Arun C Mohan
MBA IFM
ALANDUR IN CONTEXT
Located 14 km south of Chennai, Alandur is part of the Kanchipuram district of Tamil
Nadu and forms a part of the Chennai Metropolitan Development Area (CMDA). The
town has developed as a residential suburb of Chennai with a population of 160,000
(Census 2004) of which approximately one-fourth lives in slums.
Rapid urbanization during 1980s and „90s at the peripheral vicinity of Chennai resulted in
the creation of this satellite town. It is given the status of Selection Grade
Municipality.
Prior to the project, Alandur had no sewerage system and wastewater from the majority of
its residents was collected either in septic tanks or holding tanks. The sewerage was
collected periodically in tankers and disposed of in low-lying areas outside the
municipal limits. The clearance of septic tanks was irregular due to lack of sufficient
vehicles and staff in the public health department.
In 1997, the Government of Tamil Nadu decided to provide a sewerage system in 12
selected major urban centers, including Alandur, in the context of a World Bank
funded project. The Chairperson of the Municipality, Mr. R. S. Bharati took up the task
of implementing the project in Alandur.
OBJECTIVES OF ALANDUR SEWERAGE PROJECT
To improve the standard of living of the residents of Alandur on par with that of
Chennai
To provide the most essential basic facility to all the residents of the town
To eradicate the mosquito menace
To avoid the recurring expenditure on septic tank cleaning
To avoid ground water contamination
The proposed sewerage system was to be designed for the estimated population of
about 300,000 by 2027
It was planned to be completed within a five-year period from its inception date.
ASP COMPONENTS
A sewerage network consisting of the main sewer line, branch sewer line and
manholes
Construction of a sewage pumping station
A sewage treatment plant
Low cost sanitation
PROJECT IMPLEMENTATION PROCESS
Tamil Nadu Urban Infrastructure Finance Services Ltd. (TNUIFSL) was nominated as
the agency to coordinate, supervise and structure the finances for the project,
was also responsible for detailed studies on the feasibility of the project.
Lack of resources in Municipal level resulted in TNUIFSL & the Municipal
Administration of Alandur to construct the underground sewerage system on
BOQ basis, and the sewerage treatment plant (STP) on a BOT basis.
Besides the construction responsibility, the contractor was also required to
undertake the O&M of the sewerage system for a period of 5yrs from the date of
completion of the construction, on a fixed fee basis. Collection of tariff and
provision of new connections during the O&M phase was to be undertaken by
the municipality directly.
PROJECT PROCUREMENT
The project was structured such that an EPC contractor, selected through
competitive bidding process, would design and implement the sewerage system,
on turnkey works contract, and would also finance, design, build, and operate
the STP on BOT (Annuity) basis.
The procurement of private contractor for the execution of the project was carried
out as per the standards prescribed by the World Bank. A two stage bid process
was adopted - a technical proposal followed by a financial proposal.
The technical capabilities of the contractors and their experience in similar works
were given importance. Of the 13 entities who submitted the bids, three were
short-listed, and the financial proposals were received from such technically
qualified firms.
As per the financial evaluation criteria, the bidder quoting the lowest cost for the
sewerage system and lowest lease period for the STP was selected as the final,
successful contractor.
PPP STRUCTURE OF THE PROJECT
A Works Contract for construction of the sewage network, using the World Bank‟s
contract for National Competitive Bidding (NCB-W2) as the template
An O&M Contract, also using NCB-W2. The selected contractor would operate and
maintain the underground sewerage system for a period of 5yrs on a fixed fee
basis
A Lease Contract (in the nature of a BOT Agreement) for the STP, using guidelines
from FIDIC. Through this Agreement, the contractor would finance, build and
operate the STP for a period as proposed in the contractor‟s successful bid. The
contractor would be require to recover the investment o the STP on the basis of
a per unit rate payment from the municipality for treatment of sewage delivered.
The municipality agreed to provide a minimum payment level per annum
regardless of the volume of sewage actually delivered. It was designed to cover
the company‟s minimum fixed operating cost and capital investment.
FOLLOWING THE BID
Project awarded to IVRCL Infrastructures and Projects Ltd in technical collaboration
with “Va Tech Wabag Technologies Ltd.” A SPV called „First Sewerage Treatment
Plant Pvt. Ltd‟ (First STP) was incorporated and was the concessionaire company
with whom the BOT Agreement was signed 2 March 2000.
IVRCL was to carry out the civil works for the project
Va Tech Wabag, through the electro mechanical contract, was to design the process,
supply, install and commission the equipment.
Va Tech Wabag was also to carry out a contract for O&M the facility for 14 years.
The land on which the plant was set up was leased by the municipality to First STP.
IMPLEMENTATION
As per the Agreement, the expected date of completion was 31st March, 2005.
In order to ensure timely implementation of the project and adherence to quality
specifications, Consulting Engineering Services Limited (CESL) was appointed as
Project Management Consultants for the detailed supervision and quality
control.
Along with the consultants, the Chairman, Commissioner and Engineer of the AM
reviewed the progress of the project on a weekly basis.
The Commissioner of Municipal Administration, GoTN, the Secretary of the
Municipal Administration & Water Supply and the Chief Executive of TNUIFSL
also reviewed the progress of the project every month, and provided
administrative support for acquiring the necessary clearances from agencies
such as the railways, highway authority, PWD, etc.
DELIVERY
The project work was carried out in two phases.
In the first phase (the first two and a half years), 50% of the branch sewers, main
sewers, pump house including installation of machinery, pumping main and one
12 MLD capacity sewage treatment plant, were completed and commissioned.
The remaining work relating to the project was to be carried out in the next phase.
By end 2001, the laying of the sewer pipes and main sewers was completed, as also
the construction of the Pumping Station, Pumping Mains and Sewerage
Treatment Plant.
The overall date of completion was October 2003.
FINANCING INFORMATION
Initially, the cost of the project was estimated to be INR 45.31 crore, which was later
revised to INR 40.86 crore.
A unique aspect of the project funding was the initiative of bringing in people‟s
money to fund public infrastructure by generating public awareness and interest
right from inception.
PUBLIC CONTRIBUTION
To reduce the repayment burden on the local body, it was decided to collect deposits
from at least 10000 residents before calling tenders to ensure effective public
participation in the project
On the basis of a financial analysis of the project, the AM decided to collect one-time
deposits in the form of connection charges from the citizens of Alandur.
The connection charges for different categories of users were fixed as follows:
Sewer maintenance charges at various rates which were proposed to be increased
to 6% annually till they reach a level
Type
of Property
One – Time Deposit
(Rs per unit/HH)
Monthy Tariff
(Rs per unit/HH)
Residential 5,000 150
Commercial 10,000 450
Industrial 10,000 750
ASP FEATURES
The greatest challenge (as well as accomplishment) of the ASP, was that both the
municipality and the public recognized and accepted the „value‟ of bringing in
private participation.
This project truly demonstrates the benefits of bringing in PPP in the municipal
sector in terms of drawing private sector expertise while addressing important
risk related aspect that would make the project attractive for the private sector.
KEY LEARNING AND OBSERVATIONS FROM ASP
Beneficiary participatory approach
Stakeholder involvement and interdepartmental coordination
Political will and strong decision making, especially at the grass-root level
Acceptance of fiscal discipline
Commitment towards project prior to implementation
Implementing an effective fee system
Technical and financial assistance
Transparency in bidding and contracting procedures
IMPACTS OF THE PROJECT
Nearly 500 slum dwellers of the 7,000 had a sewerage connection and 43 percent
of slum dwellers have opted and paid for individual sewerage connections.
In 2005, 14 community toilets were constructed to serve poor clusters.
By end of March 2008 – all households have received sewerage connections
Alandur sewerage project is an innovative attempt for sustainable delivery of urban
services in the country and many municipalities (Trichy, Tanjavur, Tirunelveli,
Ambattur, etc.) had started adopting similar efforts for underground drainage
The initiative was awarded the National Urban Water Award in 2008.
Alandur sewerage proj   arun

More Related Content

What's hot

National Urban Transport Policy
National Urban Transport PolicyNational Urban Transport Policy
National Urban Transport Policy
Ashu Kedia
 
Revised Developement Plan, Ahmedabad 2013 - 2021
Revised Developement Plan, Ahmedabad 2013 - 2021Revised Developement Plan, Ahmedabad 2013 - 2021
Revised Developement Plan, Ahmedabad 2013 - 2021
Manaan Choksi
 
Analysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land UseAnalysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land Use
Anirban Mahajan
 
Thesis - Urban Infrastructure Development
Thesis - Urban Infrastructure DevelopmentThesis - Urban Infrastructure Development
Thesis - Urban Infrastructure Development
Rakesh Sasapu
 

What's hot (20)

National Urban Transport Policy
National Urban Transport PolicyNational Urban Transport Policy
National Urban Transport Policy
 
Jnnurm
JnnurmJnnurm
Jnnurm
 
Gender inclusive planning
Gender inclusive planningGender inclusive planning
Gender inclusive planning
 
URBAN GOVERNANCE OF CHENNAI
URBAN GOVERNANCE OF CHENNAIURBAN GOVERNANCE OF CHENNAI
URBAN GOVERNANCE OF CHENNAI
 
Pedestrian and Bicycle facility planning for kochi city region,part 1 study ...
Pedestrian and Bicycle facility planning for kochi city region,part 1  study ...Pedestrian and Bicycle facility planning for kochi city region,part 1  study ...
Pedestrian and Bicycle facility planning for kochi city region,part 1 study ...
 
Revised Developement Plan, Ahmedabad 2013 - 2021
Revised Developement Plan, Ahmedabad 2013 - 2021Revised Developement Plan, Ahmedabad 2013 - 2021
Revised Developement Plan, Ahmedabad 2013 - 2021
 
TRANSIT ORIENTED DEVELOPMENT (TOD)
TRANSIT ORIENTED DEVELOPMENT (TOD)TRANSIT ORIENTED DEVELOPMENT (TOD)
TRANSIT ORIENTED DEVELOPMENT (TOD)
 
BRT System in Delhi
BRT System in DelhiBRT System in Delhi
BRT System in Delhi
 
Town planning schemes
Town planning schemesTown planning schemes
Town planning schemes
 
Street design guidelines feb2011-PPT
Street design guidelines feb2011-PPTStreet design guidelines feb2011-PPT
Street design guidelines feb2011-PPT
 
TRANSIT ORIENTED DEVELOPMENT
TRANSIT ORIENTED DEVELOPMENTTRANSIT ORIENTED DEVELOPMENT
TRANSIT ORIENTED DEVELOPMENT
 
impact of MRTS on Landuse in Patna
impact of MRTS on Landuse in Patnaimpact of MRTS on Landuse in Patna
impact of MRTS on Landuse in Patna
 
Webinar on Town planning scheme
Webinar on Town planning schemeWebinar on Town planning scheme
Webinar on Town planning scheme
 
Analysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land UseAnalysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land Use
 
Area Appreciation Studio - 2021 - SPAD M.Plan
Area Appreciation Studio - 2021 - SPAD M.PlanArea Appreciation Studio - 2021 - SPAD M.Plan
Area Appreciation Studio - 2021 - SPAD M.Plan
 
Regional plan 2021 ncr
Regional plan 2021 ncrRegional plan 2021 ncr
Regional plan 2021 ncr
 
Transit Oriented Development.
Transit Oriented Development.Transit Oriented Development.
Transit Oriented Development.
 
Amrut ppt
Amrut pptAmrut ppt
Amrut ppt
 
Draft Proposal of Town Planning Scheme
Draft Proposal of Town Planning SchemeDraft Proposal of Town Planning Scheme
Draft Proposal of Town Planning Scheme
 
Thesis - Urban Infrastructure Development
Thesis - Urban Infrastructure DevelopmentThesis - Urban Infrastructure Development
Thesis - Urban Infrastructure Development
 

Viewers also liked

Case studies ppp
Case studies pppCase studies ppp
Case studies ppp
amityasum23
 
Construction Activities and Process
Construction Activities and ProcessConstruction Activities and Process
Construction Activities and Process
J.j. Hayashi
 

Viewers also liked (11)

Case studies ppp
Case studies pppCase studies ppp
Case studies ppp
 
Dreamcity Amritsar
Dreamcity AmritsarDreamcity Amritsar
Dreamcity Amritsar
 
Trishul presentation 2012
Trishul presentation 2012Trishul presentation 2012
Trishul presentation 2012
 
Top 10 billing engineer interview questions and answers
Top 10 billing engineer interview questions and answersTop 10 billing engineer interview questions and answers
Top 10 billing engineer interview questions and answers
 
Real estate industry presentation
Real estate industry presentationReal estate industry presentation
Real estate industry presentation
 
River Pollution In India
River Pollution In IndiaRiver Pollution In India
River Pollution In India
 
Construction Activities and Process
Construction Activities and ProcessConstruction Activities and Process
Construction Activities and Process
 
Enron presentation
Enron presentationEnron presentation
Enron presentation
 
Enron scandal
Enron scandalEnron scandal
Enron scandal
 
SEWAGE TREATMENT PLANT,LUCKNOW
SEWAGE TREATMENT PLANT,LUCKNOWSEWAGE TREATMENT PLANT,LUCKNOW
SEWAGE TREATMENT PLANT,LUCKNOW
 
ENRON PPT
ENRON PPTENRON PPT
ENRON PPT
 

Similar to Alandur sewerage proj arun

Amritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrix
Amritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrixAmritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrix
Amritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrix
NISHCHAY SAXENA
 
NEC-newsletter-70
NEC-newsletter-70NEC-newsletter-70
NEC-newsletter-70
sam hyde
 
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAYSTUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
Shabaz Khan
 

Similar to Alandur sewerage proj arun (20)

Compendium of ppp_cases_mou_ds
Compendium of ppp_cases_mou_dsCompendium of ppp_cases_mou_ds
Compendium of ppp_cases_mou_ds
 
Ppp
PppPpp
Ppp
 
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
 
Ppp
PppPpp
Ppp
 
exp_sewage.pptx
exp_sewage.pptxexp_sewage.pptx
exp_sewage.pptx
 
Padma Brige Project 2017
Padma Brige Project 2017Padma Brige Project 2017
Padma Brige Project 2017
 
АЗИЙН ХӨГЖЛИЙН БАНКТАЙ ХАМТРАН ХЭРЭГЖҮҮЛЖ БУЙ ТӨСӨЛ 01
АЗИЙН ХӨГЖЛИЙН БАНКТАЙ ХАМТРАН ХЭРЭГЖҮҮЛЖ БУЙ ТӨСӨЛ 01АЗИЙН ХӨГЖЛИЙН БАНКТАЙ ХАМТРАН ХЭРЭГЖҮҮЛЖ БУЙ ТӨСӨЛ 01
АЗИЙН ХӨГЖЛИЙН БАНКТАЙ ХАМТРАН ХЭРЭГЖҮҮЛЖ БУЙ ТӨСӨЛ 01
 
2cmc to r for sewarage system design
2cmc to r for sewarage system design 2cmc to r for sewarage system design
2cmc to r for sewarage system design
 
Chapter19 financinginfrastructureprojects
Chapter19 financinginfrastructureprojectsChapter19 financinginfrastructureprojects
Chapter19 financinginfrastructureprojects
 
Amritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrix
Amritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrixAmritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrix
Amritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrix
 
NEC-newsletter-70
NEC-newsletter-70NEC-newsletter-70
NEC-newsletter-70
 
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAYSTUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
 
Boot model
Boot modelBoot model
Boot model
 
What do you understand by Infrastructure Planning Explain the role of Infrast...
What do you understand by Infrastructure Planning Explain the role of Infrast...What do you understand by Infrastructure Planning Explain the role of Infrast...
What do you understand by Infrastructure Planning Explain the role of Infrast...
 
Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...
Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...
Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...
 
Development projects of neepal
Development projects of neepalDevelopment projects of neepal
Development projects of neepal
 
Built operate transfer case studies in local construction Sector in Pakistan
Built operate transfer case studies in local construction Sector in PakistanBuilt operate transfer case studies in local construction Sector in Pakistan
Built operate transfer case studies in local construction Sector in Pakistan
 
Delhi Metro Rail
Delhi Metro RailDelhi Metro Rail
Delhi Metro Rail
 
Final report eia (kmc)
Final report   eia (kmc)Final report   eia (kmc)
Final report eia (kmc)
 
PM Project group 4.pptx
PM Project group 4.pptxPM Project group 4.pptx
PM Project group 4.pptx
 

More from Kartikeya Pandey

More from Kartikeya Pandey (20)

Water and sanitation
Water and sanitationWater and sanitation
Water and sanitation
 
oil & gas drilling preliminaries
oil & gas drilling preliminariesoil & gas drilling preliminaries
oil & gas drilling preliminaries
 
Supplementary benefits
Supplementary benefitsSupplementary benefits
Supplementary benefits
 
Property tax
Property taxProperty tax
Property tax
 
Metros summary by Kartikeya Pandey
Metros summary by Kartikeya PandeyMetros summary by Kartikeya Pandey
Metros summary by Kartikeya Pandey
 
Marketing product placement strategies
Marketing product placement strategiesMarketing product placement strategies
Marketing product placement strategies
 
seven cs
seven csseven cs
seven cs
 
Indian ports (1)
Indian ports (1)Indian ports (1)
Indian ports (1)
 
Human resource planning ppt.
Human resource planning ppt.Human resource planning ppt.
Human resource planning ppt.
 
Gis
GisGis
Gis
 
Fire d project
Fire d projectFire d project
Fire d project
 
24 x7 water in three states of karnataka
24 x7 water in three states of karnataka24 x7 water in three states of karnataka
24 x7 water in three states of karnataka
 
4
44
4
 
Land adjustment Land value capture
Land adjustment Land value captureLand adjustment Land value capture
Land adjustment Land value capture
 
Solid waste management practices in dehradun under jn nurm
Solid waste management practices in dehradun under jn nurmSolid waste management practices in dehradun under jn nurm
Solid waste management practices in dehradun under jn nurm
 
Infrastructure unbundling in south africa
Infrastructure unbundling in south africaInfrastructure unbundling in south africa
Infrastructure unbundling in south africa
 
Indian accounting standard (ind as) 27
Indian accounting standard (ind as) 27Indian accounting standard (ind as) 27
Indian accounting standard (ind as) 27
 
Hr presentation
Hr presentationHr presentation
Hr presentation
 
Going & seeing in construction
Going & seeing in constructionGoing & seeing in construction
Going & seeing in construction
 
Concrete technology
Concrete technologyConcrete technology
Concrete technology
 

Recently uploaded

Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 

Recently uploaded (20)

DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
 
ADP Passwordless Journey Case Study.pptx
ADP Passwordless Journey Case Study.pptxADP Passwordless Journey Case Study.pptx
ADP Passwordless Journey Case Study.pptx
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Stronger Together: Developing an Organizational Strategy for Accessible Desig...
Stronger Together: Developing an Organizational Strategy for Accessible Desig...Stronger Together: Developing an Organizational Strategy for Accessible Desig...
Stronger Together: Developing an Organizational Strategy for Accessible Desig...
 
الأمن السيبراني - ما لا يسع للمستخدم جهله
الأمن السيبراني - ما لا يسع للمستخدم جهلهالأمن السيبراني - ما لا يسع للمستخدم جهله
الأمن السيبراني - ما لا يسع للمستخدم جهله
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Simplifying Mobile A11y Presentation.pptx
Simplifying Mobile A11y Presentation.pptxSimplifying Mobile A11y Presentation.pptx
Simplifying Mobile A11y Presentation.pptx
 
Navigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern EnterpriseNavigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern Enterprise
 
Modernizing Legacy Systems Using Ballerina
Modernizing Legacy Systems Using BallerinaModernizing Legacy Systems Using Ballerina
Modernizing Legacy Systems Using Ballerina
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
JohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptx
 
Intro to Passkeys and the State of Passwordless.pptx
Intro to Passkeys and the State of Passwordless.pptxIntro to Passkeys and the State of Passwordless.pptx
Intro to Passkeys and the State of Passwordless.pptx
 
JavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate GuideJavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate Guide
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 
UiPath manufacturing technology benefits and AI overview
UiPath manufacturing technology benefits and AI overviewUiPath manufacturing technology benefits and AI overview
UiPath manufacturing technology benefits and AI overview
 
API Governance and Monetization - The evolution of API governance
API Governance and Monetization -  The evolution of API governanceAPI Governance and Monetization -  The evolution of API governance
API Governance and Monetization - The evolution of API governance
 

Alandur sewerage proj arun

  • 2. ALANDUR IN CONTEXT Located 14 km south of Chennai, Alandur is part of the Kanchipuram district of Tamil Nadu and forms a part of the Chennai Metropolitan Development Area (CMDA). The town has developed as a residential suburb of Chennai with a population of 160,000 (Census 2004) of which approximately one-fourth lives in slums. Rapid urbanization during 1980s and „90s at the peripheral vicinity of Chennai resulted in the creation of this satellite town. It is given the status of Selection Grade Municipality. Prior to the project, Alandur had no sewerage system and wastewater from the majority of its residents was collected either in septic tanks or holding tanks. The sewerage was collected periodically in tankers and disposed of in low-lying areas outside the municipal limits. The clearance of septic tanks was irregular due to lack of sufficient vehicles and staff in the public health department. In 1997, the Government of Tamil Nadu decided to provide a sewerage system in 12 selected major urban centers, including Alandur, in the context of a World Bank funded project. The Chairperson of the Municipality, Mr. R. S. Bharati took up the task of implementing the project in Alandur.
  • 3. OBJECTIVES OF ALANDUR SEWERAGE PROJECT To improve the standard of living of the residents of Alandur on par with that of Chennai To provide the most essential basic facility to all the residents of the town To eradicate the mosquito menace To avoid the recurring expenditure on septic tank cleaning To avoid ground water contamination The proposed sewerage system was to be designed for the estimated population of about 300,000 by 2027 It was planned to be completed within a five-year period from its inception date.
  • 4. ASP COMPONENTS A sewerage network consisting of the main sewer line, branch sewer line and manholes Construction of a sewage pumping station A sewage treatment plant Low cost sanitation
  • 5. PROJECT IMPLEMENTATION PROCESS Tamil Nadu Urban Infrastructure Finance Services Ltd. (TNUIFSL) was nominated as the agency to coordinate, supervise and structure the finances for the project, was also responsible for detailed studies on the feasibility of the project. Lack of resources in Municipal level resulted in TNUIFSL & the Municipal Administration of Alandur to construct the underground sewerage system on BOQ basis, and the sewerage treatment plant (STP) on a BOT basis. Besides the construction responsibility, the contractor was also required to undertake the O&M of the sewerage system for a period of 5yrs from the date of completion of the construction, on a fixed fee basis. Collection of tariff and provision of new connections during the O&M phase was to be undertaken by the municipality directly.
  • 6. PROJECT PROCUREMENT The project was structured such that an EPC contractor, selected through competitive bidding process, would design and implement the sewerage system, on turnkey works contract, and would also finance, design, build, and operate the STP on BOT (Annuity) basis. The procurement of private contractor for the execution of the project was carried out as per the standards prescribed by the World Bank. A two stage bid process was adopted - a technical proposal followed by a financial proposal. The technical capabilities of the contractors and their experience in similar works were given importance. Of the 13 entities who submitted the bids, three were short-listed, and the financial proposals were received from such technically qualified firms. As per the financial evaluation criteria, the bidder quoting the lowest cost for the sewerage system and lowest lease period for the STP was selected as the final, successful contractor.
  • 7. PPP STRUCTURE OF THE PROJECT A Works Contract for construction of the sewage network, using the World Bank‟s contract for National Competitive Bidding (NCB-W2) as the template An O&M Contract, also using NCB-W2. The selected contractor would operate and maintain the underground sewerage system for a period of 5yrs on a fixed fee basis A Lease Contract (in the nature of a BOT Agreement) for the STP, using guidelines from FIDIC. Through this Agreement, the contractor would finance, build and operate the STP for a period as proposed in the contractor‟s successful bid. The contractor would be require to recover the investment o the STP on the basis of a per unit rate payment from the municipality for treatment of sewage delivered. The municipality agreed to provide a minimum payment level per annum regardless of the volume of sewage actually delivered. It was designed to cover the company‟s minimum fixed operating cost and capital investment.
  • 8. FOLLOWING THE BID Project awarded to IVRCL Infrastructures and Projects Ltd in technical collaboration with “Va Tech Wabag Technologies Ltd.” A SPV called „First Sewerage Treatment Plant Pvt. Ltd‟ (First STP) was incorporated and was the concessionaire company with whom the BOT Agreement was signed 2 March 2000. IVRCL was to carry out the civil works for the project Va Tech Wabag, through the electro mechanical contract, was to design the process, supply, install and commission the equipment. Va Tech Wabag was also to carry out a contract for O&M the facility for 14 years. The land on which the plant was set up was leased by the municipality to First STP.
  • 9. IMPLEMENTATION As per the Agreement, the expected date of completion was 31st March, 2005. In order to ensure timely implementation of the project and adherence to quality specifications, Consulting Engineering Services Limited (CESL) was appointed as Project Management Consultants for the detailed supervision and quality control. Along with the consultants, the Chairman, Commissioner and Engineer of the AM reviewed the progress of the project on a weekly basis. The Commissioner of Municipal Administration, GoTN, the Secretary of the Municipal Administration & Water Supply and the Chief Executive of TNUIFSL also reviewed the progress of the project every month, and provided administrative support for acquiring the necessary clearances from agencies such as the railways, highway authority, PWD, etc.
  • 10. DELIVERY The project work was carried out in two phases. In the first phase (the first two and a half years), 50% of the branch sewers, main sewers, pump house including installation of machinery, pumping main and one 12 MLD capacity sewage treatment plant, were completed and commissioned. The remaining work relating to the project was to be carried out in the next phase. By end 2001, the laying of the sewer pipes and main sewers was completed, as also the construction of the Pumping Station, Pumping Mains and Sewerage Treatment Plant. The overall date of completion was October 2003.
  • 11. FINANCING INFORMATION Initially, the cost of the project was estimated to be INR 45.31 crore, which was later revised to INR 40.86 crore. A unique aspect of the project funding was the initiative of bringing in people‟s money to fund public infrastructure by generating public awareness and interest right from inception.
  • 12.
  • 13. PUBLIC CONTRIBUTION To reduce the repayment burden on the local body, it was decided to collect deposits from at least 10000 residents before calling tenders to ensure effective public participation in the project On the basis of a financial analysis of the project, the AM decided to collect one-time deposits in the form of connection charges from the citizens of Alandur. The connection charges for different categories of users were fixed as follows: Sewer maintenance charges at various rates which were proposed to be increased to 6% annually till they reach a level Type of Property One – Time Deposit (Rs per unit/HH) Monthy Tariff (Rs per unit/HH) Residential 5,000 150 Commercial 10,000 450 Industrial 10,000 750
  • 14. ASP FEATURES The greatest challenge (as well as accomplishment) of the ASP, was that both the municipality and the public recognized and accepted the „value‟ of bringing in private participation. This project truly demonstrates the benefits of bringing in PPP in the municipal sector in terms of drawing private sector expertise while addressing important risk related aspect that would make the project attractive for the private sector.
  • 15. KEY LEARNING AND OBSERVATIONS FROM ASP Beneficiary participatory approach Stakeholder involvement and interdepartmental coordination Political will and strong decision making, especially at the grass-root level Acceptance of fiscal discipline Commitment towards project prior to implementation Implementing an effective fee system Technical and financial assistance Transparency in bidding and contracting procedures
  • 16. IMPACTS OF THE PROJECT Nearly 500 slum dwellers of the 7,000 had a sewerage connection and 43 percent of slum dwellers have opted and paid for individual sewerage connections. In 2005, 14 community toilets were constructed to serve poor clusters. By end of March 2008 – all households have received sewerage connections Alandur sewerage project is an innovative attempt for sustainable delivery of urban services in the country and many municipalities (Trichy, Tanjavur, Tirunelveli, Ambattur, etc.) had started adopting similar efforts for underground drainage The initiative was awarded the National Urban Water Award in 2008.

Editor's Notes

  1. (TNUIFSL), the state asset management company
  2. 1. 29% of the project cost was garnered from public 2. citizen’s committee was formed and it met frequently to review the status of the project, monitor performance of the BOT contractor and provide a forum in which citizens could air their concerns.4. TNUIFSL and TUFIDCO, placed strict lending conditions on the municipality, requiring the municipality to accept and implement strong fiscal discipline measures