US20100276983A1 - Integration of an in-situ recovery operation with a mining operation - Google Patents
Integration of an in-situ recovery operation with a mining operation Download PDFInfo
- Publication number
- US20100276983A1 US20100276983A1 US12/679,455 US67945508A US2010276983A1 US 20100276983 A1 US20100276983 A1 US 20100276983A1 US 67945508 A US67945508 A US 67945508A US 2010276983 A1 US2010276983 A1 US 2010276983A1
- Authority
- US
- United States
- Prior art keywords
- bitumen
- mining
- production
- extraction
- situ
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
- 238000005065 mining Methods 0.000 title claims abstract description 114
- 238000011065 in-situ storage Methods 0.000 title claims abstract description 85
- 238000011084 recovery Methods 0.000 title claims abstract description 74
- 230000010354 integration Effects 0.000 title description 16
- 239000010426 asphalt Substances 0.000 claims abstract description 163
- 238000004519 manufacturing process Methods 0.000 claims abstract description 160
- 239000012530 fluid Substances 0.000 claims abstract description 121
- 238000000034 method Methods 0.000 claims abstract description 109
- 238000000605 extraction Methods 0.000 claims abstract description 67
- 238000010796 Steam-assisted gravity drainage Methods 0.000 claims abstract description 38
- 238000010794 Cyclic Steam Stimulation Methods 0.000 claims abstract description 11
- 238000010348 incorporation Methods 0.000 claims abstract description 4
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 100
- 230000008569 process Effects 0.000 claims description 53
- 238000000926 separation method Methods 0.000 claims description 38
- 239000002904 solvent Substances 0.000 claims description 37
- 238000012545 processing Methods 0.000 claims description 31
- 238000011282 treatment Methods 0.000 claims description 24
- 239000003085 diluting agent Substances 0.000 claims description 17
- 239000000203 mixture Substances 0.000 claims description 14
- 239000000047 product Substances 0.000 claims description 7
- 239000007788 liquid Substances 0.000 claims description 5
- 238000001556 precipitation Methods 0.000 claims description 5
- 238000010795 Steam Flooding Methods 0.000 claims description 3
- 230000002708 enhancing effect Effects 0.000 claims description 3
- 239000007795 chemical reaction product Substances 0.000 claims description 2
- 238000007872 degassing Methods 0.000 claims description 2
- 238000010438 heat treatment Methods 0.000 claims 3
- 239000007789 gas Substances 0.000 description 22
- 239000003921 oil Substances 0.000 description 16
- 239000003027 oil sand Substances 0.000 description 16
- 239000007787 solid Substances 0.000 description 13
- 239000002002 slurry Substances 0.000 description 10
- 239000000295 fuel oil Substances 0.000 description 9
- 239000002699 waste material Substances 0.000 description 9
- 230000004048 modification Effects 0.000 description 8
- 238000012986 modification Methods 0.000 description 8
- 150000002430 hydrocarbons Chemical class 0.000 description 7
- 230000005484 gravity Effects 0.000 description 6
- 229930195733 hydrocarbon Natural products 0.000 description 6
- 239000004576 sand Substances 0.000 description 6
- 239000004215 Carbon black (E152) Substances 0.000 description 5
- 239000010779 crude oil Substances 0.000 description 5
- 238000003860 storage Methods 0.000 description 5
- 230000008901 benefit Effects 0.000 description 4
- 238000011161 development Methods 0.000 description 4
- 230000009467 reduction Effects 0.000 description 4
- 238000013459 approach Methods 0.000 description 3
- 238000001816 cooling Methods 0.000 description 3
- 230000008030 elimination Effects 0.000 description 3
- 238000003379 elimination reaction Methods 0.000 description 3
- 238000002347 injection Methods 0.000 description 3
- 239000007924 injection Substances 0.000 description 3
- IJGRMHOSHXDMSA-UHFFFAOYSA-N Atomic nitrogen Chemical compound N#N IJGRMHOSHXDMSA-UHFFFAOYSA-N 0.000 description 2
- LYCAIKOWRPUZTN-UHFFFAOYSA-N Ethylene glycol Chemical compound OCCO LYCAIKOWRPUZTN-UHFFFAOYSA-N 0.000 description 2
- PXHVJJICTQNCMI-UHFFFAOYSA-N Nickel Chemical compound [Ni] PXHVJJICTQNCMI-UHFFFAOYSA-N 0.000 description 2
- 239000002253 acid Substances 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 2
- 238000005341 cation exchange Methods 0.000 description 2
- 239000003795 chemical substances by application Substances 0.000 description 2
- 239000004927 clay Substances 0.000 description 2
- 230000007613 environmental effect Effects 0.000 description 2
- 239000000446 fuel Substances 0.000 description 2
- 229910052500 inorganic mineral Inorganic materials 0.000 description 2
- 239000011707 mineral Substances 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 239000010802 sludge Substances 0.000 description 2
- OKTJSMMVPCPJKN-UHFFFAOYSA-N Carbon Chemical compound [C] OKTJSMMVPCPJKN-UHFFFAOYSA-N 0.000 description 1
- 235000008733 Citrus aurantifolia Nutrition 0.000 description 1
- UFHFLCQGNIYNRP-UHFFFAOYSA-N Hydrogen Chemical compound [H][H] UFHFLCQGNIYNRP-UHFFFAOYSA-N 0.000 description 1
- NINIDFKCEFEMDL-UHFFFAOYSA-N Sulfur Chemical compound [S] NINIDFKCEFEMDL-UHFFFAOYSA-N 0.000 description 1
- 235000011941 Tilia x europaea Nutrition 0.000 description 1
- 230000009471 action Effects 0.000 description 1
- QVGXLLKOCUKJST-UHFFFAOYSA-N atomic oxygen Chemical compound [O] QVGXLLKOCUKJST-UHFFFAOYSA-N 0.000 description 1
- 229910052799 carbon Inorganic materials 0.000 description 1
- 238000004517 catalytic hydrocracking Methods 0.000 description 1
- 239000003518 caustics Substances 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 238000004939 coking Methods 0.000 description 1
- 230000001143 conditioned effect Effects 0.000 description 1
- 230000003750 conditioning effect Effects 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000009969 flowable effect Effects 0.000 description 1
- 238000009291 froth flotation Methods 0.000 description 1
- 230000014509 gene expression Effects 0.000 description 1
- 230000020169 heat generation Effects 0.000 description 1
- 239000001257 hydrogen Substances 0.000 description 1
- 229910052739 hydrogen Inorganic materials 0.000 description 1
- WGCNASOHLSPBMP-UHFFFAOYSA-N hydroxyacetaldehyde Natural products OCC=O WGCNASOHLSPBMP-UHFFFAOYSA-N 0.000 description 1
- 239000012535 impurity Substances 0.000 description 1
- 229910003480 inorganic solid Inorganic materials 0.000 description 1
- 238000009413 insulation Methods 0.000 description 1
- 239000004571 lime Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 229910052759 nickel Inorganic materials 0.000 description 1
- 229910052757 nitrogen Inorganic materials 0.000 description 1
- 229910052760 oxygen Inorganic materials 0.000 description 1
- 239000001301 oxygen Substances 0.000 description 1
- 239000003208 petroleum Substances 0.000 description 1
- 238000005498 polishing Methods 0.000 description 1
- 239000002244 precipitate Substances 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 238000012552 review Methods 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- 229910052717 sulfur Inorganic materials 0.000 description 1
- 239000011593 sulfur Substances 0.000 description 1
- 238000011144 upstream manufacturing Methods 0.000 description 1
- 229910052720 vanadium Inorganic materials 0.000 description 1
- LEONUFNNVUYDNQ-UHFFFAOYSA-N vanadium atom Chemical compound [V] LEONUFNNVUYDNQ-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- C—CHEMISTRY; METALLURGY
- C10—PETROLEUM, GAS OR COKE INDUSTRIES; TECHNICAL GASES CONTAINING CARBON MONOXIDE; FUELS; LUBRICANTS; PEAT
- C10G—CRACKING HYDROCARBON OILS; PRODUCTION OF LIQUID HYDROCARBON MIXTURES, e.g. BY DESTRUCTIVE HYDROGENATION, OLIGOMERISATION, POLYMERISATION; RECOVERY OF HYDROCARBON OILS FROM OIL-SHALE, OIL-SAND, OR GASES; REFINING MIXTURES MAINLY CONSISTING OF HYDROCARBONS; REFORMING OF NAPHTHA; MINERAL WAXES
- C10G1/00—Production of liquid hydrocarbon mixtures from oil-shale, oil-sand, or non-melting solid carbonaceous or similar materials, e.g. wood, coal
- C10G1/04—Production of liquid hydrocarbon mixtures from oil-shale, oil-sand, or non-melting solid carbonaceous or similar materials, e.g. wood, coal by extraction
- C10G1/047—Hot water or cold water extraction processes
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/16—Enhanced recovery methods for obtaining hydrocarbons
- E21B43/24—Enhanced recovery methods for obtaining hydrocarbons using heat, e.g. steam injection
- E21B43/2406—Steam assisted gravity drainage [SAGD]
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/34—Arrangements for separating materials produced by the well
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/26—Methods of surface mining; Layouts therefor
- E21C41/31—Methods of surface mining; Layouts therefor for oil-bearing deposits
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D13/00—Large underground chambers; Methods or apparatus for making them
-
- C—CHEMISTRY; METALLURGY
- C10—PETROLEUM, GAS OR COKE INDUSTRIES; TECHNICAL GASES CONTAINING CARBON MONOXIDE; FUELS; LUBRICANTS; PEAT
- C10G—CRACKING HYDROCARBON OILS; PRODUCTION OF LIQUID HYDROCARBON MIXTURES, e.g. BY DESTRUCTIVE HYDROGENATION, OLIGOMERISATION, POLYMERISATION; RECOVERY OF HYDROCARBON OILS FROM OIL-SHALE, OIL-SAND, OR GASES; REFINING MIXTURES MAINLY CONSISTING OF HYDROCARBONS; REFORMING OF NAPHTHA; MINERAL WAXES
- C10G2300/00—Aspects relating to hydrocarbon processing covered by groups C10G1/00 - C10G99/00
- C10G2300/40—Characteristics of the process deviating from typical ways of processing
- C10G2300/4037—In-situ processes
Definitions
- the present invention relates to the bitumen and heavy oil industry. More particularly, the present invention relates to in-situ bitumen recovery operations and bitumen mining operations.
- Oil sand deposits located in many regions of the world, comprise mixtures of sand, water, clay, minerals, and crude bitumen that can be extracted and processed for fuel.
- Bitumen is classified as an “extra heavy oil”, referring to its gravity as measured in degrees on the American Petroleum Institute (API) Scale. Bitumen has an API gravity of about 10° or less. The bitumen mined from the Athabasca oil sands of Alberta has an API gravity of about 8°. “Heavy oil” has an API gravity in the range of about 22.3° to about 10°. Heavy oil or bitumen extracted from oil sand is processed or upgraded to produce light synthetic crude oil having an API gravity of about 31° to about 33°. The terms heavy oil and bitumen are used interchangeably herein since they may be extracted using the same processes.
- Bitumen comprises large hydrocarbon molecules along with other elements, such as nitrogen, oxygen, vanadium, nickel and sulfur.
- the structure of oil sand comprises water-wetted sand grains with the viscous bitumen trapped between and around the grains. Bitumen does not flow at normal ambient temperatures and pressures making it difficult and expensive to extract and process.
- Bitumen can be recovered from oil sand by various methods, the most common of which include surface or strip mining and in-situ recovery methods, including in-situ thermal recovery methods.
- the oil sand is mined, for example using trucks and shovels, and the mined ore is transported to the extraction plant for bitumen extraction.
- the mine site may be a distance from the extraction plant and, in recent years, the preferred mode of transport for mined oil sand has been by way of a slurry pipeline.
- the mined oil sand is transported to a crusher to break up chunks and rocks.
- the oil sand is then mixed with warm water to form a slurry that is capable of being pumped through a pipeline to the extraction plant. This process is referred to as hydrotransport.
- Bituminous slurry is generally pumped at temperatures of about 25° C. to 65° C. or higher, typically about 35° C.
- bitumen begins to separate from the sand, water, and other minerals in the slurry. Hydrotransport is more cost effective and efficient than previous modes of transport and it also “conditions” the slurry for bitumen separation, such that less processing is required at the plant prior to extracting the bitumen.
- the mined oil sand is dumped into large rotating tumblers where it is slurried by steam, hot water, and optionally caustic chemicals, to condition it for separation.
- the rotary action also aerates the slurry.
- the slurry is then discharged onto vibrating screens to remove rocks and lumps of clay.
- the slurry may then be blended with material from the hydrotransport process for transport to the extraction plant.
- bitumen froth flotation One of the most common extraction techniques is bitumen froth flotation.
- the conditioned slurry is introduced into a primary separation vessel (PSV) at the extraction facility.
- PSV primary separation vessel
- Warm water, air and process aides added to the slurry for conditioning aid in the formation of a bitumen-rich froth that floats or rises to form a distinct upper hydrocarbon phase that can be separated from the lower aqueous layers.
- the middlings, containing water and residual bitumen, and tailings, containing sand and particulate, are pumped off.
- the middlings and sand tailings may be further processed, for example, to extract more bitumen or recycle water.
- the waste will eventually be treated or disposed of, for example, in tailings ponds.
- the bitumen froth is next treated in a froth separation unit (FSU) to promote separation of the bitumen from other components of the froth, which include water, solvent, other agents, and residual solids.
- FSU froth separation unit
- PFT paraffinic froth treatment
- a paraffinic solvent is mixed with the froth, resulting in the formation of bitumen globules that separate from the aqueous layer and float to the top of the FSU to form a bitumen-rich upper layer that is recovered and may be further treated.
- the lower aqueous layer, containing water, solids, and residual bitumen enriched in asphaltenes may be treated in subsequent separation vessels to recover residual bitumen or asphaltenes.
- the extracted bitumen is then pumped via pipeline to an upgrader on site or to a refinery for cleaning, treatment and upgrading.
- Upgrading of bitumen or heavy oil to a light synthetic crude oil is generally accomplished via carbon rejection (i.e. coking) or hydrogen addition.
- the latter process is typically a two-stage process involving hydrocracking to break down the large hydrocarbon molecules and hydrotreating to stabilize the hydrocarbon compounds and remove impurities.
- the upgraded synthetic crude oil can be sold to refineries, petrochemical manufacturers or other consumers.
- bitumen mining operation requires expensive and elaborate processing facilities and an abundance of water, typically provided from a nearby river or lake or process affected water from a storage pond, as well as energy for heat generation. There is a need for improving efficiencies in the mining industry in general and reducing the energy, resource consumption and environmental impact associated with bitumen mining operations.
- In-situ oil recovery methods such as in-situ thermal recovery methods, are applied when the bitumen is buried deep within a reservoir and cannot be mined economically due to the depth of the overburden. In-situ production methods may recover between about 25 and 75 percent of the bitumen initially present in a reservoir. In general, the focus of an in-situ recovery process is to reduce the viscosity of the bitumen or heavy oil to enable it to flow and be produced from a well.
- Thermal in-situ recovery processes use heat to reduce the viscosity of the bitumen in a reservoir and thereby render it more flowable.
- thermal in-situ recovery processes include but are not limited to steam-assisted gravity drainage (SAGD), cyclic steam stimulation (CSS), and various derivatives thereof, such as solvent-assisted SAGD (SA-SAGD), steam and gas push (SAGP), combined vapor and steam extraction (SAVEX), expanding solvent SAGD (ES-SAGD), constant steam drainage (CSD), and liquid addition to steam for enhancing recovery (LASER), as well as water flooding and steam flooding processes.
- SAGD process is disclosed in U.S. Pat. No. 4,344,485 (Butler); an example CSS is disclosed in U.S. Pat. No.
- a lower horizontal well ideally located near the bottom of the reservoir, serves as a production well and a horizontal well located above the production well serves as an injection well. Dry or wet steam is injected into the injection well from the surface to heat the bitumen trapped in the reservoir and lower its viscosity. As the viscosity of the bitumen is lowered, it flows into the production well, along with condensed steam, and these liquids are pumped to the surface. A hydrocarbon solvent or other agent may optionally be injected to assist the process.
- the hot production fluids typically comprising about 70% produced water and about 30% bitumen and produced gases, are recovered at the surface via the production well and are separated into their individual components on site.
- Production fluids from the wellhead are cooled somewhat and sent to a flow splitter to separate the bitumen, produced water and produced gas into individual streams, which typically each undergo further treatment on site.
- the process to separate the hot production fluids into their individual components and the subsequent treatment of the separate streams is complex and is prone to operational upsets and down time.
- a diluent or condensate is added to the bitumen stream to facilitate the removal of residual water from the oil.
- the diluted bitumen (“dilbit”) may be further treated or stored on site before being transported to an upgrader or pipelined to a refinery.
- the produced water stream is de-oiled and the oil free water stream is subsequently treated to provide boiler feed water of quality for steam generation.
- the produced gas stream can also provide gas for the steam generators. This conventional set up results in numerous waste streams that must be handled appropriately and the residual waste is sent to a disposal well or sludge lagoon.
- in-situ techniques disturb considerably less land than mining operations, and therefore require less land reclamation activity
- in-situ techniques are highly capital intensive and require a significant number of vessels for processing, treatment and storage, and disposal areas, that occupy a large land footprint.
- the commercial development of smaller sized thermal operation plants e.g. ⁇ 20,000 bbl/d bitumen) may not currently be feasible due to high capital investment costs of the existing technologies.
- the present invention is directed to a novel method and system for integrating an in-situ oil recovery operation with a bitumen mining operation. By integrating the operations, many previously unrecognized efficiencies and synergies may be achieved.
- the present invention provides a method of integrating an in-situ bitumen recovery operation with a bitumen mining operation.
- the method comprises the basic steps of (a) obtaining a production fluid from the in-situ bitumen recovery operation; (b) directing the production fluid to the bitumen mining operation; and (c) incorporating the production fluid into the bitumen mining operation.
- the in-situ bitumen recovery operation may be a thermal in-situ recovery operation, such as steam-assisted gravity drainage (SAGD), cyclic steam stimulation (CSS), or any derivative thereof.
- SAGD steam-assisted gravity drainage
- CSS cyclic steam stimulation
- the hot production fluid may be incorporated into any process in the mining operation, such as an extraction, separation or treatment process.
- the hot production fluid may alternatively be cooled prior to incorporation into a mining process, e.g. via conventional heat exchange, and the captured heat may be used to heat a fluid required for the mining operation.
- the present invention provides an integrated in-situ recovery and bitumen mining system.
- the system comprises (a) a production well for recovering production fluid from an in-situ bitumen recovery operation; (b) a bitumen mining and extraction facility; and (c) means of directing the production fluid from the production well to the bitumen mining and extraction facility for incorporation into a mining operation.
- FIG. 1 is a schematic exemplifying a typical commercial facilities processing configuration for handling production fluids recovered in an in-situ thermal recovery process
- FIG. 2 is a schematic exemplifying an integrated in-situ recovery operation and mining operation, in accordance with an embodiment of the present invention, wherein hot production fluids are cooled via heat exchange prior to separation at the mining facility, and the captured heat is used to heat a water source, exemplified as river water, for use in bitumen extraction at the mine;
- a water source exemplified as river water
- FIG. 3 exemplifies a modification of the embodiment of FIG. 2 , wherein the production fluids are cooled and added directly to the Primary Separation Vessel (PSV) at the mining facility, at which point in the operation the in-situ production fluids comingle with hydrotransport effluent;
- PSV Primary Separation Vessel
- FIG. 4 exemplifies a modification of the embodiment of FIG. 2 , wherein the production fluids are cooled and added directly to the Froth Separation Unit (FSU) at the mining facility;
- FSU Froth Separation Unit
- FIG. 5 exemplifies an optional step in the embodiment of FIG. 4 , wherein gas is separated from the production fluids and the degassed fluids are added to the FSU at the mining facility;
- FIG. 6 exemplifies a modification of the embodiment of FIG. 2 , wherein the production fluids are cooled and added directly to the hydrotransport line at the mining facility.
- the present invention provides a method and system for integrating an in-situ recovery operation with a mining operation to improve energy, resource and/or operational efficiencies. More particularly, the present invention provides a method and system for integrating a production fluid from a thermal recovery operation with a bitumen mining operation for achieving one or more improved efficiencies.
- mining and extraction facilities and in-situ oil recovery and processing facilities currently exist in distinct locations and operate entirely exclusively of one another.
- the present invention provides an innovative new process configuration that integrates an in-situ processing facility with a mining facility. These may include existing, modified, retrofit or newly constructed facilities.
- mining refers to mining of oil sand and extraction of bitumen.
- mining operation and “mining facility” are meant to encompass both oil sand mining and bitumen extraction operations and facilities.
- Integration of an in-situ recovery operation with a mining facility has the potential to eliminate substantial capital requirements for the thermal in-situ plant as well as smooth out production volumes at the mine, and would allow for more economical development of smaller scale thermal production operations.
- a small scale thermal in-situ facility is integrated with a nearby existing mining facility.
- FIG. 1 An exemplary prior art commercial facilities processing configuration for processing the production fluids from an in-situ thermal recovery process is depicted in FIG. 1 .
- the present invention is not limited in any way to an in-situ bitumen recovery operation having the exemplified configuration so long as production fluids are obtained that can be integrated with a mining operation.
- the exemplified facilities configuration is described to provide an illustrative example only.
- steam 12 from steam generators 94 and optionally solvent are injected into one or more injection wells (block 10 ) and the hot production fluids 14 are recovered to the surface via one or more production wells (block 11 ) and are separated into their individual components on site.
- the production fluids typically comprise about 70% produced water and about 30% bitumen and produced gases, although the exact proportions can vary.
- the production fluids will generally have an inlet temperature in the range of about 120° C. to 220° C., typically about 200° C., and an inlet pressure of about 450 kPa to 2300 kPa, typically about 600 kPa for conventional (bitumen less dense than water) treating. These values may vary considerably however depending on the particular operation.
- the hot production fluids 14 from the wellhead are cooled and the cooled production fluids 16 sent to a flow splitter 50 or Free Water Knock Out (FWKO).
- the hot production fluids may be cooled via one or more conventional heat exchangers 17 .
- the heat captured in the one or more heat exchangers 17 may be used to heat a fluid for the operation, such as glycol.
- the flow splitter 50 separates the production fluids into two or more separate streams. In FIG. 1 , the exemplified flow splitter separates the production fluids into a bitumen stream 18 , a produced water stream 20 and a produced gas stream 22 .
- the individual streams each undergo further processing on site.
- the bitumen stream 18 which contains residual water, is sent to treaters 24 , which may contain electrostatic grids.
- Diluent 60 such as a light hydrocarbon, or condensate is added to the bitumen stream 18 to facilitate the removal of residual water from the oil.
- the diluted bitumen (“dilbit”) (stream 28 ) and gas (stream 22 a ) are separated in a gas separator 27 .
- Dilbit from the gas separator 27 (stream 26 ) may or may not be further treated before being sent to an on-site upgrader or transported by pipeline to a refinery or an off-site upgrader.
- the dilbit is generally stored on site in storage tanks (block 29 ) prior to being pipelined (stream 30 ) to market.
- Gas stream 22 b from treaters 24 is combined with gas stream 22 .
- the produced water (PW) stream 20 which contains some residual bitumen (i.e. ⁇ 5%), is subsequently deoiled (block 70 ), via resident time in a skim tank, passage through an Induced Gas Floatation (IGF) or another suitable method, such as Induced Static Floatation (ISF), and optionally by passage though oil removal filters (ORF).
- IGF Induced Gas Floatation
- ISF Induced Static Floatation
- ORF oil removal filters
- the substantially oil-free water stream 31 is then sent to one or more primary hardness removal vessels (block 80 ), such as Hot Lime Softeners (HLS), Warm Lime Softeners (WLS) or the like, for treatment.
- HLS Hot Lime Softeners
- WLS Warm Lime Softeners
- the softened water stream 32 is directed through one or more afterfilters (block 85 ), and then passed by stream 33 to one or more secondary hardness polishing vessels (block 90 ), for example, vessels for Weak Acid Cation Exchange (WAC) or Strong Acid Cation Exchange (SAC) to produce boiler feed water (BFW, block 92 ) which is passed as stream 35 of suitable quality to steam generators (block 94 ) for steam generation.
- WAC Weak Acid Cation Exchange
- SAC Strong Acid Cation Exchange
- BFW boiler feed water
- steam generators block 94
- the production fluids from an in-situ thermal recovery operation are transported from the production well to a mine site for processing.
- the typical bitumen facilities processing configuration required to separate bitumen and produced water recovered from an in-situ thermal process is thereby minimized by integrating thermal production fluids and surface facilities with a nearby mining operation.
- the production fluids 214 from one or more production wells 211 are transported, such as by pipeline, from the one or more production wells at production temperatures and pressures to a desired mine site.
- Exemplary production temperatures and pressures may be in the range of, for example, 80° C. ⁇ T ⁇ 250° C., 450 kPa ⁇ P ⁇ 3000 kPa, more typically 120° C. ⁇ T ⁇ 220° C., 450 kPa ⁇ P ⁇ 2300 kPa.
- the distance over which the production fluids are transported may range from a few kilometers to a few hundred kilometers depending on the distance between the facilities, and may require the use of pressure boosting stations. Alternatively, the two facilities may be adjacent one another if geological conditions are suitable.
- a skilled person can determine the tolerable distance and the best mode of transporting the production fluids by taking into account practical considerations, such as heat loss over the distance to be traveled.
- the production fluids 214 may subsequently be separated in to their individual components using standard separation vessels and processes for the recovery of bitumen from the oil sands mining operation. In this approach, the requirement for processing facilities at the in-situ location may be significantly reduced.
- the first step in the process involves cooling the hot production fluids from a production temperature, typically about 200° C., to a desired temperature, for example, a temperature suitable for processing at the mine.
- the processing temperature will vary depending on which process the production fluid will enter at the mine.
- the production fluid (stream 214 ) from one or more production wells 211 can be cooled via one or more heat exchangers 217 .
- the medium used to cool the thermal production fluids may be water used in the extraction process at the mine. Extraction water will typically come from a cool water source near the mine site, such as river (block 218 ) or lake water, which is typically about 5° C. to about 15° C.
- the water source may also include cooled recycled tailings water, or any other suitable water source.
- River water is exemplified in FIG. 2 to illustrate one working example.
- cool river water (stream 232 ) is heated toward a processing temperature, typically of about 35° C. to 45° C. for extraction, to provide warm extraction water 234 for recovery of bitumen from oil sand.
- the increase in temperature of the cool water via this heat exchange will depend on the production temperature and pressure of the production fluids among other factors. For example, if the production fluids (ex. 10,000 m 3 ) are 120° C./450 kPa, a 5° C. water stream (ex. 100,000 m 3 ) could reasonably be heated to about 15° C.
- Diluent 224 or condensate is added to the cooled production fluids 216 in a separation vessel 225 (FWKO) to facilitate primary separation of the bitumen from the produced water.
- the selection of diluent 224 used to aid in the separation of the SAGD production fluids is selected such that it is compatible with the solvent 230 used in the froth treatment process of the mining operation.
- compatible it is meant that the mixture of the diluent 224 and the solvent 225 will not negatively impact the extraction process or solvent recovery.
- the diluent selected is the same as the solvent.
- a mining operation that employs C 5 solvent for Paraffinic Froth Treatment may utilize C 5 solvent to facilitate the separation of bitumen and produced water in the FWKO.
- a process that employs naphtha in the froth treatment process may use naphtha in the FWKO.
- the solvent to bitumen volume ratio may be selected such that a desired density difference (between water and diluted bitumen) is achieved.
- a suitable ratio is selected such that asphaltenes do not precipitate.
- the ratio selected will depend on the bitumen composition, temperature, pressure, and solvent choice, among other factors, as will be appreciated by the skilled person. Although, in most cases the volume ratio is about 0.5 (1:2) or less, other volume ratios may be selected, for example about 0.25 (1:4) to about 2 (2:1). Higher ratios may also be selected. For example, a ratio higher than 0.5 may be selected while ensuring that the onset of asphaltene precipitation does not occur.
- the wet bitumen stream 238 may generally contain about 5% to about 30% water by volume. In one embodiment, the amount of water in the wet bitumen stream 238 is chosen such that the water content approximates the ratio of bitumen to water present in the froth separation unit (FSU) (block 240 ) feed stream 239 of the mining operation.
- FSU froth separation unit
- the produced water stream 236 recovered from the FWKO (generally represented by block 260 ) is subsequently sent to water treatment facilities and may be used to prepare boiler feed water of quality for steam generation to support the SAGD operation.
- the produced water stream 236 can be recycled to the hydrotransport (block 270 ) of the mining operation (block 261 ) to assist in the liberation of bitumen from the oil sands.
- the produced water stream 236 may be discharged to the tailings pond and stored for future use. It is recognized however that this approach is less advantageous due to wasted heat, via cooling of the stream to ambient temperature or less, and the prevention of immediate water re-use.
- the wet bitumen stream 238 is then sent to FSU 240 wherein makeup solvent 230 is added.
- the solvent may be any suitable solvent, examples of which include, but are not limited to, C 5 to C 10 and beyond, including as examples, C 5 , C 6 , C 7 , C 8 , blends of iso C 5 and normal C 5 , mixtures of C 5 and C 6 and mixtures of C 5 -C 8 solvents.
- the amount of makeup solvent added may be selected based upon the composition of the diluent used in the mining operation. The solvent and the diluent are selected such that they are compatible with one another and are preferably identical.
- the amount of makeup C 5 solvent selected is the amount needed to achieve an overall C 5 :bitumen volume ratio of about 1.8:1.
- the volume ratio may be selected so as to precipitate about 6% to 10%, or about 6% to 8%, asphaltenes from the bitumen.
- the clean de-asphalted upgraded bitumen product 250 is then recovered from the produced water/tailings water and solids stream from the mining operation 261 and can be pipelined to market or sent to an upgrader.
- the produced water/tailings water and solids stream from the FSU may subsequently be transferred to a tailings pond.
- FIG. 2 The integration of an in-situ production facility with a mining operation utilizing PFT is exemplified in FIG. 2 .
- This process allows for the generation of a dry and solids free upgraded bitumen product 250 from in-situ production that can be pipelined to market or transferred to an upgrader either on-site or off-site.
- volume ratios of solvent may be intentionally selected to encourage the precipitation of asphaltenes.
- volume ratios of solvent may be intentionally selected to encourage the precipitation of asphaltenes.
- higher volume ratios of C 5 solvent may be intentionally added to the bitumen/produced water production fluid in the FWKO vessel for precipitation of asphaltenes.
- An exemplary ratio would be about 1.8:1 C 5 solvent to bitumen.
- de-asphalting could be carried out in the FWKO vessel.
- the precipitated asphaltenes would then flow with the produced water stream, optionally with the addition of a flocculant, from the FWKO to the water treatment facilities (e.g. HLS).
- the asphaltenes In the softening vessels, the asphaltenes would coagulate with precipitated hardness solids to form a hydrocarbon-inorganic solids mixture that would be discharged to the tailings pond upon cooling, preferably utilizing heat exchange.
- the de-asphalted bitumen product formed in the FWKO vessel could then be added to the FSU, if residual precipitation is required, or directly combined with the PFT production from the mining operation and pipelined to the desired market.
- the SAGD production fluids 314 are transported to the mine site, preferably via pipeline, and are added directly to the Primary Separation Vessel (PSV) (block 340 ) at or near processing temperature, typically about 35° C.
- PSV Primary Separation Vessel
- the bitumen present in the production fluids is recovered at the mine site after combining the production fluids with the production from the mining and extraction facilities, permitting elimination of the FWKO vessels and electrostatic treaters in the thermal operation.
- FWKO vessels and/or treaters could of course be utilized with any of the embodiments, if desired or required.
- Heat recovered from the thermal production fluids can be used to heat a fluid for use at the mine to a desired temperature, such as via conventional heat exchange 317 .
- heat from the production fluids 314 may be used to heat cold extraction water, exemplified as river water 332 , to provide warm extraction water, exemplified as warmed river water 334 , for use in bitumen extraction and the cooled production fluids 316 are then added to the PSV.
- hot production fluids 314 may be added to the PSV at or near production temperature.
- the introduction of hot production fluids 314 into the PSV could provide deaeration of froth, thereby reducing the requirement for designated steam use.
- the hot production fluids 314 are transported to the mining site and added directly to the Froth Separation Unit (FSU) (block 350 ) at or near production temperature, typically about 200° C., thereby eliminating the requirement for FWKO and electrostatic treaters in the thermal operation.
- FSU Froth Separation Unit
- Diluent for example, naphtha or paraffinic solvent
- SAGD production fluids may be added upstream of the FSU, to the SAGD production fluids, or directly to the FSU, to facilitate the separation of the bitumen from the water and solids.
- Heat from the production fluids is used to warm the FSU to the desired processing temperature to enhance separation.
- Water and solids recovered from the process can be stored in tailings ponds for further use.
- the diluted bitumen may be further processed or sent to an on site upgrader or pipelined to a desired market.
- the diluent may be recycled for reuse.
- the in-situ production fluids are combined with a mining operation that utilizes a process to remove asphaltenes, such as PFT. This results in a partially deasphalted product recovered from an in-situ recovery operation.
- FIG. 4 exemplifies an embodiment wherein the hot production fluids 414 are cooled, to at or near processing temperature, typically about 45° C. to 90° C., via heat exchange 417 , before being directed to the FSU (block 450 ).
- PFT is carried out.
- the heat recovered from the hot production fluids 414 is used for the mining and extraction operation.
- the captured heat is used to heat cool river water 432 to provide warm river water 434 for use in the extraction process.
- any other suitable water source could also be used.
- a slip stream of the SAGD production fluids is added to the FSU to maintain the proper bitumen to water to solids balance and ensure effective operation of the unit.
- the production stream coming from the thermal operation can optionally be tailored to match the fluid going into the FSU from the mining operation.
- the composition of fluids at the inlet of the FSU is approximately 60% bitumen, 30% water and 10% solids, although these proportions may vary.
- Diluent i.e. paraffinic solvent
- the production fluids from the in-situ operation comprise approximately 70% water and 30% bitumen and gas.
- the SAGD production fluids 416 may be directed to a de-gas vessel (block 420 ) for gas separation, as exemplified in FIG. 5 , prior to reaching the FSU (block 450 ), such that gas free production fluids 419 are then added to the FSU (block 450 ).
- the gas stream 422 produced may be directed to the mine processing facilities.
- the production fluid may further undergo an optional dewatering step prior to reaching the FSU to adjust the water content.
- the hot production fluids 614 are transported, preferably via pipeline, to the mining and extraction site and are subsequently added to a hydrotransport line to facilitate the extraction of bitumen from the mined oil sands.
- the production fluids 614 are cooled to processing temperature, typically about 35° C., via heat exchange 617 , and the cooled production fluids 616 are added to the hydrotransport line.
- the captured heat may be used to heat cool river water 632 to provide warm river water 634 for various mining operations, such as bitumen extraction.
- the production fluids are added to the hydrotransport line (block 630 ) at or near production temperature, typically about 200° C.
- the hot production fluids 614 assist with the extraction process by providing heat to facilitate separation of the bitumen.
- the addition of hot production fluids 614 to the hydrotransport line (block 630 ) decreases the demand for water and heat for hydrotransport at the mine. SAGD produced water composition is not expected to differ in comparison to typical extraction water sources currently used and will therefore have a negligible impact on extraction efficiency.
- the production from the hydrotransport line is subsequently directed to the froth separation facilities (PSV and FSU as shown by block 640 and 650 ) and the bitumen or partially upgraded bitumen can then be recovered and sent to the desired market.
- Water and solids generated in the process may be stored in the tailings area of the mine.
- the SAGD production fluids may optionally be directed to a de-gas vessel for gas separation prior to being added to the hydrotransport line.
- the gas may then be directed to the mine processing facilities or used to generate steam to support the SAGD operation.
- the optional step of degassing the production fluids prior to integration into the mining operation could be applied to any of the described embodiments.
- the production fluids from an in-situ operation can be partially treated at an in-situ facility prior to being integrated into the mining operation.
- the production fluids are transported from the wellhead to the mining facility to be processed. This enhances the development potential of small scale in-situ bitumen recovery operations.
- the production fluids from multiple in-situ operations may be integrated with a single mining operation.
- the production fluids from a single in-situ operation may be divided and processed in multiple mining facilities, although this scenario may be less advantageous due to the requirement for multiple pipelines from the in-situ operation.
- the in-situ operation and the mining facility need not be directly adjacent one another.
- the tolerable distance between the in-situ recovery operation and the mine site will depend on various factors, such as insulation of the pipeline and weather conditions, and it is within the ability of a skilled person to judge whether the distance between facilities is suitable for integration.
- the two facilities may be separated by up to about 200 kms or less.
- the two facilities may be separated by up to about 100 kms, up to about 50 kms, or up to about 25 kms. If geological conditions are suitable, the in-situ operation and the mining operation may be at the same or adjacent locations.
- the in-situ recovery and mining facilities may be considered two distinct yet integrated facilities or, depending on the level of integration and the distance between the operations, may be considered a single integrated facility having both in-situ oil recovery and mining and extraction capabilities. Furthermore, it is understood that the mine site and extraction facility may not be directly adjacent one another.
- the production fluids from the in-situ operation can be integrated with the mining operation at any point in the operation where a benefit or synergy will be achieved.
- the benefit or synergy may relate to energy reduction, waste reduction, manpower reduction, resource conservation or reuse, reduced land footprint or reduced capital or operating costs.
- the in-situ operation is preferably a thermal in-situ bitumen recovery operation, however, it is recognized that other in-situ recovery operations, such as vapour extraction (VAPEX) operations, could also be integrated with a mining operation, so long as the production fluids are suitable for transport to and integration with the mining operation.
- a mining operation generally includes mining, extraction, processing and treatment facilities and operations. Some mining operations may also include upgrading or partial upgrading facilities.
- Integration of production fluids from an in-situ oil recovery operation with a mining operation offers many potential capital cost reductions over individual stand-alone operations. Integration of the two plants also has the potential to: permit omission of redundant equipment, share one expensive diluent pipeline to transport product to market, produce a higher quality in-situ production product, minimize land footprint required for an in-situ operation since the production fluids can be processed at the mining facility, and omit costly waste storage and sludge lagoons typically associated with thermal in-situ bitumen recovery operations. Furthermore, energy, waste, resource consumption, and even manpower may be reduced by integrating the operations. The integration of the two processes offers the potential to lower capital and operating costs due to synergies between the mining and thermal recovery operations facilities and allow for the economic development of smaller scale in-situ production operations.
Abstract
Description
- This application claims priority from Canadian Patent Application number 2,610,463 which was filed on 9 Nov. 2007, which is incorporated herein by reference.
- Generally, the present invention relates to the bitumen and heavy oil industry. More particularly, the present invention relates to in-situ bitumen recovery operations and bitumen mining operations.
- This section is intended to introduce various aspects of the art, which may be associated with exemplary embodiments of the present invention. This discussion is believed to assist in providing a framework to facilitate a better understanding of particular aspects of the present invention. Accordingly, it should be understood that this section should be read in this light, and not necessarily as admissions of prior art.
- Oil sand deposits, located in many regions of the world, comprise mixtures of sand, water, clay, minerals, and crude bitumen that can be extracted and processed for fuel. The oil sands of Alberta, Canada, contain some of the largest deposits of hydrocarbons in the world.
- Bitumen is classified as an “extra heavy oil”, referring to its gravity as measured in degrees on the American Petroleum Institute (API) Scale. Bitumen has an API gravity of about 10° or less. The bitumen mined from the Athabasca oil sands of Alberta has an API gravity of about 8°. “Heavy oil” has an API gravity in the range of about 22.3° to about 10°. Heavy oil or bitumen extracted from oil sand is processed or upgraded to produce light synthetic crude oil having an API gravity of about 31° to about 33°. The terms heavy oil and bitumen are used interchangeably herein since they may be extracted using the same processes.
- Bitumen comprises large hydrocarbon molecules along with other elements, such as nitrogen, oxygen, vanadium, nickel and sulfur. The structure of oil sand comprises water-wetted sand grains with the viscous bitumen trapped between and around the grains. Bitumen does not flow at normal ambient temperatures and pressures making it difficult and expensive to extract and process.
- Bitumen can be recovered from oil sand by various methods, the most common of which include surface or strip mining and in-situ recovery methods, including in-situ thermal recovery methods.
- In a bitumen mining operation, the oil sand is mined, for example using trucks and shovels, and the mined ore is transported to the extraction plant for bitumen extraction. The mine site may be a distance from the extraction plant and, in recent years, the preferred mode of transport for mined oil sand has been by way of a slurry pipeline. The mined oil sand is transported to a crusher to break up chunks and rocks. The oil sand is then mixed with warm water to form a slurry that is capable of being pumped through a pipeline to the extraction plant. This process is referred to as hydrotransport. Bituminous slurry is generally pumped at temperatures of about 25° C. to 65° C. or higher, typically about 35° C. to 50° C., at a sufficient flow rate to prevent the sand particulate from settling out. During hydrotransport, the bitumen begins to separate from the sand, water, and other minerals in the slurry. Hydrotransport is more cost effective and efficient than previous modes of transport and it also “conditions” the slurry for bitumen separation, such that less processing is required at the plant prior to extracting the bitumen.
- In operations where conveyors are still in use, the mined oil sand is dumped into large rotating tumblers where it is slurried by steam, hot water, and optionally caustic chemicals, to condition it for separation. The rotary action also aerates the slurry. The slurry is then discharged onto vibrating screens to remove rocks and lumps of clay. The slurry may then be blended with material from the hydrotransport process for transport to the extraction plant.
- One of the most common extraction techniques is bitumen froth flotation. The conditioned slurry is introduced into a primary separation vessel (PSV) at the extraction facility. Warm water, air and process aides added to the slurry for conditioning aid in the formation of a bitumen-rich froth that floats or rises to form a distinct upper hydrocarbon phase that can be separated from the lower aqueous layers. The middlings, containing water and residual bitumen, and tailings, containing sand and particulate, are pumped off. The middlings and sand tailings may be further processed, for example, to extract more bitumen or recycle water. The waste will eventually be treated or disposed of, for example, in tailings ponds.
- The bitumen froth is next treated in a froth separation unit (FSU) to promote separation of the bitumen from other components of the froth, which include water, solvent, other agents, and residual solids. In a paraffinic froth treatment (PFT) process, a paraffinic solvent is mixed with the froth, resulting in the formation of bitumen globules that separate from the aqueous layer and float to the top of the FSU to form a bitumen-rich upper layer that is recovered and may be further treated. The lower aqueous layer, containing water, solids, and residual bitumen enriched in asphaltenes, may be treated in subsequent separation vessels to recover residual bitumen or asphaltenes.
- The extracted bitumen is then pumped via pipeline to an upgrader on site or to a refinery for cleaning, treatment and upgrading. Upgrading of bitumen or heavy oil to a light synthetic crude oil is generally accomplished via carbon rejection (i.e. coking) or hydrogen addition. The latter process is typically a two-stage process involving hydrocracking to break down the large hydrocarbon molecules and hydrotreating to stabilize the hydrocarbon compounds and remove impurities. The upgraded synthetic crude oil can be sold to refineries, petrochemical manufacturers or other consumers.
- Currently, on average, between one and a half and two tons of oil sand are processed to produce one 159-liter barrel of synthetic crude oil. Large quantities of oil sand must be mined and processed each day in order to supply the high demand for synthetic crude oil. A significant disadvantage of the bitumen mining operation is that the operation is subject to upset and down time whenever problems occur at either the mining, recovery or processing level. Thus, production volumes can be inconsistent from day to day and there is a need to smooth out fluctuations in production.
- The bitumen mining operation requires expensive and elaborate processing facilities and an abundance of water, typically provided from a nearby river or lake or process affected water from a storage pond, as well as energy for heat generation. There is a need for improving efficiencies in the mining industry in general and reducing the energy, resource consumption and environmental impact associated with bitumen mining operations.
- In-situ oil recovery methods, such as in-situ thermal recovery methods, are applied when the bitumen is buried deep within a reservoir and cannot be mined economically due to the depth of the overburden. In-situ production methods may recover between about 25 and 75 percent of the bitumen initially present in a reservoir. In general, the focus of an in-situ recovery process is to reduce the viscosity of the bitumen or heavy oil to enable it to flow and be produced from a well.
- Thermal in-situ recovery processes use heat to reduce the viscosity of the bitumen in a reservoir and thereby render it more flowable. Examples of thermal in-situ recovery processes include but are not limited to steam-assisted gravity drainage (SAGD), cyclic steam stimulation (CSS), and various derivatives thereof, such as solvent-assisted SAGD (SA-SAGD), steam and gas push (SAGP), combined vapor and steam extraction (SAVEX), expanding solvent SAGD (ES-SAGD), constant steam drainage (CSD), and liquid addition to steam for enhancing recovery (LASER), as well as water flooding and steam flooding processes. An example SAGD process is disclosed in U.S. Pat. No. 4,344,485 (Butler); an example CSS is disclosed in U.S. Pat. No. 4,280,559 (Best); an example SA-SAGD is disclosed in U.S. Pat. No. 5,899,274; an example SAVEX process is disclosed in U.S. Pat. No. 6,662,872 (Gutek); an example ES-SAGD is disclosed in U.S. Pat. No. 6,230,814 (Nasr et al.); an example LASER process is disclosed in U.S. Pat. No. 6,708,759 (Leaute et al.).
- In typical gravity driven thermal bitumen recovery processes, two horizontal wells are drilled into the reservoir. A lower horizontal well, ideally located near the bottom of the reservoir, serves as a production well and a horizontal well located above the production well serves as an injection well. Dry or wet steam is injected into the injection well from the surface to heat the bitumen trapped in the reservoir and lower its viscosity. As the viscosity of the bitumen is lowered, it flows into the production well, along with condensed steam, and these liquids are pumped to the surface. A hydrocarbon solvent or other agent may optionally be injected to assist the process.
- The hot production fluids, typically comprising about 70% produced water and about 30% bitumen and produced gases, are recovered at the surface via the production well and are separated into their individual components on site. Production fluids from the wellhead are cooled somewhat and sent to a flow splitter to separate the bitumen, produced water and produced gas into individual streams, which typically each undergo further treatment on site. The process to separate the hot production fluids into their individual components and the subsequent treatment of the separate streams is complex and is prone to operational upsets and down time.
- A diluent or condensate is added to the bitumen stream to facilitate the removal of residual water from the oil. The diluted bitumen (“dilbit”) may be further treated or stored on site before being transported to an upgrader or pipelined to a refinery. The produced water stream is de-oiled and the oil free water stream is subsequently treated to provide boiler feed water of quality for steam generation. The produced gas stream can also provide gas for the steam generators. This conventional set up results in numerous waste streams that must be handled appropriately and the residual waste is sent to a disposal well or sludge lagoon.
- While it is recognized that in-situ techniques disturb considerably less land than mining operations, and therefore require less land reclamation activity, in-situ techniques are highly capital intensive and require a significant number of vessels for processing, treatment and storage, and disposal areas, that occupy a large land footprint. The commercial development of smaller sized thermal operation plants (e.g. <20,000 bbl/d bitumen) may not currently be feasible due to high capital investment costs of the existing technologies.
- Challenges associated with bitumen mining and in-situ bitumen recovery processes in general include intense capital investment and operating costs, large land footprint due to the equipment and land required for bitumen extraction and processing and waste management and disposal, and vulnerability to fluctuations in production and downtime. There has been a lack of success in achieving effective improvements in these areas, despite the progress made in oil sand extraction technologies and the increasing global awareness of industrial environmental impacts.
- While attempts to improve efficiency by integrating processes within an in-situ thermal bitumen recovery operation or within a mining operation have been made, advantages to be achieved by integrating production from an in-situ operation with a mining operation have not previously been identified. Combining bitumen end products from in-situ recovery and mining facilities in a single pipeline for transport to market has previously been proposed but this would provide an endpoint transportation benefit only since a complete in-situ processing facility would still be required to separate and process the recovered production fluids and manage the waste associated therewith.
- It is desirable to provide new methods and systems for reducing capital investment and operational costs associated with bitumen and heavy oil recovery, to reduce the impact of fluctuations in production associated with bitumen and heavy oil recovery operations, and to reduce the large land footprint of facilities associated therewith.
- The present invention is directed to a novel method and system for integrating an in-situ oil recovery operation with a bitumen mining operation. By integrating the operations, many previously unrecognized efficiencies and synergies may be achieved.
- In a first aspect, the present invention provides a method of integrating an in-situ bitumen recovery operation with a bitumen mining operation. The method comprises the basic steps of (a) obtaining a production fluid from the in-situ bitumen recovery operation; (b) directing the production fluid to the bitumen mining operation; and (c) incorporating the production fluid into the bitumen mining operation.
- The in-situ bitumen recovery operation may be a thermal in-situ recovery operation, such as steam-assisted gravity drainage (SAGD), cyclic steam stimulation (CSS), or any derivative thereof.
- The hot production fluid may be incorporated into any process in the mining operation, such as an extraction, separation or treatment process. The hot production fluid may alternatively be cooled prior to incorporation into a mining process, e.g. via conventional heat exchange, and the captured heat may be used to heat a fluid required for the mining operation.
- In a further aspect, the present invention provides an integrated in-situ recovery and bitumen mining system. The system comprises (a) a production well for recovering production fluid from an in-situ bitumen recovery operation; (b) a bitumen mining and extraction facility; and (c) means of directing the production fluid from the production well to the bitumen mining and extraction facility for incorporation into a mining operation.
- Other aspects and features of the present invention will become apparent to those ordinarily skilled in the art upon review of the following description of specific embodiments of the invention in conjunction with the accompanying figures.
- Embodiments of the present invention will now be described, by way of example only, with reference to the attached Figures, wherein:
-
FIG. 1 is a schematic exemplifying a typical commercial facilities processing configuration for handling production fluids recovered in an in-situ thermal recovery process; -
FIG. 2 is a schematic exemplifying an integrated in-situ recovery operation and mining operation, in accordance with an embodiment of the present invention, wherein hot production fluids are cooled via heat exchange prior to separation at the mining facility, and the captured heat is used to heat a water source, exemplified as river water, for use in bitumen extraction at the mine; -
FIG. 3 exemplifies a modification of the embodiment ofFIG. 2 , wherein the production fluids are cooled and added directly to the Primary Separation Vessel (PSV) at the mining facility, at which point in the operation the in-situ production fluids comingle with hydrotransport effluent; -
FIG. 4 exemplifies a modification of the embodiment ofFIG. 2 , wherein the production fluids are cooled and added directly to the Froth Separation Unit (FSU) at the mining facility; -
FIG. 5 exemplifies an optional step in the embodiment ofFIG. 4 , wherein gas is separated from the production fluids and the degassed fluids are added to the FSU at the mining facility; and -
FIG. 6 exemplifies a modification of the embodiment ofFIG. 2 , wherein the production fluids are cooled and added directly to the hydrotransport line at the mining facility. - In the drawings, the same reference numerals designate like or corresponding, but not necessarily identical, elements throughout the figures.
- For purposes of clarity, not every component is labeled in every figure nor is every component of each embodiment of the invention shown where illustration is not necessary to allow those of ordinary skill in the art to understand the invention.
- In the following detailed description section, the specific embodiments of the present invention are described in connection with preferred embodiments. However, to the extent that the following description is specific to a particular embodiment or a particular use of the present invention, this is intended to be for exemplary purposes only and simply provides a description of the exemplary embodiments. Accordingly, the invention is not limited to the specific embodiments described below, but rather, it includes all alternatives, modifications, and equivalents falling within the true spirit and scope of the appended claims.
- Generally, the present invention provides a method and system for integrating an in-situ recovery operation with a mining operation to improve energy, resource and/or operational efficiencies. More particularly, the present invention provides a method and system for integrating a production fluid from a thermal recovery operation with a bitumen mining operation for achieving one or more improved efficiencies.
- Mining and extraction facilities and in-situ oil recovery and processing facilities currently exist in distinct locations and operate entirely exclusively of one another. The present invention provides an innovative new process configuration that integrates an in-situ processing facility with a mining facility. These may include existing, modified, retrofit or newly constructed facilities. The term “mining”, as used herein, refers to mining of oil sand and extraction of bitumen. Thus, the expressions “mining operation” and “mining facility” are meant to encompass both oil sand mining and bitumen extraction operations and facilities.
- Integration of an in-situ recovery operation with a mining facility has the potential to eliminate substantial capital requirements for the thermal in-situ plant as well as smooth out production volumes at the mine, and would allow for more economical development of smaller scale thermal production operations. In one embodiment of the invention, a small scale thermal in-situ facility is integrated with a nearby existing mining facility.
- An exemplary prior art commercial facilities processing configuration for processing the production fluids from an in-situ thermal recovery process is depicted in
FIG. 1 . The present invention is not limited in any way to an in-situ bitumen recovery operation having the exemplified configuration so long as production fluids are obtained that can be integrated with a mining operation. The exemplified facilities configuration is described to provide an illustrative example only. - In reference to
FIG. 1 ,steam 12 fromsteam generators 94 and optionally solvent are injected into one or more injection wells (block 10) and thehot production fluids 14 are recovered to the surface via one or more production wells (block 11) and are separated into their individual components on site. The production fluids typically comprise about 70% produced water and about 30% bitumen and produced gases, although the exact proportions can vary. The production fluids will generally have an inlet temperature in the range of about 120° C. to 220° C., typically about 200° C., and an inlet pressure of about 450 kPa to 2300 kPa, typically about 600 kPa for conventional (bitumen less dense than water) treating. These values may vary considerably however depending on the particular operation. - The
hot production fluids 14 from the wellhead are cooled and the cooledproduction fluids 16 sent to aflow splitter 50 or Free Water Knock Out (FWKO). The hot production fluids may be cooled via one or moreconventional heat exchangers 17. The heat captured in the one ormore heat exchangers 17 may be used to heat a fluid for the operation, such as glycol. Theflow splitter 50 separates the production fluids into two or more separate streams. InFIG. 1 , the exemplified flow splitter separates the production fluids into abitumen stream 18, a producedwater stream 20 and a producedgas stream 22. The individual streams each undergo further processing on site. - The
bitumen stream 18, which contains residual water, is sent to treaters 24, which may contain electrostatic grids.Diluent 60, such as a light hydrocarbon, or condensate is added to thebitumen stream 18 to facilitate the removal of residual water from the oil. The diluted bitumen (“dilbit”) (stream 28) and gas (stream 22 a) are separated in agas separator 27. Dilbit from the gas separator 27 (stream 26) may or may not be further treated before being sent to an on-site upgrader or transported by pipeline to a refinery or an off-site upgrader. The dilbit is generally stored on site in storage tanks (block 29) prior to being pipelined (stream 30) to market.Gas stream 22 b fromtreaters 24 is combined withgas stream 22. - The produced water (PW)
stream 20, which contains some residual bitumen (i.e. <5%), is subsequently deoiled (block 70), via resident time in a skim tank, passage through an Induced Gas Floatation (IGF) or another suitable method, such as Induced Static Floatation (ISF), and optionally by passage though oil removal filters (ORF). The substantially oil-free water stream 31 is then sent to one or more primary hardness removal vessels (block 80), such as Hot Lime Softeners (HLS), Warm Lime Softeners (WLS) or the like, for treatment. From there, the softened water stream 32 is directed through one or more afterfilters (block 85), and then passed bystream 33 to one or more secondary hardness polishing vessels (block 90), for example, vessels for Weak Acid Cation Exchange (WAC) or Strong Acid Cation Exchange (SAC) to produce boiler feed water (BFW, block 92) which is passed asstream 35 of suitable quality to steam generators (block 94) for steam generation. The process described in thisFIG. 1 also results in numerous waste streams (energy, water, solids, etc.) that must be handled appropriately, not shown inFIG. 1 . - Although the complete facilities processing configuration may be required for a stand-alone in-situ thermal oil recovery processing operation, the integration of a thermal oil recovery operation with a nearby oil sand mining facility provides many potential improvements to the process configuration presented in
FIG. 1 , embodiments of which will be discussed in more detail below. - While the method and system of the present invention can be used to integrate any suitable in-situ bitumen recovery operation with a bitumen mining operation, integration of a thermal in-situ operation, such as SAGD, with a bitumen mining operation will be exemplified herein for illustrative purposes. While reference is made to particular exemplary facilities configurations, a skilled person will appreciate that variations, modifications and optional steps can be added or omitted without departing from the scope of the invention.
- In a first embodiment of the invention, the production fluids from an in-situ thermal recovery operation are transported from the production well to a mine site for processing. The typical bitumen facilities processing configuration required to separate bitumen and produced water recovered from an in-situ thermal process is thereby minimized by integrating thermal production fluids and surface facilities with a nearby mining operation.
- In this approach, the
production fluids 214 from one ormore production wells 211 are transported, such as by pipeline, from the one or more production wells at production temperatures and pressures to a desired mine site. Exemplary production temperatures and pressures may be in the range of, for example, 80° C.<T<250° C., 450 kPa<P<3000 kPa, more typically 120° C.<T<220° C., 450 kPa<P<2300 kPa. The distance over which the production fluids are transported may range from a few kilometers to a few hundred kilometers depending on the distance between the facilities, and may require the use of pressure boosting stations. Alternatively, the two facilities may be adjacent one another if geological conditions are suitable. A skilled person can determine the tolerable distance and the best mode of transporting the production fluids by taking into account practical considerations, such as heat loss over the distance to be traveled. - The
production fluids 214 may subsequently be separated in to their individual components using standard separation vessels and processes for the recovery of bitumen from the oil sands mining operation. In this approach, the requirement for processing facilities at the in-situ location may be significantly reduced. - In another embodiment, exemplified in
FIG. 2 , the first step in the process involves cooling the hot production fluids from a production temperature, typically about 200° C., to a desired temperature, for example, a temperature suitable for processing at the mine. The processing temperature will vary depending on which process the production fluid will enter at the mine. The production fluid (stream 214) from one ormore production wells 211 can be cooled via one ormore heat exchangers 217. The medium used to cool the thermal production fluids may be water used in the extraction process at the mine. Extraction water will typically come from a cool water source near the mine site, such as river (block 218) or lake water, which is typically about 5° C. to about 15° C. The water source may also include cooled recycled tailings water, or any other suitable water source. River water is exemplified inFIG. 2 to illustrate one working example. As exemplified inFIG. 2 , cool river water (stream 232) is heated toward a processing temperature, typically of about 35° C. to 45° C. for extraction, to providewarm extraction water 234 for recovery of bitumen from oil sand. The increase in temperature of the cool water via this heat exchange will depend on the production temperature and pressure of the production fluids among other factors. For example, if the production fluids (ex. 10,000 m3) are 120° C./450 kPa, a 5° C. water stream (ex. 100,000 m3) could reasonably be heated to about 15° C. If the production fluids (ex. 10,000 m3) are 200° C./2300 kPa, a 5° C. water stream (ex. 100,000 m3) could reasonably be heated to about 22° C. This integration configuration results in effective heat capture of the production fluids and reduces the amount of fuel/steam required to heat the cool water to the desired processing temperature. - Diluent 224 or condensate is added to the cooled
production fluids 216 in a separation vessel 225 (FWKO) to facilitate primary separation of the bitumen from the produced water. The selection of diluent 224 used to aid in the separation of the SAGD production fluids is selected such that it is compatible with the solvent 230 used in the froth treatment process of the mining operation. By compatible, it is meant that the mixture of the diluent 224 and the solvent 225 will not negatively impact the extraction process or solvent recovery. In one embodiment, the diluent selected is the same as the solvent. For example, a mining operation that employs C5 solvent for Paraffinic Froth Treatment (PFT) may utilize C5 solvent to facilitate the separation of bitumen and produced water in the FWKO. Similarly, a process that employs naphtha in the froth treatment process may use naphtha in the FWKO. - The solvent to bitumen volume ratio may be selected such that a desired density difference (between water and diluted bitumen) is achieved. A suitable ratio is selected such that asphaltenes do not precipitate. The ratio selected will depend on the bitumen composition, temperature, pressure, and solvent choice, among other factors, as will be appreciated by the skilled person. Although, in most cases the volume ratio is about 0.5 (1:2) or less, other volume ratios may be selected, for example about 0.25 (1:4) to about 2 (2:1). Higher ratios may also be selected. For example, a ratio higher than 0.5 may be selected while ensuring that the onset of asphaltene precipitation does not occur.
- Upon separation, two liquid streams are produced, namely, a de-oiled produced
water stream 236 and awet bitumen stream 238. Thewet bitumen stream 238 may generally contain about 5% to about 30% water by volume. In one embodiment, the amount of water in thewet bitumen stream 238 is chosen such that the water content approximates the ratio of bitumen to water present in the froth separation unit (FSU) (block 240)feed stream 239 of the mining operation. - The produced
water stream 236 recovered from the FWKO (generally represented by block 260) is subsequently sent to water treatment facilities and may be used to prepare boiler feed water of quality for steam generation to support the SAGD operation. Alternatively, the producedwater stream 236 can be recycled to the hydrotransport (block 270) of the mining operation (block 261) to assist in the liberation of bitumen from the oil sands. If desired, the producedwater stream 236 may be discharged to the tailings pond and stored for future use. It is recognized however that this approach is less advantageous due to wasted heat, via cooling of the stream to ambient temperature or less, and the prevention of immediate water re-use. - The
wet bitumen stream 238, comprised of diluted bitumen and produced water, is then sent toFSU 240 whereinmakeup solvent 230 is added. The solvent may be any suitable solvent, examples of which include, but are not limited to, C5 to C10 and beyond, including as examples, C5, C6, C7, C8, blends of iso C5 and normal C5, mixtures of C5 and C6 and mixtures of C5-C8 solvents. The amount of makeup solvent added may be selected based upon the composition of the diluent used in the mining operation. The solvent and the diluent are selected such that they are compatible with one another and are preferably identical. In one example, in the integration of SAGD and a Paraffinic Froth Treatment (PFT) mining operation, the amount of makeup C5 solvent selected is the amount needed to achieve an overall C5:bitumen volume ratio of about 1.8:1. The volume ratio may be selected so as to precipitate about 6% to 10%, or about 6% to 8%, asphaltenes from the bitumen. - The clean de-asphalted upgraded
bitumen product 250 is then recovered from the produced water/tailings water and solids stream from themining operation 261 and can be pipelined to market or sent to an upgrader. The produced water/tailings water and solids stream from the FSU may subsequently be transferred to a tailings pond. - The integration of an in-situ production facility with a mining operation utilizing PFT is exemplified in
FIG. 2 . This process allows for the generation of a dry and solids free upgradedbitumen product 250 from in-situ production that can be pipelined to market or transferred to an upgrader either on-site or off-site. - In the above-described embodiment, the elimination of various equipment, such as electrostatic treaters to separate bitumen from water, as well elimination of additional diluent tankage and storage, encountered in typical SAGD operations may be realized. Moreover, integration of production from the SAGD operation would smooth out the daily fluctuations in production volumes from the mining operation.
- If desired, volume ratios of solvent may be intentionally selected to encourage the precipitation of asphaltenes. In an extension of the above-described embodiment, for example, if softening of the produced
water stream 236 isolated from the FWKO vessel is required and conventional softening (e.g. HLS or WLS) is utilized, higher volume ratios of C5 solvent may be intentionally added to the bitumen/produced water production fluid in the FWKO vessel for precipitation of asphaltenes. An exemplary ratio would be about 1.8:1 C5 solvent to bitumen. In the setup, de-asphalting could be carried out in the FWKO vessel. The precipitated asphaltenes would then flow with the produced water stream, optionally with the addition of a flocculant, from the FWKO to the water treatment facilities (e.g. HLS). In the softening vessels, the asphaltenes would coagulate with precipitated hardness solids to form a hydrocarbon-inorganic solids mixture that would be discharged to the tailings pond upon cooling, preferably utilizing heat exchange. The de-asphalted bitumen product formed in the FWKO vessel could then be added to the FSU, if residual precipitation is required, or directly combined with the PFT production from the mining operation and pipelined to the desired market. - In another embodiment of an integrated thermal bitumen recovery operation and bitumen mining operation, exemplified in
FIG. 3 , using SAGD as an example, theSAGD production fluids 314 are transported to the mine site, preferably via pipeline, and are added directly to the Primary Separation Vessel (PSV) (block 340) at or near processing temperature, typically about 35° C. In this embodiment, the bitumen present in the production fluids is recovered at the mine site after combining the production fluids with the production from the mining and extraction facilities, permitting elimination of the FWKO vessels and electrostatic treaters in the thermal operation. FWKO vessels and/or treaters could of course be utilized with any of the embodiments, if desired or required. Heat recovered from the thermal production fluids can be used to heat a fluid for use at the mine to a desired temperature, such as viaconventional heat exchange 317. For example, heat from theproduction fluids 314 may be used to heat cold extraction water, exemplified asriver water 332, to provide warm extraction water, exemplified as warmedriver water 334, for use in bitumen extraction and the cooledproduction fluids 316 are then added to the PSV. - Alternatively,
hot production fluids 314 may be added to the PSV at or near production temperature. The introduction ofhot production fluids 314 into the PSV could provide deaeration of froth, thereby reducing the requirement for designated steam use. - In yet another embodiment of an integrated thermal recovery operation and bitumen mining operation, using SAGD as an example, the
hot production fluids 314 are transported to the mining site and added directly to the Froth Separation Unit (FSU) (block 350) at or near production temperature, typically about 200° C., thereby eliminating the requirement for FWKO and electrostatic treaters in the thermal operation. - Diluent, for example, naphtha or paraffinic solvent, may be added upstream of the FSU, to the SAGD production fluids, or directly to the FSU, to facilitate the separation of the bitumen from the water and solids. Heat from the production fluids is used to warm the FSU to the desired processing temperature to enhance separation. Water and solids recovered from the process can be stored in tailings ponds for further use. The diluted bitumen may be further processed or sent to an on site upgrader or pipelined to a desired market. The diluent may be recycled for reuse.
- In one embodiment, the in-situ production fluids are combined with a mining operation that utilizes a process to remove asphaltenes, such as PFT. This results in a partially deasphalted product recovered from an in-situ recovery operation.
-
FIG. 4 exemplifies an embodiment wherein thehot production fluids 414 are cooled, to at or near processing temperature, typically about 45° C. to 90° C., viaheat exchange 417, before being directed to the FSU (block 450). In the embodiment shown, PFT is carried out. The heat recovered from thehot production fluids 414 is used for the mining and extraction operation. In the exemplified embodiment, the captured heat is used to heatcool river water 432 to providewarm river water 434 for use in the extraction process. Of course, any other suitable water source could also be used. - In a modification of this embodiment, a slip stream of the SAGD production fluids is added to the FSU to maintain the proper bitumen to water to solids balance and ensure effective operation of the unit.
- The production stream coming from the thermal operation can optionally be tailored to match the fluid going into the FSU from the mining operation. For a PFT process, the composition of fluids at the inlet of the FSU is approximately 60% bitumen, 30% water and 10% solids, although these proportions may vary. Diluent (i.e. paraffinic solvent) is then added to this composition to facilitate the partial removal of asphaltenes and solids. The production fluids from the in-situ operation comprise approximately 70% water and 30% bitumen and gas.
- In an optional step, the
SAGD production fluids 416 may be directed to a de-gas vessel (block 420) for gas separation, as exemplified inFIG. 5 , prior to reaching the FSU (block 450), such that gasfree production fluids 419 are then added to the FSU (block 450). The gas stream 422 produced may be directed to the mine processing facilities. The production fluid may further undergo an optional dewatering step prior to reaching the FSU to adjust the water content. - In a further embodiment of an integrated thermal recovery operation and bitumen mining operation, exemplified in
FIG. 6 , using SAGD as an example, thehot production fluids 614 are transported, preferably via pipeline, to the mining and extraction site and are subsequently added to a hydrotransport line to facilitate the extraction of bitumen from the mined oil sands. In the embodiment shown, theproduction fluids 614 are cooled to processing temperature, typically about 35° C., viaheat exchange 617, and the cooledproduction fluids 616 are added to the hydrotransport line. The captured heat may be used to heatcool river water 632 to providewarm river water 634 for various mining operations, such as bitumen extraction. - In an alternate embodiment, the production fluids are added to the hydrotransport line (block 630) at or near production temperature, typically about 200° C. The
hot production fluids 614 assist with the extraction process by providing heat to facilitate separation of the bitumen. The addition ofhot production fluids 614 to the hydrotransport line (block 630) decreases the demand for water and heat for hydrotransport at the mine. SAGD produced water composition is not expected to differ in comparison to typical extraction water sources currently used and will therefore have a negligible impact on extraction efficiency. - The production from the hydrotransport line is subsequently directed to the froth separation facilities (PSV and FSU as shown by
block 640 and 650) and the bitumen or partially upgraded bitumen can then be recovered and sent to the desired market. Water and solids generated in the process may be stored in the tailings area of the mine. - The SAGD production fluids may optionally be directed to a de-gas vessel for gas separation prior to being added to the hydrotransport line. The gas may then be directed to the mine processing facilities or used to generate steam to support the SAGD operation. The optional step of degassing the production fluids prior to integration into the mining operation could be applied to any of the described embodiments.
- The addition of production fluids to a hydrotransport line at the mine eliminates the requirement for the FWKO vessels and associated electrostatic treaters and water treatment facilities, and thereby minimizes the land footprint and operating costs of the thermal facility. The requirement for disposal areas and other processing equipment may also be eliminated at the thermal facility depending on the level of integration of the production fluids into the mining operation.
- The production fluids from an in-situ operation can be partially treated at an in-situ facility prior to being integrated into the mining operation. However, for optimal synergy, the production fluids are transported from the wellhead to the mining facility to be processed. This enhances the development potential of small scale in-situ bitumen recovery operations.
- The production fluids from multiple in-situ operations may be integrated with a single mining operation. Alternatively, the production fluids from a single in-situ operation may be divided and processed in multiple mining facilities, although this scenario may be less advantageous due to the requirement for multiple pipelines from the in-situ operation.
- The in-situ operation and the mining facility need not be directly adjacent one another. The tolerable distance between the in-situ recovery operation and the mine site will depend on various factors, such as insulation of the pipeline and weather conditions, and it is within the ability of a skilled person to judge whether the distance between facilities is suitable for integration. Generally speaking, the two facilities may be separated by up to about 200 kms or less. For instance the two facilities may be separated by up to about 100 kms, up to about 50 kms, or up to about 25 kms. If geological conditions are suitable, the in-situ operation and the mining operation may be at the same or adjacent locations.
- The in-situ recovery and mining facilities may be considered two distinct yet integrated facilities or, depending on the level of integration and the distance between the operations, may be considered a single integrated facility having both in-situ oil recovery and mining and extraction capabilities. Furthermore, it is understood that the mine site and extraction facility may not be directly adjacent one another.
- The production fluids from the in-situ operation can be integrated with the mining operation at any point in the operation where a benefit or synergy will be achieved. The benefit or synergy may relate to energy reduction, waste reduction, manpower reduction, resource conservation or reuse, reduced land footprint or reduced capital or operating costs.
- The in-situ operation is preferably a thermal in-situ bitumen recovery operation, however, it is recognized that other in-situ recovery operations, such as vapour extraction (VAPEX) operations, could also be integrated with a mining operation, so long as the production fluids are suitable for transport to and integration with the mining operation. A mining operation generally includes mining, extraction, processing and treatment facilities and operations. Some mining operations may also include upgrading or partial upgrading facilities.
- Integration of production fluids from an in-situ oil recovery operation with a mining operation offers many potential capital cost reductions over individual stand-alone operations. Integration of the two plants also has the potential to: permit omission of redundant equipment, share one expensive diluent pipeline to transport product to market, produce a higher quality in-situ production product, minimize land footprint required for an in-situ operation since the production fluids can be processed at the mining facility, and omit costly waste storage and sludge lagoons typically associated with thermal in-situ bitumen recovery operations. Furthermore, energy, waste, resource consumption, and even manpower may be reduced by integrating the operations. The integration of the two processes offers the potential to lower capital and operating costs due to synergies between the mining and thermal recovery operations facilities and allow for the economic development of smaller scale in-situ production operations.
- In the preceding description, for purposes of explanation, numerous details are set forth in order to provide a thorough understanding of the embodiments of the invention. However, it will be apparent to one skilled in the art that these specific details are not required in order to practice the invention. For instance, temperature and pressure ranges are provided for exemplary purposes and not to limit the scope of the invention.
- While the present invention may be susceptible to various modifications and alternative forms, the exemplary embodiments discussed above have been shown only by way of example. However, it should again be understood that the invention is not intended to be limited to the particular embodiments disclosed herein. Indeed, the present invention includes all alternatives, modifications, and equivalents falling within the true spirit and scope of the appended claims.
Claims (52)
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CA2610463 | 2007-11-09 | ||
CA2610463A CA2610463C (en) | 2007-11-09 | 2007-11-09 | Integration of an in-situ recovery operation with a mining operation |
PCT/US2008/075929 WO2009061552A1 (en) | 2007-11-09 | 2008-09-11 | Integration of an in-situ recovery operation with a mining operation |
Publications (1)
Publication Number | Publication Date |
---|---|
US20100276983A1 true US20100276983A1 (en) | 2010-11-04 |
Family
ID=40620881
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US12/679,455 Abandoned US20100276983A1 (en) | 2007-11-09 | 2008-09-11 | Integration of an in-situ recovery operation with a mining operation |
Country Status (3)
Country | Link |
---|---|
US (1) | US20100276983A1 (en) |
CA (1) | CA2610463C (en) |
WO (1) | WO2009061552A1 (en) |
Cited By (26)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2013025260A1 (en) * | 2011-06-01 | 2013-02-21 | Exxonmobil Upstream Research Company | Method of processing a bitumen stream using a membrane |
US20130068458A1 (en) * | 2011-03-04 | 2013-03-21 | Conocophillips Company | Heat recovery method for wellpad sagd steam generation |
WO2013180909A1 (en) * | 2012-05-29 | 2013-12-05 | Exxonmobil Upstream Research Company | Systems and methods for hydrotreating a shale oil stream using hydrogen gas that is concentrated from the shale oil stream |
US8770284B2 (en) | 2012-05-04 | 2014-07-08 | Exxonmobil Upstream Research Company | Systems and methods of detecting an intersection between a wellbore and a subterranean structure that includes a marker material |
US20140238905A1 (en) * | 2011-11-08 | 2014-08-28 | James A. Dunn | Processing a hydrocarbon stream using supercritical water |
US8863839B2 (en) | 2009-12-17 | 2014-10-21 | Exxonmobil Upstream Research Company | Enhanced convection for in situ pyrolysis of organic-rich rock formations |
US8875789B2 (en) | 2007-05-25 | 2014-11-04 | Exxonmobil Upstream Research Company | Process for producing hydrocarbon fluids combining in situ heating, a power plant and a gas plant |
US20150159092A1 (en) * | 2012-07-06 | 2015-06-11 | Statoil Canada Limited | Method and a system of recovering and processing a hydrocarbon mixture from a subterranean formation |
US9080441B2 (en) | 2011-11-04 | 2015-07-14 | Exxonmobil Upstream Research Company | Multiple electrical connections to optimize heating for in situ pyrolysis |
US9207019B2 (en) | 2011-04-15 | 2015-12-08 | Fort Hills Energy L.P. | Heat recovery for bitumen froth treatment plant integration with sealed closed-loop cooling circuit |
US9347302B2 (en) | 2007-03-22 | 2016-05-24 | Exxonmobil Upstream Research Company | Resistive heater for in situ formation heating |
US9394772B2 (en) | 2013-11-07 | 2016-07-19 | Exxonmobil Upstream Research Company | Systems and methods for in situ resistive heating of organic matter in a subterranean formation |
US9512699B2 (en) | 2013-10-22 | 2016-12-06 | Exxonmobil Upstream Research Company | Systems and methods for regulating an in situ pyrolysis process |
US9546323B2 (en) | 2011-01-27 | 2017-01-17 | Fort Hills Energy L.P. | Process for integration of paraffinic froth treatment hub and a bitumen ore mining and extraction facility |
US9587177B2 (en) | 2011-05-04 | 2017-03-07 | Fort Hills Energy L.P. | Enhanced turndown process for a bitumen froth treatment operation |
US9587176B2 (en) | 2011-02-25 | 2017-03-07 | Fort Hills Energy L.P. | Process for treating high paraffin diluted bitumen |
US9644466B2 (en) | 2014-11-21 | 2017-05-09 | Exxonmobil Upstream Research Company | Method of recovering hydrocarbons within a subsurface formation using electric current |
US9676684B2 (en) | 2011-03-01 | 2017-06-13 | Fort Hills Energy L.P. | Process and unit for solvent recovery from solvent diluted tailings derived from bitumen froth treatment |
US9791170B2 (en) | 2011-03-22 | 2017-10-17 | Fort Hills Energy L.P. | Process for direct steam injection heating of oil sands slurry streams such as bitumen froth |
US10041005B2 (en) | 2011-03-04 | 2018-08-07 | Fort Hills Energy L.P. | Process and system for solvent addition to bitumen froth |
US10226717B2 (en) | 2011-04-28 | 2019-03-12 | Fort Hills Energy L.P. | Method of recovering solvent from tailings by flashing under choked flow conditions |
US10487636B2 (en) | 2017-07-27 | 2019-11-26 | Exxonmobil Upstream Research Company | Enhanced methods for recovering viscous hydrocarbons from a subterranean formation as a follow-up to thermal recovery processes |
US11002123B2 (en) | 2017-08-31 | 2021-05-11 | Exxonmobil Upstream Research Company | Thermal recovery methods for recovering viscous hydrocarbons from a subterranean formation |
US11142681B2 (en) | 2017-06-29 | 2021-10-12 | Exxonmobil Upstream Research Company | Chasing solvent for enhanced recovery processes |
US11261383B2 (en) | 2011-05-18 | 2022-03-01 | Fort Hills Energy L.P. | Enhanced temperature control of bitumen froth treatment process |
US11261725B2 (en) | 2017-10-24 | 2022-03-01 | Exxonmobil Upstream Research Company | Systems and methods for estimating and controlling liquid level using periodic shut-ins |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105921262B (en) * | 2016-05-09 | 2018-09-11 | 天津大学 | A kind of continuous separation method in parallel and system rich in carbonate heavy oil field |
CN105885909B (en) * | 2016-05-09 | 2018-05-15 | 天津海威欧能源科技有限责任公司 | The continuous system and method separated and convert rich in carbonate heavy oil field |
Citations (54)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3684699A (en) * | 1971-02-10 | 1972-08-15 | Univ California | Process for recovering oil from tar-oil froths and other heavy oil-water emulsions |
US3898058A (en) * | 1973-04-12 | 1975-08-05 | H T Management Company | Vacuum stripping of hydrocarbon contaminated water streams |
US4116275A (en) * | 1977-03-14 | 1978-09-26 | Exxon Production Research Company | Recovery of hydrocarbons by in situ thermal extraction |
US4234232A (en) * | 1978-10-04 | 1980-11-18 | Standard Oil Company | Methods of and apparatus for mining and processing tar sands and the like |
US4240897A (en) * | 1975-06-06 | 1980-12-23 | Clarke Thomas P | Oil sands hot water extraction process |
US4280559A (en) * | 1979-10-29 | 1981-07-28 | Exxon Production Research Company | Method for producing heavy crude |
US4343691A (en) * | 1979-11-09 | 1982-08-10 | The Lummus Company | Heat and water recovery from aqueous waste streams |
US4344485A (en) * | 1979-07-10 | 1982-08-17 | Exxon Production Research Company | Method for continuously producing viscous hydrocarbons by gravity drainage while injecting heated fluids |
US4430861A (en) * | 1982-06-03 | 1984-02-14 | The Johns Hopkins University | Open cycle OTEC plant |
US4499949A (en) * | 1983-06-09 | 1985-02-19 | Mobil Oil Corporation | Combined surface and in situ tar sand bitumen production |
US4529497A (en) * | 1984-03-26 | 1985-07-16 | Standard Oil Company (Indiana) | Disposal of spent oil shale and other materials |
US4561965A (en) * | 1979-11-09 | 1985-12-31 | Lummus Crest Inc. | Heat and water recovery from aqueous waste streams |
US4608126A (en) * | 1984-03-26 | 1986-08-26 | Amoco Corporation | Retorting system and disposal site |
US4676889A (en) * | 1984-02-27 | 1987-06-30 | Chevron Research Company | Solvent extraction process for recovering bitumen from tar sand |
US5236577A (en) * | 1990-07-13 | 1993-08-17 | Oslo Alberta Limited | Process for separation of hydrocarbon from tar sands froth |
US5262013A (en) * | 1991-07-17 | 1993-11-16 | Amalgamated Technologies, Inc. | Coolant recycling method and apparatus |
US5415673A (en) * | 1993-10-15 | 1995-05-16 | Texaco Inc. | Energy efficient filtration of syngas cooling and scrubbing water |
US5555838A (en) * | 1994-10-31 | 1996-09-17 | Seatek International, Inc. | Ocean thermal energy conversion platform |
US5582691A (en) * | 1993-12-14 | 1996-12-10 | Flynn; Robert J. | Ocean thermal energy conversion (OTEC) system |
US5876592A (en) * | 1995-05-18 | 1999-03-02 | Alberta Energy Co., Ltd. | Solvent process for bitumen separation from oil sands froth |
US5899274A (en) * | 1996-09-18 | 1999-05-04 | Alberta Oil Sands Technology And Research Authority | Solvent-assisted method for mobilizing viscous heavy oil |
US5925291A (en) * | 1997-03-25 | 1999-07-20 | Midwest Research Institute | Method and apparatus for high-efficiency direct contact condensation |
US5968349A (en) * | 1998-11-16 | 1999-10-19 | Bhp Minerals International Inc. | Extraction of bitumen from bitumen froth and biotreatment of bitumen froth tailings generated from tar sands |
US5986148A (en) * | 1993-08-02 | 1999-11-16 | Mobil Oil Corporation | Di-isopropyl ether synthesis and dry product recovery |
US6007709A (en) * | 1997-12-31 | 1999-12-28 | Bhp Minerals International Inc. | Extraction of bitumen from bitumen froth generated from tar sands |
US6036748A (en) * | 1997-06-06 | 2000-03-14 | Texaco Inc. | Black water flash and vapor recovery method |
US6042718A (en) * | 1996-11-29 | 2000-03-28 | Universal Industries Corp. | Process for removing water from a water-containing crude oil |
US6074558A (en) * | 1998-11-16 | 2000-06-13 | Bhp Minerals International Inc. | Biochemical treatment of bitumen froth tailings |
US6214213B1 (en) * | 1995-05-18 | 2001-04-10 | Aec Oil Sands, L.P. | Solvent process for bitumen seperation from oil sands froth |
US6230814B1 (en) * | 1999-10-14 | 2001-05-15 | Alberta Oil Sands Technology And Research Authority | Process for enhancing hydrocarbon mobility using a steam additive |
US20020006969A1 (en) * | 2000-05-30 | 2002-01-17 | O'beck John Timothy | System and method for converting light hydrocarbons into heavier hydrocarbons and for treating contaminated water |
US6358403B1 (en) * | 1999-05-14 | 2002-03-19 | Aec Oil Sands, L.P. | Process for recovery of hydrocarbon from tailings |
US6357526B1 (en) * | 2000-03-16 | 2002-03-19 | Kellogg Brown & Root, Inc. | Field upgrading of heavy oil and bitumen |
US6358404B1 (en) * | 1999-05-13 | 2002-03-19 | Aec Oil Sands, L.P. | Method for recovery of hydrocarbon diluent from tailing |
US20030127400A1 (en) * | 1997-01-14 | 2003-07-10 | Steve Kresnyak | Water treatment process for thermal heavy oil recovery |
US6662872B2 (en) * | 2000-11-10 | 2003-12-16 | Exxonmobil Upstream Research Company | Combined steam and vapor extraction process (SAVEX) for in situ bitumen and heavy oil production |
US6708759B2 (en) * | 2001-04-04 | 2004-03-23 | Exxonmobil Upstream Research Company | Liquid addition to steam for enhancing recovery of cyclic steam stimulation or LASER-CSS |
US6712215B2 (en) * | 2000-07-28 | 2004-03-30 | Adolf Frederik Scheybeler | Method and apparatus for recovery of lost diluent in oil sands extraction tailings |
US6769486B2 (en) * | 2001-05-31 | 2004-08-03 | Exxonmobil Upstream Research Company | Cyclic solvent process for in-situ bitumen and heavy oil production |
US6800116B2 (en) * | 2002-05-23 | 2004-10-05 | Suncor Energy Inc. | Static deaeration conditioner for processing of bitumen froth |
US20050150844A1 (en) * | 2004-01-08 | 2005-07-14 | Truenorth Energy Corp. | Process and apparatus for treating tailings |
US20050252833A1 (en) * | 2004-05-14 | 2005-11-17 | Doyle James A | Process and apparatus for converting oil shale or oil sand (tar sand) to oil |
US6988549B1 (en) * | 2003-11-14 | 2006-01-24 | John A Babcock | SAGD-plus |
US20060048920A1 (en) * | 2003-02-25 | 2006-03-09 | Donald Helleur | Energy reclaiming process |
US20060113218A1 (en) * | 2004-11-29 | 2006-06-01 | Baker Hughes Incorporated | Process for extracting bitumen |
US7067811B2 (en) * | 2002-11-06 | 2006-06-27 | Her Majesty The Queen In Right Of Canada, As Represented By The Minister Of Natural Resources Canada | NIR spectroscopy method for analyzing chemical process components |
US20060138055A1 (en) * | 2002-09-19 | 2006-06-29 | Garner William N | Bituminous froth hydrocarbon cyclone |
US20060196812A1 (en) * | 2005-03-02 | 2006-09-07 | Beetge Jan H | Zone settling aid and method for producing dry diluted bitumen with reduced losses of asphaltenes |
US20060260980A1 (en) * | 2005-05-20 | 2006-11-23 | Value Creation Inc. | Decontamination of asphaltic heavy oil and bitumen |
US20070111903A1 (en) * | 2005-11-17 | 2007-05-17 | General Electric Company | Separatory and emulsion breaking processes |
US20070131427A1 (en) * | 2005-10-24 | 2007-06-14 | Ruijian Li | Systems and methods for producing hydrocarbons from tar sands formations |
US7261810B2 (en) * | 2002-11-12 | 2007-08-28 | Sinvent As | Method and system for transporting flows of fluid hydrocarbons containing wax, asphaltenes, and/or other precipitating solids |
US7282136B2 (en) * | 2004-05-26 | 2007-10-16 | Nalco Company | Method of dispersing hydrocarbon foulants in hydrocarbon processing fluids |
US7556715B2 (en) * | 2004-01-09 | 2009-07-07 | Suncor Energy, Inc. | Bituminous froth inline steam injection processing |
-
2007
- 2007-11-09 CA CA2610463A patent/CA2610463C/en active Active
-
2008
- 2008-09-11 US US12/679,455 patent/US20100276983A1/en not_active Abandoned
- 2008-09-11 WO PCT/US2008/075929 patent/WO2009061552A1/en active Application Filing
Patent Citations (57)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3684699A (en) * | 1971-02-10 | 1972-08-15 | Univ California | Process for recovering oil from tar-oil froths and other heavy oil-water emulsions |
US3898058A (en) * | 1973-04-12 | 1975-08-05 | H T Management Company | Vacuum stripping of hydrocarbon contaminated water streams |
US4240897A (en) * | 1975-06-06 | 1980-12-23 | Clarke Thomas P | Oil sands hot water extraction process |
US4116275A (en) * | 1977-03-14 | 1978-09-26 | Exxon Production Research Company | Recovery of hydrocarbons by in situ thermal extraction |
US4234232A (en) * | 1978-10-04 | 1980-11-18 | Standard Oil Company | Methods of and apparatus for mining and processing tar sands and the like |
US4344485A (en) * | 1979-07-10 | 1982-08-17 | Exxon Production Research Company | Method for continuously producing viscous hydrocarbons by gravity drainage while injecting heated fluids |
US4280559A (en) * | 1979-10-29 | 1981-07-28 | Exxon Production Research Company | Method for producing heavy crude |
US4343691A (en) * | 1979-11-09 | 1982-08-10 | The Lummus Company | Heat and water recovery from aqueous waste streams |
US4561965A (en) * | 1979-11-09 | 1985-12-31 | Lummus Crest Inc. | Heat and water recovery from aqueous waste streams |
US4430861A (en) * | 1982-06-03 | 1984-02-14 | The Johns Hopkins University | Open cycle OTEC plant |
US4499949A (en) * | 1983-06-09 | 1985-02-19 | Mobil Oil Corporation | Combined surface and in situ tar sand bitumen production |
US4676889A (en) * | 1984-02-27 | 1987-06-30 | Chevron Research Company | Solvent extraction process for recovering bitumen from tar sand |
US4529497A (en) * | 1984-03-26 | 1985-07-16 | Standard Oil Company (Indiana) | Disposal of spent oil shale and other materials |
US4608126A (en) * | 1984-03-26 | 1986-08-26 | Amoco Corporation | Retorting system and disposal site |
US5236577A (en) * | 1990-07-13 | 1993-08-17 | Oslo Alberta Limited | Process for separation of hydrocarbon from tar sands froth |
US5262013A (en) * | 1991-07-17 | 1993-11-16 | Amalgamated Technologies, Inc. | Coolant recycling method and apparatus |
US5986148A (en) * | 1993-08-02 | 1999-11-16 | Mobil Oil Corporation | Di-isopropyl ether synthesis and dry product recovery |
US5415673A (en) * | 1993-10-15 | 1995-05-16 | Texaco Inc. | Energy efficient filtration of syngas cooling and scrubbing water |
US5582691A (en) * | 1993-12-14 | 1996-12-10 | Flynn; Robert J. | Ocean thermal energy conversion (OTEC) system |
US5555838A (en) * | 1994-10-31 | 1996-09-17 | Seatek International, Inc. | Ocean thermal energy conversion platform |
US5876592A (en) * | 1995-05-18 | 1999-03-02 | Alberta Energy Co., Ltd. | Solvent process for bitumen separation from oil sands froth |
US6214213B1 (en) * | 1995-05-18 | 2001-04-10 | Aec Oil Sands, L.P. | Solvent process for bitumen seperation from oil sands froth |
US5899274A (en) * | 1996-09-18 | 1999-05-04 | Alberta Oil Sands Technology And Research Authority | Solvent-assisted method for mobilizing viscous heavy oil |
US6042718A (en) * | 1996-11-29 | 2000-03-28 | Universal Industries Corp. | Process for removing water from a water-containing crude oil |
US6984292B2 (en) * | 1997-01-14 | 2006-01-10 | Encana Corporation | Water treatment process for thermal heavy oil recovery |
US20030127400A1 (en) * | 1997-01-14 | 2003-07-10 | Steve Kresnyak | Water treatment process for thermal heavy oil recovery |
US5925291A (en) * | 1997-03-25 | 1999-07-20 | Midwest Research Institute | Method and apparatus for high-efficiency direct contact condensation |
US6036748A (en) * | 1997-06-06 | 2000-03-14 | Texaco Inc. | Black water flash and vapor recovery method |
US6007709A (en) * | 1997-12-31 | 1999-12-28 | Bhp Minerals International Inc. | Extraction of bitumen from bitumen froth generated from tar sands |
US6074558A (en) * | 1998-11-16 | 2000-06-13 | Bhp Minerals International Inc. | Biochemical treatment of bitumen froth tailings |
US5968349A (en) * | 1998-11-16 | 1999-10-19 | Bhp Minerals International Inc. | Extraction of bitumen from bitumen froth and biotreatment of bitumen froth tailings generated from tar sands |
US6358404B1 (en) * | 1999-05-13 | 2002-03-19 | Aec Oil Sands, L.P. | Method for recovery of hydrocarbon diluent from tailing |
US6358403B1 (en) * | 1999-05-14 | 2002-03-19 | Aec Oil Sands, L.P. | Process for recovery of hydrocarbon from tailings |
US6230814B1 (en) * | 1999-10-14 | 2001-05-15 | Alberta Oil Sands Technology And Research Authority | Process for enhancing hydrocarbon mobility using a steam additive |
US6357526B1 (en) * | 2000-03-16 | 2002-03-19 | Kellogg Brown & Root, Inc. | Field upgrading of heavy oil and bitumen |
US20020006969A1 (en) * | 2000-05-30 | 2002-01-17 | O'beck John Timothy | System and method for converting light hydrocarbons into heavier hydrocarbons and for treating contaminated water |
US6712215B2 (en) * | 2000-07-28 | 2004-03-30 | Adolf Frederik Scheybeler | Method and apparatus for recovery of lost diluent in oil sands extraction tailings |
US6662872B2 (en) * | 2000-11-10 | 2003-12-16 | Exxonmobil Upstream Research Company | Combined steam and vapor extraction process (SAVEX) for in situ bitumen and heavy oil production |
US6708759B2 (en) * | 2001-04-04 | 2004-03-23 | Exxonmobil Upstream Research Company | Liquid addition to steam for enhancing recovery of cyclic steam stimulation or LASER-CSS |
US6769486B2 (en) * | 2001-05-31 | 2004-08-03 | Exxonmobil Upstream Research Company | Cyclic solvent process for in-situ bitumen and heavy oil production |
US6800116B2 (en) * | 2002-05-23 | 2004-10-05 | Suncor Energy Inc. | Static deaeration conditioner for processing of bitumen froth |
US7141162B2 (en) * | 2002-09-19 | 2006-11-28 | Suncor Energy, Inc. | Bituminous froth inclined plate separator and hydrocarbon cyclone treatment process |
US20060138055A1 (en) * | 2002-09-19 | 2006-06-29 | Garner William N | Bituminous froth hydrocarbon cyclone |
US7067811B2 (en) * | 2002-11-06 | 2006-06-27 | Her Majesty The Queen In Right Of Canada, As Represented By The Minister Of Natural Resources Canada | NIR spectroscopy method for analyzing chemical process components |
US7261810B2 (en) * | 2002-11-12 | 2007-08-28 | Sinvent As | Method and system for transporting flows of fluid hydrocarbons containing wax, asphaltenes, and/or other precipitating solids |
US20060048920A1 (en) * | 2003-02-25 | 2006-03-09 | Donald Helleur | Energy reclaiming process |
US6988549B1 (en) * | 2003-11-14 | 2006-01-24 | John A Babcock | SAGD-plus |
US20050150844A1 (en) * | 2004-01-08 | 2005-07-14 | Truenorth Energy Corp. | Process and apparatus for treating tailings |
US7556715B2 (en) * | 2004-01-09 | 2009-07-07 | Suncor Energy, Inc. | Bituminous froth inline steam injection processing |
US20050252833A1 (en) * | 2004-05-14 | 2005-11-17 | Doyle James A | Process and apparatus for converting oil shale or oil sand (tar sand) to oil |
US7282136B2 (en) * | 2004-05-26 | 2007-10-16 | Nalco Company | Method of dispersing hydrocarbon foulants in hydrocarbon processing fluids |
US20060113218A1 (en) * | 2004-11-29 | 2006-06-01 | Baker Hughes Incorporated | Process for extracting bitumen |
US20060196812A1 (en) * | 2005-03-02 | 2006-09-07 | Beetge Jan H | Zone settling aid and method for producing dry diluted bitumen with reduced losses of asphaltenes |
US20060260980A1 (en) * | 2005-05-20 | 2006-11-23 | Value Creation Inc. | Decontamination of asphaltic heavy oil and bitumen |
US20070131427A1 (en) * | 2005-10-24 | 2007-06-14 | Ruijian Li | Systems and methods for producing hydrocarbons from tar sands formations |
US7562706B2 (en) * | 2005-10-24 | 2009-07-21 | Shell Oil Company | Systems and methods for producing hydrocarbons from tar sands formations |
US20070111903A1 (en) * | 2005-11-17 | 2007-05-17 | General Electric Company | Separatory and emulsion breaking processes |
Cited By (31)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9347302B2 (en) | 2007-03-22 | 2016-05-24 | Exxonmobil Upstream Research Company | Resistive heater for in situ formation heating |
US8875789B2 (en) | 2007-05-25 | 2014-11-04 | Exxonmobil Upstream Research Company | Process for producing hydrocarbon fluids combining in situ heating, a power plant and a gas plant |
US8863839B2 (en) | 2009-12-17 | 2014-10-21 | Exxonmobil Upstream Research Company | Enhanced convection for in situ pyrolysis of organic-rich rock formations |
US9546323B2 (en) | 2011-01-27 | 2017-01-17 | Fort Hills Energy L.P. | Process for integration of paraffinic froth treatment hub and a bitumen ore mining and extraction facility |
US9587176B2 (en) | 2011-02-25 | 2017-03-07 | Fort Hills Energy L.P. | Process for treating high paraffin diluted bitumen |
US9676684B2 (en) | 2011-03-01 | 2017-06-13 | Fort Hills Energy L.P. | Process and unit for solvent recovery from solvent diluted tailings derived from bitumen froth treatment |
US20130068458A1 (en) * | 2011-03-04 | 2013-03-21 | Conocophillips Company | Heat recovery method for wellpad sagd steam generation |
US10988695B2 (en) | 2011-03-04 | 2021-04-27 | Fort Hills Energy L.P. | Process and system for solvent addition to bitumen froth |
US10041005B2 (en) | 2011-03-04 | 2018-08-07 | Fort Hills Energy L.P. | Process and system for solvent addition to bitumen froth |
US8973658B2 (en) * | 2011-03-04 | 2015-03-10 | Conocophillips Company | Heat recovery method for wellpad SAGD steam generation |
US9791170B2 (en) | 2011-03-22 | 2017-10-17 | Fort Hills Energy L.P. | Process for direct steam injection heating of oil sands slurry streams such as bitumen froth |
US9207019B2 (en) | 2011-04-15 | 2015-12-08 | Fort Hills Energy L.P. | Heat recovery for bitumen froth treatment plant integration with sealed closed-loop cooling circuit |
US10226717B2 (en) | 2011-04-28 | 2019-03-12 | Fort Hills Energy L.P. | Method of recovering solvent from tailings by flashing under choked flow conditions |
US9587177B2 (en) | 2011-05-04 | 2017-03-07 | Fort Hills Energy L.P. | Enhanced turndown process for a bitumen froth treatment operation |
US11261383B2 (en) | 2011-05-18 | 2022-03-01 | Fort Hills Energy L.P. | Enhanced temperature control of bitumen froth treatment process |
WO2013025260A1 (en) * | 2011-06-01 | 2013-02-21 | Exxonmobil Upstream Research Company | Method of processing a bitumen stream using a membrane |
US9080441B2 (en) | 2011-11-04 | 2015-07-14 | Exxonmobil Upstream Research Company | Multiple electrical connections to optimize heating for in situ pyrolysis |
US20140238905A1 (en) * | 2011-11-08 | 2014-08-28 | James A. Dunn | Processing a hydrocarbon stream using supercritical water |
US9505989B2 (en) * | 2011-11-08 | 2016-11-29 | Exxonmobil Upstream Research Company | Processing a hydrocarbon stream using supercritical water |
US8770284B2 (en) | 2012-05-04 | 2014-07-08 | Exxonmobil Upstream Research Company | Systems and methods of detecting an intersection between a wellbore and a subterranean structure that includes a marker material |
WO2013180909A1 (en) * | 2012-05-29 | 2013-12-05 | Exxonmobil Upstream Research Company | Systems and methods for hydrotreating a shale oil stream using hydrogen gas that is concentrated from the shale oil stream |
US20150159092A1 (en) * | 2012-07-06 | 2015-06-11 | Statoil Canada Limited | Method and a system of recovering and processing a hydrocarbon mixture from a subterranean formation |
US10407621B2 (en) * | 2012-07-06 | 2019-09-10 | Statoil Canada Limited | Method and a system of recovering and processing a hydrocarbon mixture from a subterranean formation |
US9512699B2 (en) | 2013-10-22 | 2016-12-06 | Exxonmobil Upstream Research Company | Systems and methods for regulating an in situ pyrolysis process |
US9394772B2 (en) | 2013-11-07 | 2016-07-19 | Exxonmobil Upstream Research Company | Systems and methods for in situ resistive heating of organic matter in a subterranean formation |
US9739122B2 (en) | 2014-11-21 | 2017-08-22 | Exxonmobil Upstream Research Company | Mitigating the effects of subsurface shunts during bulk heating of a subsurface formation |
US9644466B2 (en) | 2014-11-21 | 2017-05-09 | Exxonmobil Upstream Research Company | Method of recovering hydrocarbons within a subsurface formation using electric current |
US11142681B2 (en) | 2017-06-29 | 2021-10-12 | Exxonmobil Upstream Research Company | Chasing solvent for enhanced recovery processes |
US10487636B2 (en) | 2017-07-27 | 2019-11-26 | Exxonmobil Upstream Research Company | Enhanced methods for recovering viscous hydrocarbons from a subterranean formation as a follow-up to thermal recovery processes |
US11002123B2 (en) | 2017-08-31 | 2021-05-11 | Exxonmobil Upstream Research Company | Thermal recovery methods for recovering viscous hydrocarbons from a subterranean formation |
US11261725B2 (en) | 2017-10-24 | 2022-03-01 | Exxonmobil Upstream Research Company | Systems and methods for estimating and controlling liquid level using periodic shut-ins |
Also Published As
Publication number | Publication date |
---|---|
CA2610463A1 (en) | 2009-05-09 |
WO2009061552A1 (en) | 2009-05-14 |
CA2610463C (en) | 2012-04-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA2610463C (en) | Integration of an in-situ recovery operation with a mining operation | |
CA2610230C (en) | Water integration between an in-situ recovery operation and a bitumen mining operation | |
US9097110B2 (en) | Viscous oil recovery using a fluctuating electric power source and a fired heater | |
CA2621991C (en) | Method and system for generating steam in the oil industry | |
CA2651155C (en) | Upgrading bitumen in a paraffinic froth treatment process | |
US7628204B2 (en) | Wastewater disposal with in situ steam production | |
US20120000642A1 (en) | Steam driven direct contact steam generation | |
US20100282593A1 (en) | Recovery of high water from produced water arising from a thermal hydrocarbon recovery operation using vaccum technologies | |
JP2011084676A (en) | Oil-water separator, oil-water separating system, oil-water separating method, and water reusing method using oil-water separating method | |
CA2741916C (en) | Integration of viscous oil recovery processes | |
CN104619947A (en) | In situ upgrading via hot fluid injection | |
US10913903B2 (en) | System and method for using a flash evaporator to separate bitumen and hydrocarbon condensate | |
CA2746987A1 (en) | Treatment of bitumen froth with super critical water | |
US9475994B2 (en) | Enhancing fine capture in paraffinic froth treatment process | |
US9505989B2 (en) | Processing a hydrocarbon stream using supercritical water | |
US10280102B1 (en) | Methods to properly condition feed water for steam generators in oil-fields and the like | |
Neff et al. | Environmental challenges of heavy crude oils: Management of liquid wastes | |
US10161624B2 (en) | Steam diluent generator | |
US20190017359A1 (en) | Improvements in in situ upgrading via hot fluid injection | |
CA3057120C (en) | System and method for shortened-path processing of produced fluids and steam generation | |
CA2956736A1 (en) | Processes for treating reservoir fluid comprising material produced from a hydrocarbon containing reservoir | |
CA2870798C (en) | Processes for treating reservoir fluid comprising material produced from a hydrocarbon containing reservoir | |
KR20230100869A (en) | Oil sand production system and production method using the same | |
CA2962997A1 (en) | Enthalpy recovery from tailings | |
Murthy Nadella | Improving Energy Efficiency in Thermal Oil Recovery Surface Facilities |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: EXXONMOBIL UPSTREAM RESEARCH COMPANY, TEXAS Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:IMPERIAL OIL RESOURCES LIMITED;REEL/FRAME:026391/0771 Effective date: 20080310 Owner name: IMPERIAL OIL RESOURCES LIMITED, CANADA Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:DUNN, JAMES A.;SPEIRS, BRIAN C.;REEL/FRAME:026391/0989 Effective date: 20080108 Owner name: IMPERIAL OIL RESOURCES LIMITED, CANADA Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:DUNN, JAMES A.;SPEIRS, BRIAN C.;REEL/FRAME:026391/0753 Effective date: 20080108 |
|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |