose not to shut off power, but may wish to enter the real property to access the equipment (for inspection or modification. This equipment may be utility owned equipment or possibly CPE 10.
  • While the method of FIG. 4 applies to breaches (violations of the agreement) by means of a failure to make payment, any breach of a condition or provision may be cause for property entry and/or power interruption or shut off. For example, any failure to maintain insurance for CPE 10 or pay real or personal property taxes as required by financial instrument 35 may be subject to power shut off. In addition, the arrangement described with respect to the method in FIG. 4 is a financial instrument (e.g., a PPA or other security agreement). However, any legal arrangement may be used for this method including a PPA or any other legal arrangement.
  • The foregoing description of the embodiments of the invention has been presented for purposes of illustration and description. It is not intended to be exhaustive or to limit the invention to the precise form disclosed and modifications and variations are possible in light of the above teachings or may be acquired from practice of the invention. The embodiments were chosen and described in order to explain the principles of the invention and its practical application to enable one skilled in the art to utilize the invention in various embodiments and with various modifications as are suited to the particular use contemplated. It is intended that the scope of the invention be defined by the claims appended hereto and their equivalents.
  • APPENDIX Terms and Definitions
  • “collateral” shall mean any property or asset pledged by a borrower to secure a loan or other credit, and subject it to seizure in the event of default.
  • “consumer” shall mean a user or purchaser of power (electricity).
  • “computer implementation” (also known referred to “computer implemented”) shall mean the execution of any or all process steps by computer.
  • “consumer premises equipment” (also known or referred to as “CPE,” “consumer premises equipment” “renewable energy consumer premises equipment” and “renewable energy CPE”) shall mean the physical assets of the CPE such as any and all renewable energy equipment that resides (or is disposed) on or near a residential building, business, institution or other real property. CPE shall include solar components as the renewable energy equipment (source) and any and all mounting equipment. Alternatively, CPE may include any other renewable equipment such as wind, biomass or water (hydroelectric) energy generation equipment as well as non-renewable energy sources.
  • “credits” shall mean any money or other valuable consideration offered to an entity for certain defined acts.
  • “deed of trust” shall mean a document which pledges real property to secure a loan by a consumer. The property is deeded by a title holder (trustor) to a trustee (often a title or escrow company), which holds the title in trust for the beneficiary (the lender of the money). When the loan is fully paid, the trustor requests the trustee to return the title by reconveyance. If the loan becomes delinquent or is in default, the beneficiary can file a notice of default and, if the loan is not brought current, the trustee can demand that the trustee begin foreclosure on the property so that the beneficiary may either be paid or obtain title.
  • “default” shall mean the failure to make a payment when due, which can lead to a notice of default and the start of foreclosure proceedings if the debt is secured by real property or a repossession if secured by personal property. Default shall also include any breach (violation) by the consumer of one or more provisions or conditions of the contractual arrangement (e.g., a PPA or other legal arrangement) between the lender and consumer. An example of this is a consumer's failure to maintain insurance coverage on the CPE as required by the agreement.
  • “easement” shall mean the legal right or restriction that enables an entity to enter the real property of another entity. An easement attaches to the real property and therefore may be enforced against all who own or lease the real property.
  • “entity” shall mean any person, group of persons, company, division, agency, partnership or other entity (private or government). Entity includes, without limitation, a consumer, lender or other party.
  • “financial instrument” shall mean any real or virtual document representing a legal agreement involving some sort of monetary value. Such financial instrument shall include an agreement between a lender (also known and referred to herein as “creditor,” “vendor” and “PPA Investor”) and consumer/borrower for financing consumer premises equipment (CPE). A power purchase agreement (PPA) is an example of a financial instrument. Financial instruments shall include “notes.” Financial instruments are also known as securities.
  • “foreclosure” shall mean a method of enforcing a security interest in real property.
  • “intervention” (also referred to as “shut off”) means the interference of or the ability (i.e., the right) to interfere with a consumer's ability to use power generated by the CPE or provided by a utility.
  • “lender” (also referred to as “creditor,” “vendor,” and “PPA Investor”) shall mean an entity that provides the financing for the CPE. A lender shall include an entity that provides a loan to a consumer for the purchase of the CPE or a PPA investor that actually purchases CPE for power generation and purchase by a consumer.
  • “license” shall mean the right of one entity to enter the real property of another. A license does not attach to the real property and therefore cannot be enforced against all who own or lease the real property.
  • “loan” shall mean an arrangement in which a lender gives money to a borrower (e.g., the consumer), and the borrower agrees to repay the money, usually along with interest, at some future point(s) in time. A loan is usually evidenced by a specific financial instrument (or financial instruments).
  • “mortgage” (or “mortgages”) shall mean a debt financial instrument by which the borrower (mortgagor or consumer) gives the lender (mortgagee) a lien on property as security for the repayment of a loan.
  • “personal property” shall mean property of any kind except real property. Personal property may be tangible, having physical existence, or intangible, having no physical existence, such as financial instruments. Personal property shall include, without limitation, receivables, credits, subsidiaries.
  • “power purchase agreement” (also known as “PPA”) shall mean an agreement in which a PPA Investor agrees to purchase and install CPE, and the consumer agrees to purchase the power generated by the CPE for a period of time. A power purchase agreement may be treated as or incorporate a lease of the CPE by the consumer.
  • “power” shall mean electricity. Power is also known as or referred to as “electricity” or “energy.”
  • “power grid” (also known as the “power transmission and distribution grid,” “electric grid” or “grid”) shall mean the network of transmission and distribution lines (and the step-up and step-down transformers) that is used to deliver electricity to consumers.
  • “PPA Investor” shall mean an entity that provides the financing for CPE in connection with a power purchase agreement with a consumer.
  • “provision” shall mean any portion, text, section or language of an agreement between a consumer and lender for financing CPE. The terms “provision” and “section” are used interchangeably in this application. A provision may be in the body of the agreement, or alternatively, it may be set forth in an attachment to the agreement.
  • “rebates” shall mean a deduction from the amount due or a return of part of an amount given in payment.
  • “receivables” shall mean any payment, instrument or other valuable consideration owed to an entity (e.g., consumer) for the power generated by the CPE, whether or not such payment, instrument or other valuable consideration is currently due. The receivables may be provided by a utility or other entity. Receivables shall include, without limitation, any credit, money certificate or other quantifiable value for power generated by a CPE.
  • “real property” shall mean the land as well as any permanent fixtures on it including buildings, trees and other fixtures.
  • “renewable energy” shall mean power supplied by energy sources that are naturally and continually replenished such as wind, solar power, geothermal, hydropower, and various forms of biomass.
  • “renewable energy source” shall mean sources of renewable energy such as water (hydroelectric power), wind, biomass and solar energy.
  • “shut off” (also known as “disconnected”, “interrupted” and “intervention”) shall mean the interference with a consumer's use of power generated by the CPE or provided by a utility.
  • “subsidies” shall mean a monetary grant given by government to lower the price of a good such as CPE, generally because they are considered to be in the public interest.
  • “utility” shall mean any entity that purchases, sells or markets power to (or from) the consumer of power or has the primary relationship with that consumer.

Claims (9)

1. A system for increasing a likelihood of timely receiving payment for financing renewable energy consumer premises equipment (CPE) by a consumer for power generation at a consumer premises, the system comprising:
a renewable energy CPE installed at a consumer premises for power generation, the renewable energy CPE coupled to a power grid to enable delivery of power generated by the renewable energy CPE onto the power grid;
a control device operable to control power at the consumer premises;
an agreement between the consumer and a lender enabling the consumer to purchase the renewable energy CPE with a loan provided by the lender to the consumer and enabling the lender to control power at the consumer premises by operating the control device.
2. The system of claim 1, wherein the control device can be operated remotely.
3. The system of claim 1, wherein the control device is coupled between a main service panel on the consumer premises and the renewable energy CPE, and the control device can be used to disconnect the renewable energy CPE from the main service panel according to terms defined at least in part by the agreement.
4. The system of claim 2, wherein the control device is coupled between a main service panel on the consumer premises and the power grid, the control device being operable to disconnect the consumer premises from the power grid.
5. A system comprising:
a renewable energy consumer premises equipment (CPE) installed at a consumer premises for power generation and coupled to a power grid to enable power delivery onto the power grid, the CPE purchased by the consumer with a loan provided by a lender according to an agreement granting the lender rights to control power at the consumer premises;
a main service panel located at the consumer premises;
a first control device coupled between the CPE and the main service panel, the first control device operable by the lender according to the agreement;
a second control device coupled between the main service panel and a power grid providing power to the consumer premises, the second control device operable by the lender according to the agreement.
6. The system of claim 5, wherein the first control device is operable to disconnect the CPE from the main service panel.
7. The system of claim 5, wherein the second control device is operable to disconnect the main service panel from the power grid.
8. A business method of increasing the probability of timely receiving payment for financing renewable energy consumer premises equipment (CPE) by a consumer for power generation at a consumer premises, the renewable energy CPE adapted to deliver power onto a power grid, the method comprising:
providing a loan to a consumer by a lender for the consumer's purchase of renewable energy CPE;
making payments incrementally by a consumer to the lender over a period of time to repay the loan; and
controlling the power generated by the renewable energy CPE.
9. The business method of claim 8, further comprising controlling the power delivered by the power grid.
US11/958,346 2007-01-12 2007-12-17 Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment Abandoned US20080172330A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US11/958,346 US20080172330A1 (en) 2007-01-12 2007-12-17 Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment

Applications Claiming Priority (8)

Application Number Priority Date Filing Date Title
US11/653,325 US20080091590A1 (en) 2006-10-17 2007-01-12 Methods, systems and financial instruments for financing renewable energy consumer premises equipment
US11/653,167 US20080091626A1 (en) 2006-10-17 2007-01-12 Systems, methods and financial instruments for renewable energy consumer premises equipment financing
US11/653,052 US7890436B2 (en) 2006-10-17 2007-01-12 Billing and payment methods and systems enabling consumer premises equipment
US11/653,043 US20080091580A1 (en) 2006-10-17 2007-01-12 Methods for cost reduction and underwriting considerations for financing renewable energy consumer premises equipment (CPE)
US11/652,712 US20080091589A1 (en) 2006-10-17 2007-01-12 Method for underwriting the financing of solar consumer premises equipment
US11/653,044 US20080091581A1 (en) 2006-10-17 2007-01-12 Systems and methods of reducing financing costs for renewable energy consumer premises equipment
US11/750,941 US7698219B2 (en) 2007-01-12 2007-05-18 Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment
US11/958,346 US20080172330A1 (en) 2007-01-12 2007-12-17 Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
US11/750,941 Division US7698219B2 (en) 2007-01-12 2007-05-18 Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment

Publications (1)

Publication Number Publication Date
US20080172330A1 true US20080172330A1 (en) 2008-07-17

Family

ID=39618510

Family Applications (2)

Application Number Title Priority Date Filing Date
US11/750,941 Active US7698219B2 (en) 2007-01-12 2007-05-18 Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment
US11/958,346 Abandoned US20080172330A1 (en) 2007-01-12 2007-12-17 Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment

Family Applications Before (1)

Application Number Title Priority Date Filing Date
US11/750,941 Active US7698219B2 (en) 2007-01-12 2007-05-18 Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment

Country Status (1)

Country Link
US (2) US7698219B2 (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080172346A1 (en) * 2007-01-12 2008-07-17 Clean Power Finance, Inc. Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment
US20090024541A1 (en) * 2007-07-20 2009-01-22 Gary Kremen Power purchase methods, agreements and financial instruments for tax-advantaged financing residential renewable energy equipment
US20090055300A1 (en) * 2007-07-17 2009-02-26 Mcdowell Grant Method and system for remote generation of renewable energy
US20090157545A1 (en) * 2007-11-19 2009-06-18 Morgan Stanley Facilitating the ownership of solar-powered electricity-generating systems
US20090222320A1 (en) * 2008-02-29 2009-09-03 David Arfin Business model for sales of solar energy systems
US20090234685A1 (en) * 2008-03-13 2009-09-17 Ben Tarbell Renewable energy system maintenance business model
US20100010939A1 (en) * 2008-07-12 2010-01-14 David Arfin Renewable energy system business tuning
US20100057480A1 (en) * 2008-08-27 2010-03-04 David Arfin Energy Services
US20100057544A1 (en) * 2008-09-03 2010-03-04 Ben Tarbell Renewable energy employee and employer group discounting
US20100223180A1 (en) * 2007-01-12 2010-09-02 Gary Kremen Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment
US7890436B2 (en) 2006-10-17 2011-02-15 Clean Power Finance, Inc. Billing and payment methods and systems enabling consumer premises equipment
US7904382B2 (en) * 2008-03-11 2011-03-08 Solarcity Corporation Methods for financing renewable energy systems
US20110173110A1 (en) * 2008-03-13 2011-07-14 Solarcity Corporation Renewable energy system monitor
US20140074556A1 (en) * 2012-09-13 2014-03-13 James Louis Garner Method for Financing and Operating Onsite Renewable Energy Systems with Aggregated Onsite Demand
WO2021096785A1 (en) * 2019-11-12 2021-05-20 Zola Electric Labs Inc. Method and system for automatically controlling electrical power supply based on payment status

Families Citing this family (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8412643B2 (en) * 2008-03-07 2013-04-02 Eqs, Inc. Apparatus, system, and method for quantifying, bundling, and applying credits and incentives to financial transactions
US8032436B2 (en) * 2008-05-05 2011-10-04 James Dailey Systems and methods for facilitating aggregation of social credits
WO2010076610A1 (en) * 2008-12-30 2010-07-08 Renault Trucks Onboard vehicle system and method for configuring vehicle functionalities
US8352091B2 (en) 2009-01-02 2013-01-08 International Business Machines Corporation Distributed grid-interactive photovoltaic-based power dispatching
US20100175741A1 (en) * 2009-01-13 2010-07-15 John Danhakl Dual Axis Sun-Tracking Solar Panel Array
US20100200191A1 (en) * 2009-02-11 2010-08-12 American Ecothermal, Inc. Geothermal heating and cooling system and method
US8693228B2 (en) 2009-02-19 2014-04-08 Stefan Matan Power transfer management for local power sources of a grid-tied load
US20100299270A1 (en) * 2009-05-19 2010-11-25 Maglaque Chad L System and method for energy device activation
GB201008368D0 (en) * 2010-05-20 2010-07-07 Moore Jesse K Mobile meter
US8725330B2 (en) 2010-06-02 2014-05-13 Bryan Marc Failing Increasing vehicle security
US8401711B2 (en) 2010-10-28 2013-03-19 Solar Chief, Llc System and method for managing distributed renewable energy systems
US10069454B2 (en) 2010-10-28 2018-09-04 Solar Chief, Llc System and method for managing distributed renewable energy systems and service providers
EP2672604A4 (en) * 2011-01-31 2017-01-04 Nec Corporation Electrical power management system and electrical power management method
US20140089032A1 (en) * 2012-09-21 2014-03-27 General Electric Company Management system and method
US20160350734A1 (en) * 2014-06-01 2016-12-01 Gideon Samid Versatile, Real Time, Two-Ways Payment for Power and Utilities
US10038602B2 (en) 2016-06-13 2018-07-31 International Business Machines Corporation Monitoring resource consumption based on fixed cost for threshold use and additional cost for use above the threshold
CN109685220A (en) * 2018-12-07 2019-04-26 融智通科技(北京)股份有限公司 Power grid O&M repairs operational method and platform
CN109685219A (en) * 2018-12-07 2019-04-26 融智通科技(北京)股份有限公司 The O&M repairing operational method and platform of power grid user equipment
US20240028985A1 (en) * 2022-07-20 2024-01-25 Robert R. Tipton Sustainable Business Method for Sustainable Energy Delivery

Citations (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4383210A (en) * 1980-06-18 1983-05-10 Wilkinson Rudolph P Apparatus and method for recharging an energy storage device
US6191501B1 (en) * 1997-02-14 2001-02-20 Merlin Gerin S.A. (Proprietary) Limited Security system for alternative energy supplies
US6195648B1 (en) * 1999-08-10 2001-02-27 Frank Simon Loan repay enforcement system
US20020040356A1 (en) * 2000-09-26 2002-04-04 Gluck Daniel S. Automated new energy technology consulting and demand aggregation system and method
US20020091653A1 (en) * 1997-12-19 2002-07-11 Michael R. Peevey Method and apparatus for metering electricity usage and electronically providing information associated therewith
US20020120569A1 (en) * 1997-10-16 2002-08-29 Day Mark E. System and method for communication between remote locations
US20020128853A1 (en) * 2001-03-12 2002-09-12 Hiroshige Kikuchi Electric appliance renting system
US20020194145A1 (en) * 2002-05-28 2002-12-19 Boucher Thomas Charles Method and system for financing a renewable energy generating facility
US6553353B1 (en) * 2000-01-28 2003-04-22 John Joseph Littlejohn Advanced metering system enabling regulation and billing of utilities by third party interagent
US20030080876A1 (en) * 2001-10-29 2003-05-01 Martin Warren T. Utility disconnect controller
US20030126060A1 (en) * 2000-12-29 2003-07-03 Abb Ab System, method and computer program product for enhancing commercial value of electrical power produced from a renewable energy power production facility
US6717527B2 (en) * 2000-09-29 2004-04-06 Payment Protection Systems, Inc. Vehicle location system
US20040083163A1 (en) * 2002-10-24 2004-04-29 Michael Cooper System and method for purchasing increased efficiency items
US20040117223A1 (en) * 2002-12-13 2004-06-17 Smith Wade W. Water metering system
US20040138981A1 (en) * 2002-03-28 2004-07-15 Ehlers Gregory A System and method of controlling delivery and/or usage of a commodity
US6828692B2 (en) * 2002-05-21 2004-12-07 Payment Protection Systems, Inc. Tampering detector and system disabler
US6870467B2 (en) * 2000-09-29 2005-03-22 Payment Protection Systems, Inc. Tampering detector and system disabler
US20050086341A1 (en) * 2000-06-15 2005-04-21 Enga David A. Utility monitoring and control systems
US6947854B2 (en) * 2000-02-29 2005-09-20 Quadlogic Controls Corporation System and method for on-line monitoring and billing of power consumption
US6980973B1 (en) * 1999-09-07 2005-12-27 Visa International Service Association Self-paying smart utility meter and payment service
US20060031180A1 (en) * 2004-08-03 2006-02-09 Uscl Corporation Integrated metrology systems and information and control apparatus for interaction with integrated metrology systems
US20060276938A1 (en) * 2005-06-06 2006-12-07 Equinox Energy Solutions, Inc. Optimized energy management system
US20060277131A1 (en) * 2005-06-01 2006-12-07 Bacon Richard M Hybrid financing structure for renewable power facilities
US7171287B2 (en) * 2000-09-28 2007-01-30 Siemens Aktiengesellschaft System and method for planning energy supply and interface to an energy management system for use in planning energy supply
US7191150B1 (en) * 2000-02-01 2007-03-13 Fair Isaac Corporation Enhancing delinquent debt collection using statistical models of debt historical information and account events
US20070150366A1 (en) * 2005-12-23 2007-06-28 Sharp Electronics Corporation Integrated solar agent business model

Family Cites Families (41)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4116523Y1 (en) 1965-06-18 1966-07-30
US4597046A (en) * 1980-10-22 1986-06-24 Merrill Lynch, Pierce Fenner & Smith Securities brokerage-cash management system obviating float costs by anticipatory liquidation of short term assets
US4774663A (en) * 1980-07-29 1988-09-27 Merrill Lynch, Pierce, Fenner & Smith Incorporated Securities brokerage-cash management system with short term investment proceeds allotted among multiple accounts
US4346442A (en) * 1980-07-29 1982-08-24 Merrill Lynch, Pierce, Fenner & Smith Incorporated Securities brokerage-cash management system
US4376978A (en) * 1980-07-29 1983-03-15 Merrill Lynch Pierce, Fenner & Smith Securities brokerage-cash management system
US4337466A (en) * 1980-09-02 1982-06-29 Bell Telephone Laboratories, Incorporated Tamper protection for an automatic remote meter reading unit
GB2100528B (en) 1981-06-15 1985-05-09 Bevis Smythe Edward Anthony Power supply connector
GB8704762D0 (en) 1987-02-28 1987-04-01 Terise Ltd D c to a c inverters
DE3805677C2 (en) 1988-02-24 1994-06-01 Gerhard Scherer Electricity distribution cabinet for construction sites
FR2631753B1 (en) 1988-05-20 1992-04-24 Photowatt Int BATTERY CHARGE REGULATOR FOR PHOTOVOLTAIC GENERATOR
DE3918203A1 (en) 1989-06-03 1990-12-06 Nsm Apparatebau Gmbh Kg Monitoring and control device for automatic entertainment machine - has solar-powered accumulator and reserve battery for mains-independent operation
FR2689333B1 (en) 1992-03-30 1995-02-24 Transenergie Regulator and recorder assembly for electrical energy production and storage installation.
GB2281401B (en) 1993-08-28 1997-07-30 Ampy Automation Digilog Electricity comsumption meter
US6460021B1 (en) * 1993-09-28 2002-10-01 William E. Kirksey Collaterally secured debt obligation and method of creating same
US5694552A (en) * 1995-07-24 1997-12-02 Aharoni; Amos Financing method incorporating new use of trade acceptance drafts
FR2746941B1 (en) 1996-03-29 1998-06-12 Schneider Electric Sa PREPAYMENT ENERGY CONTROL SYSTEM WITH AUTOMATIC TEST
US5940809A (en) * 1996-08-19 1999-08-17 Merrill Lynch & Co. Securities brokerage-asset management system
JPH10165232A (en) 1996-12-13 1998-06-23 Matsushita Electric Works Ltd Outdoor table
GB9709604D0 (en) 1997-05-12 1997-07-02 Landis & Gyr Uk Ltd Metering systems
US6154730A (en) * 1997-10-20 2000-11-28 Adams; Edward S. Facility-based financing system
US6025774A (en) * 1998-06-24 2000-02-15 Forbes; Mark P. Method for retrieving vehicular collateral
US6785592B1 (en) * 1999-07-16 2004-08-31 Perot Systems Corporation System and method for energy management
DE10052688A1 (en) * 2000-10-24 2002-05-23 Takata Europa Vehicle Safety T seatbelt device
WO2002037433A2 (en) * 2000-11-01 2002-05-10 International Carbon Bank And Exchange Method and system for banking and exchanging emission reduction credits
US10135253B2 (en) * 2000-12-29 2018-11-20 Abb Schweiz Ag System, method and computer program product for enhancing commercial value of electrical power produced from a renewable energy power production facility
US20030074244A1 (en) * 2001-04-11 2003-04-17 Braxton Charles R. Distributed energy technology assurance
US20030023467A1 (en) * 2001-07-30 2003-01-30 Vlad Moldovan Method for developing and promoting operations and services that are supported by an energy, energy efficiency, water management, environmental protection and pollution prevention fund
JP2003122819A (en) 2001-10-16 2003-04-25 Sharp Corp Management method and system for solar power facility
US20030093345A1 (en) * 2001-11-09 2003-05-15 Cutbirth Michael D. Fund for wind energy projects and a method for establishing the same
US20050165672A1 (en) * 2002-08-14 2005-07-28 Pembroke John J. System and method for bundling telecommunications and utilities into a mortgage
US20050137956A1 (en) * 2003-12-19 2005-06-23 North American Energy Credit And Clearing Corporation Utilizing cash flow contracts and physical collateral for energy-related clearing and credit enhancement platforms
US20060064366A1 (en) * 2004-09-21 2006-03-23 Smith Steven E Method and cash trust for financing and operating a business project
US20070219932A1 (en) * 2006-03-15 2007-09-20 Carroll Scott T Cooperative energy farms and virtual net metering
US20080091590A1 (en) * 2006-10-17 2008-04-17 Gary Kremen Methods, systems and financial instruments for financing renewable energy consumer premises equipment
US7890436B2 (en) * 2006-10-17 2011-02-15 Clean Power Finance, Inc. Billing and payment methods and systems enabling consumer premises equipment
US20080091626A1 (en) * 2006-10-17 2008-04-17 Gary Kremen Systems, methods and financial instruments for renewable energy consumer premises equipment financing
US20080091581A1 (en) * 2006-10-17 2008-04-17 Gary Kremen Systems and methods of reducing financing costs for renewable energy consumer premises equipment
US20080091580A1 (en) * 2006-10-17 2008-04-17 Gary Kremen Methods for cost reduction and underwriting considerations for financing renewable energy consumer premises equipment (CPE)
US20080091589A1 (en) * 2006-10-17 2008-04-17 Gary Kremen Method for underwriting the financing of solar consumer premises equipment
US7698219B2 (en) * 2007-01-12 2010-04-13 Clean Power Finance, Inc. Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment
US20090024541A1 (en) * 2007-07-20 2009-01-22 Gary Kremen Power purchase methods, agreements and financial instruments for tax-advantaged financing residential renewable energy equipment

Patent Citations (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4383210A (en) * 1980-06-18 1983-05-10 Wilkinson Rudolph P Apparatus and method for recharging an energy storage device
US6191501B1 (en) * 1997-02-14 2001-02-20 Merlin Gerin S.A. (Proprietary) Limited Security system for alternative energy supplies
US20020120569A1 (en) * 1997-10-16 2002-08-29 Day Mark E. System and method for communication between remote locations
US20020091653A1 (en) * 1997-12-19 2002-07-11 Michael R. Peevey Method and apparatus for metering electricity usage and electronically providing information associated therewith
US6195648B1 (en) * 1999-08-10 2001-02-27 Frank Simon Loan repay enforcement system
US6980973B1 (en) * 1999-09-07 2005-12-27 Visa International Service Association Self-paying smart utility meter and payment service
US6553353B1 (en) * 2000-01-28 2003-04-22 John Joseph Littlejohn Advanced metering system enabling regulation and billing of utilities by third party interagent
US7191150B1 (en) * 2000-02-01 2007-03-13 Fair Isaac Corporation Enhancing delinquent debt collection using statistical models of debt historical information and account events
US6947854B2 (en) * 2000-02-29 2005-09-20 Quadlogic Controls Corporation System and method for on-line monitoring and billing of power consumption
US20050086341A1 (en) * 2000-06-15 2005-04-21 Enga David A. Utility monitoring and control systems
US20020040356A1 (en) * 2000-09-26 2002-04-04 Gluck Daniel S. Automated new energy technology consulting and demand aggregation system and method
US7171287B2 (en) * 2000-09-28 2007-01-30 Siemens Aktiengesellschaft System and method for planning energy supply and interface to an energy management system for use in planning energy supply
US6717527B2 (en) * 2000-09-29 2004-04-06 Payment Protection Systems, Inc. Vehicle location system
US6870467B2 (en) * 2000-09-29 2005-03-22 Payment Protection Systems, Inc. Tampering detector and system disabler
US20030126060A1 (en) * 2000-12-29 2003-07-03 Abb Ab System, method and computer program product for enhancing commercial value of electrical power produced from a renewable energy power production facility
US20020128853A1 (en) * 2001-03-12 2002-09-12 Hiroshige Kikuchi Electric appliance renting system
US20030080876A1 (en) * 2001-10-29 2003-05-01 Martin Warren T. Utility disconnect controller
US20040138981A1 (en) * 2002-03-28 2004-07-15 Ehlers Gregory A System and method of controlling delivery and/or usage of a commodity
US6828692B2 (en) * 2002-05-21 2004-12-07 Payment Protection Systems, Inc. Tampering detector and system disabler
US20020194145A1 (en) * 2002-05-28 2002-12-19 Boucher Thomas Charles Method and system for financing a renewable energy generating facility
US20040083163A1 (en) * 2002-10-24 2004-04-29 Michael Cooper System and method for purchasing increased efficiency items
US20040117223A1 (en) * 2002-12-13 2004-06-17 Smith Wade W. Water metering system
US20060031180A1 (en) * 2004-08-03 2006-02-09 Uscl Corporation Integrated metrology systems and information and control apparatus for interaction with integrated metrology systems
US20060277131A1 (en) * 2005-06-01 2006-12-07 Bacon Richard M Hybrid financing structure for renewable power facilities
US20060276938A1 (en) * 2005-06-06 2006-12-07 Equinox Energy Solutions, Inc. Optimized energy management system
US20070150366A1 (en) * 2005-12-23 2007-06-28 Sharp Electronics Corporation Integrated solar agent business model

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7890436B2 (en) 2006-10-17 2011-02-15 Clean Power Finance, Inc. Billing and payment methods and systems enabling consumer premises equipment
US9031874B2 (en) 2007-01-12 2015-05-12 Clean Power Finance, Inc. Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment
US20080172346A1 (en) * 2007-01-12 2008-07-17 Clean Power Finance, Inc. Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment
US7698219B2 (en) 2007-01-12 2010-04-13 Clean Power Finance, Inc. Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment
US20100223180A1 (en) * 2007-01-12 2010-09-02 Gary Kremen Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment
US20090055300A1 (en) * 2007-07-17 2009-02-26 Mcdowell Grant Method and system for remote generation of renewable energy
US20090024541A1 (en) * 2007-07-20 2009-01-22 Gary Kremen Power purchase methods, agreements and financial instruments for tax-advantaged financing residential renewable energy equipment
US20090157545A1 (en) * 2007-11-19 2009-06-18 Morgan Stanley Facilitating the ownership of solar-powered electricity-generating systems
US8504471B2 (en) * 2007-11-19 2013-08-06 Morgan Stanley Facilitating the ownership of solar-powered electricity-generating systems
US20090222320A1 (en) * 2008-02-29 2009-09-03 David Arfin Business model for sales of solar energy systems
US8249902B2 (en) 2008-02-29 2012-08-21 Solarcity Corporation Methods of processing information in solar energy system
US8175964B2 (en) * 2008-03-11 2012-05-08 Solarcity Corporation Systems and methods for financing renewable energy systems
US7904382B2 (en) * 2008-03-11 2011-03-08 Solarcity Corporation Methods for financing renewable energy systems
US20110137752A1 (en) * 2008-03-11 2011-06-09 Solarcity Corporation Systems and Methods for Financing Renewable Energy Systems
US20110173110A1 (en) * 2008-03-13 2011-07-14 Solarcity Corporation Renewable energy system monitor
US20090234685A1 (en) * 2008-03-13 2009-09-17 Ben Tarbell Renewable energy system maintenance business model
US20100010939A1 (en) * 2008-07-12 2010-01-14 David Arfin Renewable energy system business tuning
US20100057480A1 (en) * 2008-08-27 2010-03-04 David Arfin Energy Services
US20100057544A1 (en) * 2008-09-03 2010-03-04 Ben Tarbell Renewable energy employee and employer group discounting
US20140074556A1 (en) * 2012-09-13 2014-03-13 James Louis Garner Method for Financing and Operating Onsite Renewable Energy Systems with Aggregated Onsite Demand
WO2021096785A1 (en) * 2019-11-12 2021-05-20 Zola Electric Labs Inc. Method and system for automatically controlling electrical power supply based on payment status

Also Published As

Publication number Publication date
US7698219B2 (en) 2010-04-13
US20080172346A1 (en) 2008-07-17

Similar Documents

Publication Publication Date Title
US7698219B2 (en) Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment
US9031874B2 (en) Methods, systems and agreements for increasing the likelihood of repayments under a financing agreement for renewable energy equipment
US7890436B2 (en) Billing and payment methods and systems enabling consumer premises equipment
US20090024541A1 (en) Power purchase methods, agreements and financial instruments for tax-advantaged financing residential renewable energy equipment
Wiser et al. Financing investments in renewable energy: the impacts of policy design
US20080091580A1 (en) Methods for cost reduction and underwriting considerations for financing renewable energy consumer premises equipment (CPE)
US20080091590A1 (en) Methods, systems and financial instruments for financing renewable energy consumer premises equipment
US20080091626A1 (en) Systems, methods and financial instruments for renewable energy consumer premises equipment financing
US20080091589A1 (en) Method for underwriting the financing of solar consumer premises equipment
US20080091581A1 (en) Systems and methods of reducing financing costs for renewable energy consumer premises equipment
US20130226763A1 (en) Method and system for grouping and marketing consumer premises equipment loans
Hamilton Standard Contracts and Prices for Small Power Producers
Fulton BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Massaro Via Electronic Mail
Runde et al. The Role of Incentives in Green Building Valuation.
MAI et al. The Role of Incentives in Green Building Valuation
Attachment et al. VIA ELECTRONIC FILING
Yes‘No et al. È ANNUAL REPORT PURSUANT TO SECTION 13 OR 15 (d) OF THE SECURITIES EXCHANGE ACT OF 1934
Center et al. Federal Energy Regulatory Commission Washington, DC 20426
Liebmann Regulatory Highlights–The Year 2016 In Review and Implications for 2017
DECISION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Nos Calpine Generating Company, LLC
Law I. BACKGROUND
McFarland C. Self-Regulatory Organization's Statement on Comments on the Proposed Rule Change Received from Members, Participants, or Others No written comments were solicited or re-ceived with respect to the proposed rule change.
Dios The Service Contract Exception to the Tax-Exempt Leasing Restrictions and New Section 7701 (e): Was It Intended to Copy Xerox v. United States

Legal Events

Date Code Title Description
AS Assignment

Owner name: CLEAN POWER FINANCE, INC., CALIFORNIA

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:COLEMAN, DAVID G.;KREMEN, GARY;REEL/FRAME:020347/0338;SIGNING DATES FROM 20070516 TO 20070517

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION